Docket Log

Docket: 01-AFC-19C
Project Title: SMUD Cosumnes Power Plant - Compliance
Generated On: 8/3/2020 3:08:06 AM

Include:     
TN #Docketed DateDocument TitleExhibit #ToFrom
2338097/8/2020 STATEMENT OF STAFF APPROVAL OF PROPOSED CHANGE

3 page(s)
 CEC/Docket UnitCalifornia Energy Commission
2334446/8/2020 Information Request Form

1 page(s)
 CEC/Docket UnitCalifornia Energy Commission
2330835/22/2020 Cosumnes Power Plant - AQ-10 Correction
Memo to Commission to correct Condition of Certification AQ-10.
Compliance
2 page(s)
 CEC/DocketsCalifornia Energy Commission
23111812/11/2019 SMUD Cosumnes Power Plant - 2018 Annual Compliance Report
2018 Annual Compliance Report for the SMUD Cosumnes Power Plant.
Compliance
49 page(s)
 CEC/Mary DyasEthosEnergy
2262321/7/2019 Cosumnes Power Plant Petition to Amend Notice of Decision
Notice of Decision for the Cosumnes Power Plant petition to amend to operate previously installed Advanced Gas Path upgrades.
Compliance
1 page(s)
 CEC/DocketsCalifornia Energy Commission
2262311/7/2019 Cosumnes Power Plant Order Approving Petition to Amend
Cosumnes Power Plant Order Approving Petition to Amend to Operate previously installed Advanced Gas Path upgrades.
Compliance
3 page(s)
  California Energy Commission
22604212/7/2018 Steve Uhler Comments Dear Energy Commission Commissioners, in terms of trying to do it right

Executive Summary
2 page(s)
 CEC/Docket UnitSteve Uhler
22603412/6/2018 Cosumnes Power Plant - Petition to Amend - Staff Response to Non-Agency Comments

14 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22599612/3/2018 SFA's Comments on the the Staff Assessment

Air Quality
4 page(s)
 Ms. Mary DyasJacobs/SFA
22596311/27/2018 Steve Uhler Comments Dear Energy Commission Commissioners, Please confirm the capacity of SMUD's Hedge Power Plant

Air Quality, Facility Design, Compliance, Reliability, Transmission System Engineering, Greenhouse Gases
5 page(s)
 CEC/DocketsSteve Uhler
22595511/26/2018 Steve Uhler Comments Dear Energy Commission Commissioners, Tell me about SMUD's natural gas health, safety, and environmental guidelines

Air Quality, Facility Design, Compliance, Hazardous Materials, Public Health, Worker Safety and Fire Protection, Waste Management, Greenhouse Gases
47 page(s)
 CEC/DocketsSteve Uhler
22595411/26/2018 Steve Uhler Comments Dear Energy Commission Commissioners, tell me about staff's training and private agreements with SMUD

Air Quality, Compliance, Hazardous Materials, Public Health, Reliability, Worker Safety and Fire Protection, Waste Management
3 page(s)
 CEC/DocketsSteve Uhler
22586311/8/2018 Cosumnes Power Plant - Petition to Amend - AGP Upgrades - Staff Analysis
Staff Analysis of the Cosumnes Power Plant AGP Upgrades Petition to Amend.
87 page(s)
 Interested PartiesCalifornia Energy Commission
22583911/7/2018 Cosumnes Power Plant - Petition to Amend - Email - Air Quality Questions and Responses

4 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22583111/6/2018 SFA Response to Public Comments

Facility Design, Hazardous Materials, Land Use, Public Health
37 page(s)
 CEC/Mary DyasJacobs
22580011/5/2018 Steve Uhler Comments Energy Commission please verify SFA statements in TN225760

Air Quality, Compliance, Hazardous Materials, Public Health, Greenhouse Gases
3 page(s)
 CEC/DocketsSteve Uhler
22576011/2/2018 SFA Response to Steve Uhler Comments

Air Quality, Efficiency, Public Health
5 page(s)
 CEC/DocketsCH2M HILL
22557210/30/2018 Compliance Docketing Policy

3 page(s)
 Plant ManagerCalifornia Energy Commission
22507510/24/2018 Cosumnes Power Plant - Petition to Amend - Comments
Comments from Herald Fire Protection District regarding AGP Upgrades Petition to Amend
8 page(s)
 CEC/Docket UnitHerald Fire Protection District
22498310/15/2018 Steve Uhler Comments CPP Heat Rate

