Docket Log

Docket: 01-AFC-21C
Project Title: Tesla Power Project Compliance
Generated On: 3/28/2024 8:32:19 AM

Include:     
TN #Docketed DateDocument TitleExhibit #ToFrom
557743/8/2010 Memorandum of Understanding (MOU) Betweet the California Energy Commission (CEC) & AIMS Corporation

6 page(s)
 CEC/ Docket UnitCEC/ T. O'Brien
534139/25/2009 Order Denying Petition for Extension of Construction Deadline

9 page(s)
 CEC/ Docket UnitCEC/ All Commissioners
533139/22/2009 R. Sarvey's Response to PG&E's Comments on Siting Proposed Order

4 page(s)
 CEC/ Docket UnitPublic/ R. Sarvey
532869/21/2009 PG&E's Comments on the Siting Committee's Proposed Order on its Request for Extension of Construction Deadline

13 page(s)
 CEC/ Docket UnitGalati & Blek LLP/ M. Mills
532639/21/2009 Letter from Turn Supporting PG&E Petition to Extend Certification

1 page(s)
 CEC/ J. ByronUtility Reform Network/ M. Florio
532229/15/2009 {Proposed} Order Denying Petition for Extension of Construction Deadline

9 page(s)
 CEC/ Docket UnitCEC/ All Commissioners
532149/15/2009 Order Extending License to October 15, 2009

3 page(s)
 CEC/Docket UnitCEC/K. Douglas/A. Rosenfeld/J. Levin/J. Boyd
530518/28/2009 Notice of Consideration of Additional 30-Day License Extension & Notice of New Hearing Date on Committee Proposed Decision

7 page(s)
 CEC/ Docket UnitCEC/ K. Douglas & J. Byron
526928/4/2009 Staff's Post-Hearing Brief

6 page(s)
 CEC/ Docket UnitCEC/ K. Bell
526808/3/2009 Robert Sarvey's Post Hearing Brief

16 page(s)
 CEC/ Docket UnitState of California Energy Resources Conservation & Development Commison/ R. Sarvey
526788/3/2009 CEC Staff's Post-Hearing Brief

4 page(s)
 CEC/ Docket UnitCEC/ K. Bell
526738/3/2009 PG&E's Post Hearing Brief in Support of its Request for Extension of Construction Deadline

9 page(s)
 CEC/ Docket UnitGalati Blek/ PG&E
525337/23/2009 Order Granting Ownership Change

3 page(s)
 CEC/ Docket UnitCEC/ K. Douglas
524937/21/2009 Post-Hearing Briefing Schedule

4 page(s)
 CEC/ Docket UnitCEC/ G. Fay
524297/15/2009 Committee Order Denying Petition to Intervene

5 page(s)
 CEC/ Docket UnitCEC/ K. Douglas & J. Byron
524137/14/2009 Intervenor Robert Sarvey's Support for Intervention of the Independent Energy Producers

4 page(s)
 CEC/ Docket UnitIntervenor/ R. Sarvey
524087/13/2009 Robert Sarvey’s Rebuttal Testimony Resume, Declaration ,and Exhibit List

37 page(s)
 CEC/ Docket UnitPublic/ R. Sarvey
524037/13/2009 San Joaquin Valley Air Pollution Control District Rebuttal Testimony

6 page(s)
 CEC/ Docket UnitSan Joaquin Valley Air Pollution Control District/ D. Warner
523757/13/2009 PG&E's Opposition to IEP's Petition to Intervene

6 page(s)
 CEC/ Docket UnitGalati & Blek LLP/ M. Mills
523097/6/2009 Petition to Intervene by the Independent Energy Producers

5 page(s)
 CEC/ Docket UnitEllison, Schneider & Harris LLP/ G. Wheatland
522757/2/2009 Staff's Request for Leave to File its Brief Testimony

13 page(s)
 CEC/ Docket UnitCEC/ K. Bell
521946/29/2009 PG&E's Initial Brief in Support of its Request for Extension of Construction Deadline

