519136/10/2009Order Approving Transfer of Ownership from Mountainview Power Co. to Southern California Edison
Order Approving Transfer of Ownership from Mountainview Power Co. to Southern California Edison
1 page(s)
 CEC/ Docket UnitCEC/ K. Douglas
519226/10/2009Notice of Decision
Notice of Decision
1 page(s)
 California Resources AgencyCEC/ C. Davis
509084/7/2009Notice of Receipt Petition to Change Ownership
Notice of Receipt Petition to Change Ownership
2 page(s)
 CEC/ Docket UnitCEC/ E. Allen
507694/1/2009Applicant's Petition to Amend to Change Name of Owning Entity
Applicant's Petition to Amend to Change Name of Owning Entity
5 page(s)
 CEC/ C. DavisMountainview Power Co/ I. Cuthbertson
373137/7/2006Notice of Decision by the CEC Mountainview Power Project
Notice of Decision by the CEC Mountainview Power Project
1 page(s)
 Ca Resource AngencyCEC/ D. Stone
373147/7/2006Order Approving Petition to Increase The Volatile Organic Compound VOC Emissions Limits and Change The Equipment Description of The Emergency Diesel Generation
Order Approving Petition to Increase The Volatile Organic Compound VOC Emissions Limits and Change The Equipment Description of The Emergency Diesel Generation
5 page(s)
 St CA Energy Resources Conservation & Development CommCEC / J, Pfannenstiel
370886/9/2006Mountainview Power Project Staff Analysis of Proposed Modifications to the Volatile Organic Compound Emissions Limits Within the Air Quality Conditions of Certification AQ-11 & AQ- 12 as well as a Description Change of a Emergency Generator & the Deletion of Condition AQ-19
Mountainview Power Project Staff Analysis of Proposed Modifications to the Volatile Organic Compound Emissions Limits Within the Air Quality Conditions of Certification AQ-11 & AQ- 12 as well as a Description Change of a Emergency Generator & the Deletion of Condition AQ-19
8 page(s)
 Interested Parties /Docket UnitD. Stone / CEC
369465/17/2006Spreadsheet which provides the documentation for the ERC's Which have been either procured by SCE or already banked and will be used by MVL for additional VOC offsets.
Spreadsheet which provides the documentation for the ERC's Which have been either procured by SCE or already banked and will be used by MVL for additional VOC offsets.
3 page(s)
 D. Stone CEC / Docket UnitJ. Diven URS Corporation
369435/16/2006NOTICE OF RECEIPT Petition to Amend The Energy Commission Decision for the Mountainview Power Project
NOTICE OF RECEIPT Petition to Amend The Energy Commission Decision for the Mountainview Power Project
3 page(s)
 CEC/Docket UnitCEC/R. Johnson
369085/8/2006Amendment to CEC License for the Mountainview Power Project.
Amendment to CEC License for the Mountainview Power Project.
86 page(s)
 CEC/DocketsMoutainview Power Company, LLC
361441/5/2006Notice of Insignificant Project Change: To modify the equipment description of the emergency power generator.
Notice of Insignificant Project Change: To modify the equipment description of the emergency power generator.
2 page(s)
 CEC/Docket UnitCEC/R. Johnson
3612212/22/2005Notice of Receipt of Petition to Modify and Staff Analysis
Notice of Receipt of Petition to Modify and Staff Analysis
4 page(s)
 Interested PartiesCEC/Stone
3613912/19/2005Amendment To CEC License For The Mountain View Power Project
Amendment To CEC License For The Mountain View Power Project
1 page(s)
 CEC/ Docket UnitMountain View Power Company
3608512/14/2005Order No. 05-0824-03 - Order Approving Petition to Delay Completing the color Treatment Application of the Power Plant to Within 90 days After the Start of Commercial Operations
Order No. 05-0824-03 - Order Approving Petition to Delay Completing the color Treatment Application of the Power Plant to Within 90 days After the Start of Commercial Operations
3 page(s)
 CEC/Docket UnitCEC/Pfannenstiel
354509/7/2005ORDER APPROVING (Order number 05-0824-03) Petition to Delay Completing the Color Treatment Application of the Power Plant to Within 90 days After the Start of Commercial Operations.