Compliance, Reliability, Efficiency
1 page(s)
 CEC/Docket UnitSteve Uhler
22498010/13/2018 Steve Uhler Comments CPP Fuel content

Compliance, Hazardous Materials, Public Health, Reliability, Soil and Water, Air Quality, Facility Design
1 page(s)
 CEC/Docket UnitSteve Uhler
22494810/11/2018 Steve Uhler Comments CPP PTA TOD Timer adoption modeling

Reliability
2 page(s)
 CEC/DocketsSteve Uhler
22494710/11/2018 Steve Uhler Comments CPP PTA LORS (210)Pb

Air Quality, Compliance, Hazardous Materials
1 page(s)
 CEC/DocketsSteve Uhler
22494610/11/2018 Steve Uhler Comments CPP PTA LORS SMAQMD BACT

1 page(s)
 CEC/DocketsSteve Uhler
22494510/11/2018 Steve Uhler Comments CPP PTA NERC Compliance errors in TN224837

Compliance, Reliability
1 page(s)
 CEC/DocketsSteve Uhler
22483710/1/2018 SFA Cosumnes Power Plant Supplemental PTA NERC Compliance Documentation

Facility Design
16 page(s)
 CEC/DocketsCH2M HILL
2246839/11/2018 Cosumnes Power Plant - Petition to Amend - AGP_Upgrades - Notice of Receipt
Notice of Receipt for the Cosumnes Power Plant Petition to Amend for Advanced Gas Path Upgrades
Compliance
3 page(s)
 CEC/DocketsCalifornia Energy Commission
2246258/29/2018 SFA Cosumnes Power Plant Petition to Amend
Petition to Amend to Increase Electrical Production
215 page(s)
 Lon PayneCH2M HILL
6293711/18/2011 Notice of Decision

1 page(s)
 California Resource AgencyCEC/ C. Stora
6284311/8/2011 Order Approving a Petition to Modify the Fuel Supply and Other Modifications

9 page(s)
 CEC/Docket UnitCEC/ C. Stora
617908/8/2011 Revised Staff Analysis of Proposed Modification Fuel Supply

24 page(s)
 Interested PartiesCEC/ C. Stora
614407/21/2011 Comments on Staff Analysis of Proposed Modifications

5 page(s)
 CEC/C.StoraSFA/R.Gould
611746/20/2011 Staff Analysis for Fuelo Supply Modifications

22 page(s)
 Interested PartiesCEC/ C. Stora
603794/25/2011 Petition for Post Certification License Amendment for Fuel Supply Modifications and Revision

64 page(s)
 CEC/C. StoraCH2MHILL
603174/22/2011 Application to Modify Air Permits for the Gas Turbines and Cooling Tower Application Numbers 22672 22673 and 22674

64 page(s)
 SMAQMD/ Venk ReddySacramento Municipal Utility District Financial Authority
601403/25/2011 Data Requests 1-11

5 page(s)
 CEC/ Docket UnitCEC/ C. Snow
594581/11/2011 Notice of Receipt Petition to Amend the Energy Commission Decision for the Cosumnes Power PLant Project

3 page(s)
 CEC/ Docket UnitCEC/ C. Marxen
5937112/29/2010 Cosumnes Power Plant Project Petition fro Post Certification License

213 page(s)
 CEC/ C. SnowCH2MHILL
576187/19/2010 Proposed Gate Reorientation Response Letter

5 page(s)
 Generation Design Power Generation/K. HudsonCEC/A. Juarez-Garcia
574557/6/2010 SMUD Cosumes Power Plant Proposed Gate Reorientation.

2 page(s)
 CEC/ Docket UnitSMUD/ K. Hudson
548011/14/2010 Letter to SMUD Scott Flake regarding Energy Commission Jurisdiction

1 page(s)
 SMUD/ S. FlakeCEC/ M. Jones
5463412/22/2009 Repeated Application for Confidential - Cultural Resources Monitoring Report

3 page(s)
 CEC/ M. JonesSMUD/ L. Jimenez-Price
520576/17/2009 Countersigned CBO MOU for ZLD & OnePass Filter Addition

7 page(s)
 CEC/ A. Juarez-GarciaSMUD/ K. Hudson
511974/20/2009 Request for Delegation of CBO Self Performance

1 page(s)
 CEC/ J. CaswellSMUD/ S. Flake
511204/16/2009 Approval of Modification to Upgrade the Zero Liquid Discharge System

