Docket Log

Docket: 03-AFC-01
Project Title: Roseville Energy Park
Generated On: 4/26/2024 8:54:48 PM

Include:     
TN #Docketed DateDocument TitleExhibit #ToFrom
3863412/13/2006 Roseville Energy Park Condition of certification BIO-3

5 page(s)
 CEC/ D. StoneREP/ A. Grenier
3805210/2/2006 App. for conf. designation and Paleo. Report

18 page(s)
 CEC/ B.B. BlevinsREP/ A. Grenier
363682/16/2006 January 6, 2006 Site Visit to Roseville Park Energy

3 page(s)
 Docket Unit / Andrea GrenierCEC/ D. Stone
342495/3/2005 Commission Adoption Order

3 page(s)
 DocketsCEC/Commissioners
339394/18/2005 Notice of Decision, Notice of Completion, and Receipt. POS

8 page(s)
 CEC/Docket UnitCEC/James Reede
339364/15/2005 Commission Decision - POS Publication Number CEC-800-2005-003

406 page(s)
 CEC/DocketsCdc
339354/15/2005 Commission Adoption Order

3 page(s)
 Cdc/DocketsCEC Cec
339094/11/2005 Errata to the Presiding Member Proposed Decision

9 page(s)
 CEC/DocketsCEC/Geesman/rosefeld
338114/5/2005 Proposed modified language for page 71 of Efficiency that incorporates staff's and applicant's comments.

2 page(s)
 CEC/Fay/docket UnitCEC/Willis
337283/24/2005 Roseville's Comments on the Presiding Member's Proposed Decision (PMPD). POS

8 page(s)
 CEC/Docket UnitGalati & Blek Llp/Roseville Energy Park
337263/24/2005 Staff PMPD Comments. POS

8 page(s)
 Commissioner Geesman/Cec/docket UnitCEC/J. Reede
336673/11/2005 Notice of Availability of the Presiding Member's Proposed Decision and Notice of Committee Conference and Notice of Commission Hearing

6 page(s)
 CEC/DocketsCEC/Geesman/rosenfeld
336663/11/2005 Commission Grant the Applicant a license to construct and operate the project

1 page(s)
 DocketsCEC/Geesman/rosenfeld
336653/11/2005 Presiding Member's Proposed Decision Roseville Energy Park - CEC 800-2005-003-PMPD

395 page(s)
 CEC/DocketsCEC Cec
335422/28/2005 Response to consultant's request for an approval jurisdictional determination. POS

5 page(s)
 CEC/Docket UnitDept Of The Us Army/T. J. Cavanaugh
334882/18/2005 Applicant's Reply Brief

150 page(s)
 CEC/Rodriguez/docket UnitGalati & Blek/Galati
333242/11/2005 Staff's Post-Hearing Brief - POS

9 page(s)
 CEC/DocketsCEC/Willis
332822/7/2005 Evidentiary Hearing Before The California Energy Resources Conservation and Development Commission.

103 page(s)
 DocketsCEC Cec
331561/19/2005 2nd Errata to the Traffic & Transportation, Condition of Certification. POS

9 page(s)
 Commission Geesman/Cec/docket UnitCEC/J. Reede
331521/7/2005 Staff's Report of Resolution of Issues - POS

21 page(s)
 CEC/DocketsCEC/Willis
331181/14/2005 Applicant's Testimony. Pos

98 page(s)
 CEC/Docket UnitRoseville/Galati & Blek Llp/c. Philps
331161/14/2005 Errata to the Traffic & Transportation Analysis filed by staff in the FSA. POS

6 page(s)
 CEC/Docket UnitCEC/J. Reede
330951/10/2005 Notice of Evidentiary Hearing. POS

9 page(s)
 CEC/Docket UnitCEC/Commissioners Geesman & Rosenfeld
330611/5/2005 Air Quality Errata to the Roseville Energy Park FSA. POS

9 page(s)
 John Geesman/Docket UnitCEC/J. Reede
3304412/29/2004 CEC Staff's Prehearing Conference Statement. POS

5 page(s)
 CEC/Docket UnitCEC Cec
3302512/29/2004 Roseville Prehearing Conference Statement. POS.

