TN #Docketed DateDocument TitleExhibit #ToFrom
707965/14/2013CEC Operations Letter to Competitive Power Ventures, Inc.
CEC Operations Letter to Competitive Power Ventures, Inc.
1 page(s)
 Competitive Power Ventures, Inc./M.McDanielsCEC/ C. Hoffman
698693/8/2013CEC Response to Application for Confidentiality for Cultural Resources CUL-4
CEC Response to Application for Confidentiality for Cultural Resources CUL-4
2 page(s)
 Latham & Watkins LLP/ M. CarrollCEC/ R. Oglesby
695982/15/2013Application for Confidential Designation - CUL - 4 Cultural Resources Report
Application for Confidential Designation - CUL - 4 Cultural Resources Report
3 page(s)
 CEC/ Robert OglesbyLatham & Watkins/ CPV Sentinnel, LLC
660566/27/2012Application for Confidential Designation - Conditions of Certification Soil and Water
Application for Confidential Designation - Conditions of Certification Soil and Water
8 page(s)
 CEC/ R.OglesbyApplicant/Latham Watkins/ M.Carroll
652575/16/2012CEC Response to Application for Confidential Designation Regarding CUL-6 Cultural Resource Data
CEC Response to Application for Confidential Designation Regarding CUL-6 Cultural Resource Data
2 page(s)
 Latham & Watkins/M.CarrollCEC/R.Oglesby
651275/9/2012Application for Confidential Designation Cultural Resources
Application for Confidential Designation Cultural Resources
13 page(s)
 CEC/R.OglesbyApplicant/Latham & Watkins/M.Carroll
642393/20/2012Letter from Maggie Fitzgerald to Roy Olivares Regarding RECLAIM/ Title V Facility Permit
Letter from Maggie Fitzgerald to Roy Olivares Regarding RECLAIM/ Title V Facility Permit
7 page(s)
 South Coast AQMD/R.OlivaresSierra Research/M.Fitzgerald
623469/23/2011Notice of Decision
Notice of Decision
1 page(s)
 California Resources AgencyCEC/ D. Rundquist
623079/21/2011Order Approving a Petition to Modify the General Arrangement
Order Approving a Petition to Modify the General Arrangement
2 page(s)
 CEC/ Docket UnitCEC/ H. Kallemeyn
621039/7/2011Approval of Request to Modify Construction Parking Area
Approval of Request to Modify Construction Parking Area
1 page(s)
 Competitive Power Ventures Inc./J.MurphyCEC/F.Miller
620849/6/2011Withdrawal of Letter of Objection from James Turney
Withdrawal of Letter of Objection from James Turney
1 page(s)
 CEC/ D. RundquistLaw Offices of James C. Turney
619918/24/2011Notice of Determination to Modify the Laydown Area
Notice of Determination to Modify the Laydown Area
2 page(s)
 CEC/Dockets UnitCEC/C.Marxen
618088/9/2011Staff Analysis of Request for General Arrangement Refinements
Staff Analysis of Request for General Arrangement Refinements
10 page(s)
 CEC/Dockets UnitCEC/D.Rundquist
618098/9/2011Letter to James C. Turney Re Petition to Amend
Letter to James C. Turney Re Petition to Amend
2 page(s)
 CEC/Dockets UnitCEC/D.Rundquist
617218/4/2011Notice of Receipt - Peition to Modify the General Arrangement of Site
Notice of Receipt - Peition to Modify the General Arrangement of Site
3 page(s)
 CEC/ Docket UnitCEC/ C. Marxen
614457/21/2011Objection to Determination Letter
Objection to Determination Letter
2 page(s)
 CEC/Dockets UnitCEC/D.Rundquist
613677/13/2011Construction Parking Area Addition
Construction Parking Area Addition
22 page(s)
 CEC/ Dale RundquistURS/ M. Fitzgerald
612396/29/2011Notice of Determination
Notice of Determination
2 page(s)
 CEC/Dockets UnitCEC/C. Marxen
610776/10/2011Petition to Amend, General Arrangement Refinements
Petition to Amend, General Arrangement Refinements
43 page(s)
 CEC/D.RundquistURS/M.Fitzgerald
602814/7/2011Application for Confidential Designation CPV Sentinel Energy Project Power Plant
Application for Confidential Designation CPV Sentinel Energy Project Power Plant
4 page(s)
 CEC/M.JonesLatham & Watkins LLP
600303/17/2011Notice of Determination Petiton to Modify the Laydown Area for the CP Sentimel Project
Notice of Determination Petiton to Modify the Laydown Area for the CP Sentimel Project
2 page(s)
 CEC/ Docket UnitCEC/ C. Marxen
596802/14/2011Petition to Shift the Construction Laydown Area at the CPV Sentinel Power Plant
Petition to Shift the Construction Laydown Area at the CPV Sentinel Power Plant
5 page(s)
 CEC/ D. RundquistURS/ M. Fitzgerald
565955/6/2010MOU Between CEC & Bureau Veritas re Design, Review & Construction Inspection
MOU Between CEC & Bureau Veritas re Design, Review & Construction Inspection
6 page(s)
 CEC/Docket UnitCEC/M. Dyas