1 page(s)
 SMUD/ L. Jimenez-PriceCEC/ A. Juarez-Garcia
507444/1/2009 Notice of Receipt

2 page(s)
 CEC/ Docket UnitCEC/ E. Allen
503423/2/2009 Kevin Hudson Hydrogen Usage Letter

2 page(s)
 CEC/ A. Juarez-GarciaSMUD Financing Authority/ Kevin Hudson
500482/10/2009 SFA's Petition for Post Certification Project Modification

47 page(s)
 CEC/ A. Juarez-GarciaSMUD/ Lourdes Jimenez-Price
4931612/9/2008 Response to the Condition of Certification HAZ-1 Requested Additions Letter

5 page(s)
 SMUC/ K. HudsonCEC/ A. Juarez-Garcia
4928312/8/2008 Response to the Condition of Certification HAZ-1 Requested Additions Letter

6 page(s)
 SMUD/ Kevin HudsonCEC/ A. Juarez-Garcia
4927912/5/2008 Condition of Certifcation HAZ-1: Requested Additions

5 page(s)
 CEC/ A. Juarez-GarciaSMUD/ K. Hudson
4875810/24/2008 Notification of CBO Delegate Designation

2 page(s)
 CEC/ A. Juarez-GarciaSMUD/ K. Hudson
480219/15/2008 Consumnes Power Plant Condition of Certification WATER RES-1

6 page(s)
 CEC/ A. Juarez-GarciaSFA/ B. Nelson
473677/28/2008 Repeated Application for Confidential Designation - Cultural Resources

150 page(s)
 CEC / M. JonesSMUD / L. Jimenez-Price
470987/9/2008 Repeated Application for Confidential Designation - Cultural Resources

131 page(s)
 CEC / M. JonesSMUD / L. Jimenez-Price
466976/13/2008 Notice of Decision RE: Modify condition of certification, as well as the project description relating to the coolign tower.

1 page(s)
 CEC / Docket UnitCEC / R. Yasny
466326/9/2008 Application for Confidential Designation - Cultural Resources

131 page(s)
 CEC / M. JonesSWCA / N. Sikes
466176/6/2008 Order to Amend the Energy Commission Decision to Change Three Air Quality Conditions of Certification and Project description

3 page(s)
 CEC / Docket UnitCEC / J. Pfannenstiel
459744/21/2008 Petition to Amend the Project Description and Operating Parameters for the Cooling Tower at the Sacramento Municipal Utility District Financing Authority's Cosumnes Power Plant (01-AFC-19C)

5 page(s)
 CEC/Docket UnitCEC/R. Yasney
4337811/15/2007 Notice of Receipt SMUD Financing Authority Petition to Amend the Project Description and Operating Parameters for the Cooling Tower at the Cosumnes Power Plant

3 page(s)
 CEC / Docket UnitCEC / R. Johnson
4325911/7/2007 SFA's Petition for Post Certification license Amendment

65 page(s)
 CEC / Docket UnitSMUD / L. Jimenez-Price
425739/28/2007 Email re Withdrawing Sept 6th Petition

1 page(s)
 CEC / P. DavidSacramento Municipal Utility District / L. Jimenez-Price
422079/6/2007 SFA's Petition for Post Certification License Amendment for the Cosumnes PPP

62 page(s)
 CEC/ Docket UnitSMUD/ L. Jimenez
416887/27/2007 Cosumnes Power Plant withdrawal of petition to amend dated March 29, 2007

1 page(s)
 CEC / R. YasnyThermal Generation Assets / B. Nelson
406385/29/2007 Environmental Noise Analysis.

29 page(s)
 Aspen Environmental GroupBrown-Buntin Associates
397913/28/2007 Petition to Amend Conditions of Certification

42 page(s)
 CEC/ J. ScottSMUD Financing Authority
368805/2/2006 Acoustic Compliance Test Report (This is the attachment to the letter from SMUD dated 5/2/06 - Condition of Certification Noise-5)

131 page(s)
 CEC/Docket UnitATCO Noise Management
368795/2/2006 Consumnes Power Plant Condition of Certification Noise-5

139 page(s)
 CEC/J. Scott/County of Sacramento Planning Dept/R. SherrySMUD/Consumnes Power Plant/K. Hudson
363902/22/2006 Repeated Application for Confidential Designation Pursuant to Section 2505(a)(4) of Title 20: SMUD's Consumnes Power Plant (01-AFC-19): Cultural Resources

175 page(s)
 CEC/Blevins/Docket UnitSMUD/Cohn
362051/18/2006 Environmental Impact Noise Informal Complaint

1 page(s)
 CEC/Scott/Docket UnitSalvatore and Pamela Ali
361961/18/2006 SMUD Consumnes Power Plant Environmental Impact Noise Informal Complaint.