30 page(s)
 CEC/Docket UnitRoseville/Galati & Blek Llp
3296112/21/2004 Roseville Energy Park: Air Quality Concerns. Pos

6 page(s)
 J. Reede/Cec/docket UnitRoseville Joint Union High School Dist./ R. Strick
3290212/7/2004 Records of Conversation and e-mail relating to Plumes. 1. 10/12/04, D. Campbell to J. Adams - 2. 11/15/04, B. Simi to J. Adams - 3. Record of Conversation, 11/1/04, B. Simi and J. Adams and 4. Record of Conversation 12/1/04, S. Brown and J. Adams - POS

8 page(s)
 CEC/DocketsCEC/Reed
3289212/6/2004 Notice of Site Visit, Prehearing Conference, and Issues Workshop. POS

8 page(s)
 CEC/Docket UnitCEC Cec
3285912/2/2004 Attachment A- Cooling Tower Plume Ground Level Fogging Analysis- to the Traffic and Transportation Section of the FSA. POS

12 page(s)
 CEC/Docket UnitCEC Cec
3285512/2/2004 Memo from Don Campbell, Fehr & Peers Assoc., re: Power Plant Fog.

1 page(s)
 CEC/Docket UnitCEC/J. Adams
3285412/2/2004 Memo from B. Simi, DOT, re: Plume Abatement.

1 page(s)
 CEC/Docket UnitCEC/J. Adams
3285111/30/2004 Roseville Final Staff Assessment. POS

755 page(s)
 CEC/Docket UnitCEC/J. Reede
3284811/30/2004 Notice of Availability for the Roseville FSA.

2 page(s)
 CEC/Docket UnitCEC/Richins
3284711/30/2004 Agency Distribution for Roseville FSA.

2 page(s)
 CEC/Docket UnitCEC/Richins
3284611/30/2004 Library Distribution Letter of Roseville FSA

3 page(s)
 CEC/Docket UnitCEC/Richins
3265011/4/2004 ABC's Comments to the 2005 IEPR

28 page(s)
 CEC/DocketAbc/Tennis
3264811/4/2004 Response to Comments of August 10, 2004

11 page(s)
 Associated Builders And Contractors/TennisCEC/Therkelsen
3264311/2/2004 Final Determination of Compliance - POS

212 page(s)
 CEC/DocketGalati & Blek/Galati
3264211/2/2004 Applicant's Status Report No. 7 - POS

4 page(s)
 CEC/DocketGalati & Blek/Galati
3263211/2/2004 Final Determination of Compliance

212 page(s)
 CEC/DocketPlacer County Apcd/Christofk
3258510/22/2004 Roseville Energy Park Biological Resources Mitigation Summary - POS

7 page(s)
 CEC/Docket UnitCh2mhill/Davy
3256810/20/2004 Roseville Energy Park-Air Quality Concerns

5 page(s)
 CEC/Reede/docket UnitRoseville Joint Union High School District/Grimes
3255510/15/2004 Roseville Accident Data

8 page(s)
 CEC/Adams/docketsCity Of Roseville/Jensen
3249610/13/2004 Addendum to Wetland Delineation Report and Request for Wetland Verification-POS

20 page(s)
 CEC/Reede/docket UnitCh2mhill/Davy
3243510/6/2004 City of Roseville's Comments to the PSA - POS

6 page(s)
 CEC/ReedeCity Of Roseville/Robinson
3241510/1/2004 Supplemental Information to the Project Description

30 page(s)
 CEC/Reede/docket UnitCh2mhill/Davy
324009/29/2004 City of Roseville's Letter to Dr. James Reede regarding visual vapor plumes dated 9/29/04

5 page(s)
 CEC/Rodriguez/docket UnitGalati & Blek/Galati
323849/23/2004 Status Report #7.

2 page(s)
 CEC/DocketCEC/J. Reede
323759/22/2004 Cultural Resources Monitoring & Migation Plan (cd). POS

49 page(s)
 CEC/DocketRoseville/Ch2mhill
323489/16/2004 Report of Conservation, Roseville Energy Park, Placer Ranch Development.

1 page(s)
 Eric Bryant/Bryant, EsqCEC/Adams
323249/10/2004 Roseville Electric's Proposed Revision to CEC Staff's VIS-4. POS

4 page(s)
 CEC/DocketRoseville/Galati & Blek Llp
322479/3/2004 Roseville Electric's Status Report No. 6 - POS

4 page(s)
 CEC/Rodriguez/docket UnitGalati & Blek Llp/Galati
322128/27/2004 Status Report Number 6 - POS

5 page(s)
 CEC/Geesman/rosenfeldCEC/Reede
322078/27/2004 Issue Resolution Workshop. POS

5 page(s)
 CEC/DocketCEC/J. Reede
321988/26/2004 Request that the CEC include information in its 2005 Integrated Energy Report regarding the impact of Project Labor Agreements & Labor disputes on energy infrastructure development.