ORDER APPROVING (Order number 05-0824-03) Petition to Delay Completing the Color Treatment Application of the Power Plant to Within 90 days After the Start of Commercial Operations.
3 page(s)
 CEC/Docket UnitCEC/Commissioner Pfannenstiel/D. Stone
354439/2/2005Notice of Decision.
Notice of Decision.
1 page(s)
 CEC/Docket UnitCEC/Donna Stone
348577/8/2005Notice of Receipt & Public Review of Staff Analysis: Petition to Delay Application of Color Treatment.
Notice of Receipt & Public Review of Staff Analysis: Petition to Delay Application of Color Treatment.
4 page(s)
 CEC/Docket UnitCEC/D. Stone
347636/24/2005Mountainview Power Project-Proposed VIS -1 Amendment
Mountainview Power Project-Proposed VIS -1 Amendment
20 page(s)
 Docket UnitURS/J. Diven
3254710/15/2004Order Approving a Petition to Amend the Natural Gas Pipeline Alignment
Order Approving a Petition to Amend the Natural Gas Pipeline Alignment
7 page(s)
 CEC/DocketsCEC/Rosenfled
3245210/12/2004Condition of Certification Submittals Package No. AQ-29 and AQ-33 Cooling Tower PM10 Emission and Drift Eliminator Design
Condition of Certification Submittals Package No. AQ-29 and AQ-33 Cooling Tower PM10 Emission and Drift Eliminator Design
10 page(s)
 Mountainview Power/Yamada/docketsBechtel/Cromer
323519/16/2004Order Approving a Petition to Modify Air Quality Conditions of Certification.
Order Approving a Petition to Modify Air Quality Conditions of Certification.
14 page(s)
 Mountainview Power Company, L.l.c.CEC/Keese
323349/14/2004Order No. 04-0908-05: Order Approving a Petition to modify air quality conditions of certification
Order No. 04-0908-05: Order Approving a Petition to modify air quality conditions of certification
14 page(s)
 CEC/Docket UnitCEC/Keese
323069/8/2004Notice of Decision
Notice of Decision
1 page(s)
 CEC/DocketCEC Cec
321388/19/2004Staff Analysis of Proposed Modifications to Conditions of Certification Air Quality: -1 thru -16; -18, -23, -24, -25, -28, -36, and -38; Deletion of Condition Air Quality -13, & Reinstatement of Condition Air Quality -19.
Staff Analysis of Proposed Modifications to Conditions of Certification Air Quality: -1 thru -16; -18, -23, -24, -25, -28, -36, and -38; Deletion of Condition Air Quality -13, & Reinstatement of Condition Air Quality -19.
47 page(s)
 CEC/DocketCEC/D. Stone
312064/7/2004Notice of Receipt -- Petition to Amend The Energy Commission Decision.
Notice of Receipt -- Petition to Amend The Energy Commission Decision.
3 page(s)
 CEC/DocketsCEC/T. O'brien
312074/7/2004Notice of Receipt -- Petition to Amend--Changes from the original Energy Commission Decision include: "Addition of a valve station..."; "Routing the line under the UPRR rail line..."; "Routing the line through the Tippecanoe Bridge over Santa Ana River..."; and "Adding several construction lay down areas to ease & speed construction of the line."
Notice of Receipt -- Petition to Amend--Changes from the original Energy Commission Decision include: "Addition of a valve station..."; "Routing the line under the UPRR rail line..."; "Routing the line through the Tippecanoe Bridge over Santa Ana River..."; and "Adding several construction lay down areas to ease & speed construction of the line."
3 page(s)
 CEC/DocketsCEC/T. O'brien
311243/18/2004Amendment for the 17.9-Mile Natural Gas Pipeline
Amendment for the 17.9-Mile Natural Gas Pipeline
58 page(s)
 CEC/DocketsMoutainview Power Company
310143/1/2004Amendment to CEC License for the Mountianview Power Project.
Amendment to CEC License for the Mountianview Power Project.