13 page(s)
 CEC/ Docket UnitGalati Blek LLP/ M. Mills
521936/29/2009 Testimony of Fong Wan & William V. Manheim & Testimony of Andrea Grenier & Jerry Salamy

28 page(s)
 CEC/ Docket UnitGalati Blek LLP/ M. Mills
518906/9/2009 Notice of Evidentiary Hearing & Committee Order Regarding Applicant's Petition for Extension

10 page(s)
 CEC/ Docket UnitCEC/ R. Avalos
517345/28/2009 Petition for Change of Ownership & Extension of teh Deadline to Commence Construction

3 page(s)
 CEC/ Docket UnitCEC/ E. Allen
516305/20/2009 Comments on Petition for Ownership Change & Extension of License

2 page(s)
 CEC/ S. MunroSan Joaquin Valley/ D. Warner
516035/18/2009 Comments of R. Sarvey on the Extension of Time for Construction & Ownership Change

7 page(s)
 CEC/ Docket UnitPublic/ R. Sarvey
513504/24/2009 PG&E's Petition for Ownership Change and Extension of License

7 page(s)
 CEC/ Docket UnitGalatiBlek/ A. Garner
4881610/29/2008 Energy Commission Authorization to Construct Reclaimed Water Pipeline

4 page(s)
 Peter WeinerCEC/ J. Caswell
4881410/29/2008 Response to Information Provided on Pipeline Segment Installation

14 page(s)
 Peter H. WeinerCEC/ K. Bell
477648/26/2008 Tesla Project Request for Geotech Investigation

1 page(s)
 CEC/ J. Caswell/ S. MunroGalatiBlek/ S. Galati
475748/15/2008 Authorization to Conduct Geotechnical Testing for Tesla Powe Project Lette

2 page(s)
 CEC/ Docket UnitCEC/ S. Munro
474918/7/2008 Notice of Water Pipe Installation

3 page(s)
 CEC/ J. CaswellPaul, Hastings, Janofsky & Walker LLP/ P. Weiner
473327/18/2008 PG&E/Tesla GSP Prepared Testimony, Public Version

140 page(s)
 CEC/ Docket UnitPG&E
473317/18/2008 Application of PG&E for Expedited Approval of the Tesla GS and Issuance of a Certificate of Public Convenience and Necessity and Request for Interim Order Authorizing Early Project Commitment to Stabilize Costs (Public Version)

101 page(s)
 CEC/ Docket UnitPG&E
471657/22/2008 Notice of an Application for a Certificate of Public Convenience and Necessity

1 page(s)
 CEC/ S. MunroPG&E
471597/21/2008 Amendment to Application of PG&E

85 page(s)
 CEC / Docket UnitPG&E / W. Manheim / C. Middlekauff / K. Klein / J. Levenberg
413016/29/2007 June 2007 Post Certification Amendment Data Responses

17 page(s)
 CEC/ S. MunroCH2MHILL/ D. Stein/ FPL
390831/25/2007 Notice of Receipt - Petition to Amend CEC Decision.

3 page(s)
 Interested Parties/ Property OwnersCEC/ R. Johnson
3877812/26/2006 Establishment of Post Certification Mailing list for the Tesla Power Project

2 page(s)
 Docket UnitS. Munro / CEC
3848011/28/2006 Tesla Petition for Post-Certification Amendments

1 page(s)
 CEC/ J. ScottCH2MHill/ D. Stein
367424/14/2006 Thank you for your e-mail. I am forwarding your concerns to Connie Burins.

1 page(s)
 Wexler/JeanneCEC/MediaOffice
332261/31/2005 Demand to Correct or Cure Violaions on the Bagley-Keene Open Meeting Act

10 page(s)
 CEC/DocketsCare/Sarvey
2468-08/3/2009 Transcript of Evidentiary Hearing on July 20th

90 page(s)