4 page(s)
 CEC/DocketAssemblyman Dave Cox
321958/26/2004 Request for the 2005 Integrated Energy Policy Report investigate the abuse of the permitting process by special interest groups with primary objective unrelated to environment protection.

28 page(s)
 CEC/DocketAbc
321868/26/2004 Roseville Electric's Cumulative Air Quality Impact Analysis. POS

6 page(s)
 CEC/DocketRoseville/Galati & Blek Llp
321848/26/2004 Application of County Noise Ordinance. POS

4 page(s)
 CEC/DocketCounty Of Placer/H. Heinzen
321668/24/2004 Letter from U.S. Army Engineer District to Tom Habashi, dated August 19, 2004 - POS

4 page(s)
 CEC/DocketGalati & Blek/Galati
321618/24/2004 U.S. Army Corps of Engineers Response to The applicant's Request for Verification of Authorization by Nationwide Permit Number (NWP) 39 - POS

5 page(s)
 City Of Roseville/HabashiU.s. Army/Habashi
320968/12/2004 Revised site plan, layout, and construction laydown plan./POS

6 page(s)
 CEC/Dockets/reedeCh2mhill/Davy
320928/11/2004 Supplemental Comments on the Preliminary Staff Assessment for the Roseville Energy Park Project.

49 page(s)
 CEC/DocketsGalati&blek/Galati
320248/3/2004 Final West Roseville Specific Plan

220 page(s)
 CEC/EllerCh2mhill/Davy
320238/2/2004 Preliminary Staff Assessment/PSA for Roseville Energy Park

2 page(s)
 CEC/DocketsJ. Mckinsey
319757/26/2004 CD copy of the plume modeling files. POS

4 page(s)
 CEC/D. Edwards/docketAspen
319637/26/2004 Report on tactics used by California Unions for Reliable Energy (CURE).

25 page(s)
 CEC/DocketAbc/M. Tennis
319297/21/2004 EPA Comments to Placer County APCD regarding the PDOC

6 page(s)
 CEC/DocketCEC/Eller
319267/21/2004 Media clipping "Unions Push Roseville for Power Plant Pact"

3 page(s)
 CEC/DocketSacramento Business Journal/Lamb
319117/16/2004 "Energy Park accord draws closer look, Proposed labor agreement spurs debate with city officials" - media clipping dated Wednesday, July 14, 2004

2 page(s)
 CEC/DocketRoseville Press Tribune/Probst
318997/16/2004 Applicant's Preliminary Comments on the Preliminary Staff Assessment. POS

21 page(s)
 CEC/DocketsRoseville/Galati & Blek
318717/9/2004 Supplemental Filing for Biological Resources - Permit Application, Wetland Delineation Report, Biological Assessment, Rare Plant Survey Report - POS

491 page(s)
 CEC/Eller/docketsCh2mhil/Davy
318707/8/2004 Workshop Notice - PSA Workshop - POS

5 page(s)
 CEC/DocketsCEC/O'brian
318657/8/2004 Public Notice - Preliminary Determination of Compliance

1 page(s)
 CEC/DocketsPlacer County Air Pollution Control Dist
318647/8/2004 Preliminary Determination of Compliance

2 page(s)
 CEC/TherkelsenPlacer County Air Pollution Control Dist/Finnell
318376/30/2004 Staff's comments regarding the Preliminary Determination of Compliance for the Roseville Energy Park./POS

6 page(s)
 John Finnell/Placer County Air Pollution Control DCEC/O'brien
318366/30/2004 Report of Conservation, Location of CA-Pla-137./POS

4 page(s)
 CEC/ReinoehlDoug Davy
318336/30/2004 Status Report #5/POS

5 page(s)
 Geesman/RosenfeldCEC/Eller
318206/28/2004 Notice of Availability Preliminary Staff Assessment for the Roseville Energy Park.

3 page(s)
 Notice Of AvailabilityCEC Cec
318196/28/2004 Request for Agency Comments on the Preliminary Staff Assessment for the Roseville Energy Park (03-AFC-1).