1 page(s)
 Jeri Scott/CEC/Docket UnitBill Warwick
3608912/14/2005 Order No. 05-1019-01(a) - Order Approving Transfer of Ownership to Sacramento Municipal Utility District Financing Authority

1 page(s)
 CEC/Docket UnitCEC/Desmond
3581110/26/2005 Order No. 05-1019-01-(a) Order Approving Transfer of Ownership to Sacramento Municipal Utility District Financing Authority.

1 page(s)
 Docket UnitCEC
354999/15/2005 Notice of receipt-Petition to change ownership.

2 page(s)
 CEC/ Docket UnitCEC/R. Johnson
354228/30/2005 SMUD's Post Certification Change in Ownership Petition for the Consumnes Power Plant Project.

3 page(s)
 CEC/Docket UnitSMUD/Jan Schori, Steven M Cohn
336843/17/2005 Repeated Application for Confidential Designation - Cultural Resources

2 page(s)
 CEC/Therkelsen/docketsSmud/Cohn
319287/21/2004 Establishment of Post-Certification Mailing List - POS

2 page(s)
 CEC/DocketCEC/Scott
318857/14/2004 Repeated Application for Confidential Designation Pursuant to section 2505(a)(4) of Title: 20 SMUD's Consumnes Power Plant: Cultural Resources

22 page(s)
 CEC/DocketsCEC/J. Scott
315705/21/2004 Response to Comments on Insignificant Project Change.

2 page(s)
 CEC/DocketsCEC/J. Scott
313314/29/2004 Letter to SMUD dated 4-28-04 regarding Approval of Petition to Modify the Project Description with Enclosures

28 page(s)
 Smud/Hudson/docketCEC/Scott
313164/26/2004 NOTICE OF INSIGNIFICANT PROJECT CHANGE, Consumnes Power Plant Project (01-AFC-19C).

1 page(s)
 CEC/ScottKathy Peasha
312134/9/2004 Notice of Insignificant Project Change (Relocate Segment of Natural Gas Pipeline)

2 page(s)
 Interested Parties/Cec/docketCEC/O'brien
312124/9/2004 Petition to Modify Project Description to Relocate Gas Pipeline Alignment Along Franklin Blvd. in Elk Grove

27 page(s)
 CEC/DocketSmud/Cohen
310683/5/2004 Repeated Application for Confidential Designation

2 page(s)
 CEC/TherkelsenSmud/Cohn
308001/29/2004 Approval to relocate water supply pipeline.

3 page(s)
 Kevin Hudson, Smud/DocketsCEC Cec
307991/29/2004 Approval to install concrete batch plant.

3 page(s)
 Kevin M Hudson, Smud/DocketsCEC Cec
3064212/19/2003 Consumnes (SMUD) -- NOTICE OF INSIGNIFICANT PROJECT CHANGE (Temporary Concrete Batch Plant).

2 page(s)
 CEC/DocketsCEC Cec
3064112/19/2003 Consumnes (SMUD) - NOTICE OF INSIGNIFICANT PROJECT CHANGE (Relocate Water Supply Pipeline).

2 page(s)
 CEC/DocketsCEC Cec
3043811/19/2003 Petition to Modify Project Description

7 page(s)
 CEC/DocketsSmud/Cohn
3039411/13/2003 Order Denying Petition For Reconsideration - POS

7 page(s)
 CEC/DocketCEC/Pernell/boyd/rosenfeld
3024210/27/2003 SMUD's Response to Peasha Petition for Reconsideration-POS

12 page(s)
 CEC/DocketSmud/Cohn
3020710/20/2003 Notice of Commission Hearing on Petition for Reconsideration POS

5 page(s)
 CEC/DocketsCEC/Keese
3016910/21/2003 Revised Proof of Service

4 page(s)
 CEC/DocketCEC/Hearing Office
3007310/8/2003 Kathy Peasha's Request for Reconsideration of the Commission Decision on the Consumnes Power Project - POS.

6 page(s)
 CEC/DocketsKathy Peasha