30 page(s)
 CEC/DocketsMountainview Power Company/J. Diven, Urs
257956/3/2002Establishment of Post-Certification List
Establishment of Post-Certification List
2 page(s)
 CEC/DocketsCEC/Stone
246182/25/2002Construction Schedule - POS
Construction Schedule - POS
4 page(s)
 CEC/Stone/docketsLivingston & Mattesich/Mckinnsey
242191/16/2002Deletion of Condition of Certification AQ19 Allowing for the Use of Caterpillar Model
Deletion of Condition of Certification AQ19 Allowing for the Use of Caterpillar Model
1 page(s)
 Office Of Planning & Research/DocketsCEC/Stone
240261/11/2002Approval of Project Changes: Allowing use of Caterpillar Model 3512B and Deletion of Condition of Certification AQ-19
Approval of Project Changes: Allowing use of Caterpillar Model 3512B and Deletion of Condition of Certification AQ-19
3 page(s)
 Mountainview Power Co./Kehres/docketsCEC/Therkelsen
2274310/18/2001Notice of Exemption-General Arrangement Amendment
Notice of Exemption-General Arrangement Amendment
1 page(s)
 Office Of Planning And Research/DocketsCEC/Stone
223499/18/2001Approval of Request for General Arrangement Amendment Changes to Conditions of Certification AQ-9 and AQ-10 Additional of Condition WQ-8
Approval of Request for General Arrangement Amendment Changes to Conditions of Certification AQ-9 and AQ-10 Additional of Condition WQ-8
4 page(s)
 Mountainview Power Co/Hall/docketsCEC/Therkelsen
220818/29/2001Notice of Exemption-Expansion of Construction Laydown Area
Notice of Exemption-Expansion of Construction Laydown Area
1 page(s)
 Office Of Planning And Research/DocketsCEC/Stone
219188/16/2001Notice of Exemption-Addition of Condition of Certification to Ensure Coordinated Integration of New Generating Unit with California's Electricity Grid
Notice of Exemption-Addition of Condition of Certification to Ensure Coordinated Integration of New Generating Unit with California's Electricity Grid
1 page(s)
 Office Of Planning And Research/DocketsCEC/Bruins
220808/16/2001Approval of Request for Additional Laydown Area
Approval of Request for Additional Laydown Area
2 page(s)
 Mountainview Power Co. Llc/Hall/docketsCEC/Therkelsen
215107/25/2001General Arrangement Amendment
General Arrangement Amendment
67 page(s)
 CEC/Stone/docketUrs/Diven
216567/25/2001Revised Air Quality Modeling
Revised Air Quality Modeling
27 page(s)
 CEC/Stone/docketsSierra Research/Rubenstein
214277/13/2001Pre-Construction and Construction Milestones
Pre-Construction and Construction Milestones
3 page(s)
 Mountainview Power Plant/Chandler/cec/docketsCEC/Therkelsen
213977/12/2001Notice of Exemption: Approval of Request to Modify Mountainview Power Project Condition of Certification AQ-C2 to Allow the Use of Ultra-Low Sulfur Fuel in Conjunction with 1996 ARB Certified Engines in Place of Oxidizing Coot Filters
Notice of Exemption: Approval of Request to Modify Mountainview Power Project Condition of Certification AQ-C2 to Allow the Use of Ultra-Low Sulfur Fuel in Conjunction with 1996 ARB Certified Engines in Place of Oxidizing Coot Filters
1 page(s)
 Office Of Planning & Research/DocketsCEC/Stone
213987/12/2001Approval of Request to Change Mountainview Power Project Condition AQ-C2 to Allow the Use of Ultra Low Sulfur Fuel in Conjunction with 1996 ARB Certified Engines in Lieu of Soot Filters
Approval of Request to Change Mountainview Power Project Condition AQ-C2 to Allow the Use of Ultra Low Sulfur Fuel in Conjunction with 1996 ARB Certified Engines in Lieu of Soot Filters
5 page(s)
 Mountainview Power Co/Hall/docketsCEC/Therkelsen
213097/5/2001Notice of Availability Staff Assessment for the Mountainview Power Plant Project
Notice of Availability Staff Assessment for the Mountainview Power Plant Project
1 page(s)
 CEC/Therkelsen/docketDepartment Of Public Works/Varma
210996/22/2001Proposed Additional Construction Laydown Area
Proposed Additional Construction Laydown Area
4 page(s)
 CEC/Stone/docketsUrs/Diven
212836/22/2001Request for Update of Construction Equipment Mitigation Condition AQ-C2
Request for Update of Construction Equipment Mitigation Condition AQ-C2
4 page(s)
 CEC/Stone/docketsMountain Power Co./Hall