TN #Docketed DateDocument TitleExhibit #ToFrom
2461359/16/2022 Order Approving Settlement
Order No: 22-0914-05
3 page(s)
 CEC/Docket UnitCalifornia Energy Commission
24005710/13/2021 Statement of Staff Approval of Proposed Change

13 page(s)
 CEC/Docket UnitCalifornia Energy Commission
2398049/21/2021 Notice of Receipt Petition for Post Certification Project Change

2 page(s)
 CEC/Docket UnitCalifornia Energy Commission
2393058/13/2021 Petition for Minor Amendments to CEC Decision
Petition for minor amendments to the CEC Decision to: (1) allow for short-term like-kind replacement of turbines when turbine maintenance offsite is needed; and (2) make the California Energy Commission’s (CEC’s) Conditions of Certification for air quality consistent with new Permits to Operate issued by the San Diego County Air Pollution Control District (APCD) that allow for such short-term like-kind turbine replacement.
60 page(s)
 CEC/Mr. Joseph DouglasOrange Grove Energy
23102812/10/2019 Orange Grove Project 2018 Report

77 page(s)
 CEC/DocketsCalifornia Energy Commission
22562410/30/2018 Compliance Docketing Policy

3 page(s)
 Plant ManagerCalifornia Energy Commission
2123637/20/2016 Notice of Decision by the California Energy Commission
Filing of Notice of Decision in compliance with Public Resources Code Section
1 page(s)
  California Energy Commission
2123337/18/2016 Order Approving Petition to Amend
This document supersedes TN 212331.
36 page(s)
 PartiesCalifornia Energy Commission
2123317/18/2016 Order Approving Petition to Amend to Replace Potable Water with Recycled Water
Superseded by TN 212333
36 page(s)
 PartiesCalifornia Energy Commission
2117636/9/2016 Staff Analysis of the Petition to Amend
Replacement of like-kind components of the emission control system
57 page(s)
 Interested PartiesCalifornia Energy Commission
2110204/13/2016 Notice of Receipt
Petition to Amend
2 page(s)
  California Energy Commission
2110044/12/2016 Petition for Emission Control Reliability Improvements

82 page(s)
 CEC/Joe DouglasOrange Grove Energy, L.P.
2035001/5/2015 Withdrawal of Petition for Post Certification Amendment to Address Water Truck Complaints

2 page(s)
 Joe Douglas, Compliance Project ManagerDay Carter & Murphy LLP
20317610/7/2014 Walter Rusinek Comments: Comments of the Pala Band of Mission Indians on the Orange Grove Energy L.P.'s Response to Data Requests 1, 2, and 3

Alternatives, Compliance, Visual Resources, Soil and Water
21 page(s)
 CEC/Docket UnitWalter Rusinek
20314210/1/2014 Pala Band of Mission Indians c/o Walter Rusinek, Procopio Comments: Updated Comments of the Pala Band of Mission Indians on the Petition to Amend the California Energy Commission Decision for the Orange Grove Power Project (08-AFC-4C)

Alternatives, Compliance, Visual Resources, Soil and Water
84 page(s)
 CEC/Dockets UnitPala Band of Mission Indians c/o Walter Rusinek, Procopio
2030409/8/2014 Response to Data Requests 1, 2, and 3

8 page(s)
 CEC / Docket UnitDay Carter Murphy LLP
2029698/21/2014 Petition to Amend the California Energy Commission Decision for the Orange Grove Power Project (08-AFC-4C)

83 page(s)
 CEC/ Docket UnitProcopio, Cory, Hargreaves & Savitch LLP
2023915/29/2014 Notice of Receipt of Petition to Amend Received from Orange Grove Power Project

2 page(s)
  California Energy Commission
2023615/21/2014 Petition for Post Certification Amendment to Address Water Truck Complaints

159 page(s)
 CEC Docket UnitDay Carter Murphy LLP
645894/4/2012 Order Approving Petition to Amend

22 page(s)
 CEC/Docket UnitCEC/J.Douglas
645243/28/2012 Notice of Decision

1 page(s)
 CA Resources AgencyCEC/ J. Douglas
6317312/20/2011 Staff Analysis with Cover Letter for Modification to AQ Conditions

32 page(s)
 CEC/Dockets UnitCEC/J.Douglas
6251210/6/2011 Notice of Receipt - Petition to Amend

3 page(s)
 CEC/ Docket UnitCEC/ C. Marxen
622319/15/2011 Petition to Amend the Orange Grove Project

29 page(s)
 CEC/ J. DouglasTRC/ J. Stenger
607005/19/2011 Notice of Receipt Petition to Amend the CEC Decision for the Orange Grove Project

3 page(s)
 CEC/Dockets UnitCEC/C.Marxen
605585/5/2011 Petition to Modify the Orange Grove Project

21 page(s)
 CEC/ Docket UnitCEC/ C. Stora
5366710/15/2009 Notice of Receipt: Petition to Amend the CEC Decision

3 page(s)
 CEC/ Docket UnitCEC/ E. Allen
532339/16/2009 Petition to Modify

21 page(s)
 CEC/ Docket UnitApplicant/ R. Jones
531369/3/2009 Revised Notice of Receipt

2 page(s)
 CEC/ Docket UnitCEC/ E. Allen
530208/27/2009 Notice of Reciept - Petition to Amend

2 page(s)
 CEC/ Docket UnitCEC/ E. Allen
523577/9/2009 Start of Constrcution Letter to Mr. Richard M. Jones

2 page(s)
 J-Power USA/ R. JonesCEC/ R. Yasny
518226/4/2009 Petition to Amend Laydown Area

31 page(s)
 CEC/ Docket UnitCEC/ R. Yasny
506243/19/2009 Application for Certification - Cultural Resources Monitoring & Mitigation Plan

4 page(s)
 CEC/ M. JonesTRC Solutions/ J. Taylor
504993/12/2009 Deficient Application for Certification - Cultural Resources Monitoring & Mitigation Plan

4 page(s)
 CEC/ R. YasnyTRC Solutions/ E. Back