1 page(s)
 Agency Distribution ListCEC/Richins
318186/28/2004 Document Handling for the Roseville Energy Park (03-AFC-1)

3 page(s)
 Librarian/Members Of The PublicCEC Cec
318126/25/2004 Roseville Energy Park Preliminary Staff Assessment - POS

509 page(s)
 CEC/DocketsCEC Cec
318086/25/2004 Application Status Report # 5 - POS

4 page(s)
 CEC/DocketsGalti & Blek/Galati
316095/27/2004 Roseville Energy Park Status Report #4 - POS

5 page(s)
 CEC/Geesman/rosenfeld/docket UnitCEC/Eller
316045/27/2004 Placer County Air Pollution Control District's Preliminary Determination of Compliance

123 page(s)
 CEC/Rodriguez/docket UnitGalati & Blek/Galati
316005/26/2004 Applicant's Status Report #4

4 page(s)
 CEC/Rodriguez/dockets UnitGalati & Blek/Galati
315995/26/2004 Preliminary Determination of Compliance

121 page(s)
 CEC/Therkelsen/docket UnitPlacer County Air Pollution Control District/Chris
315875/25/2004 Roseville Electric and CURE Stipulation Relating to CURE Data Requests

3 page(s)
 CEC/Rodriguez/docket UnitGalati & Blek/Galati
315865/25/2004 Report of Conversation re: EDD's Labor Market Information

1 page(s)
 California Edd/VaderCEC/Diamond
314435/11/2004 CURE's Data Requests, Set One (#1-41)

32 page(s)
 Roseville Electric/HrenAdams Broadwell Joseph & Cardozo/Gulessarian
314295/10/2004 Negotiations underway in West Roseville Lawsuit-Traffic, air quality cited as main concerns among those opposed to new housing development

2 page(s)
 CEC/DocketThe Press Tribune
314275/10/2004 Applicant's Status Report No 3

6 page(s)
 CEC/DocketGalati & Blek/Galati
314025/6/2004 ROC - - Joe Loyer, CEC, and John Finnell, Placer County APCD, re: Revised expected release date for PDOC.

1 page(s)
 CEC/DocketsCEC/J. Loyer
313755/3/2004 Email re: all constructed arterial roads in the City of Roseville; Class II bike lanes in Place.

2 page(s)
 CEC/DocketsCity Of Roseville/M. Wixon
313725/3/2004 Placer County General Plan Update - - Countywide General Plan POLICY DOCUMENT.

3 page(s)
 CEC/DocketsPlacer County
313715/3/2004 Email from City of Roseville, Rob Jensen, to Jim Adams, re: status of future improvements to Fiddyment Road, Baseline Road, Pleasant Grove Boulevard, & Blue Oaks Boulevard in the vicinity of the Energy Facility, & potential conflicts between those improvements.

2 page(s)
 CEC/J. Adams/docketsCity Of Roseville/R. Jensen
313705/3/2004 Letter from City of Roseville's re: existing & proposed intersection geometries, accident rates, funding mechanisms & improvement timing for various intersections related to the Roseville Energy Park.

3 page(s)
 CEC/James Adams/docketsCity Of Roseville/S. Gandler, P.e.
313695/3/2004 Report of Conversation - - James Adams, CEC, Kelly Wickline, City of Roseville, re: Roseville Waste Water Treatment Facility.

1 page(s)
 CEC/DocketsCEC/J. Adams
313685/3/2004 Report of Conversation - - James Adams, CEC, and Susannah Altonan, City of Roseville, re: Traffic counts for selected streets in Roseville.

1 page(s)
 CEC/DocketsCEC/J. Adams
313504/30/2004 Roseville Energy Park Status Report #3. POS

5 page(s)
 CEC/DocketsCEC/B. Eller
313244/28/2004 Maps Showing Construction Laydown/Parking/Office Areas

5 page(s)
 CEC/Eller/docket UnitCh2mhill/Davy
313234/27/2004 Report of Conservation between Dr. Joseph Diamond and Dr. Fatuma Yusuf, regarding REP Project construction/capital costs are in 2006 dollars.

1 page(s)
 CEC/Dockets/yusufCEC/Diamond
312654/16/2004 Biological Issue Resolution Workshop - POS

3 page(s)
 All Interested Parties/DocketCEC/O'brien
312454/15/2004 Comments RE: Corridor Study Report for Roseville

8 page(s)
 Dtsc/Gillette/cec/docketsAvanti Environmental/Manzo
312224/12/2004 Corrections to Air Quality Data Tables - POS

16 page(s)
 CEC/Eller/docketsCh2mhill/Davy
312034/7/2004 Report of Conversation between Stuart Itoga, Adam Zerrener, USFWS and Will Ness, USACE on 3-09-04 regarding Mitigation for wetlands/sensitive species associated with REP

1 page(s)
 CEC/DocketCEC/Itoga
312024/7/2004 Report Of Conversation between Stuart Itoga and Jeff Finn, DFG on 3-19-04 regarding Mitigation for REP Impacts

1 page(s)
 CEC/DocketCEC/Itoga
311954/6/2004 Email Report of Conversation between Doug Davy and Fatuma Yusuf regarding Year of Cost Estimates

1 page(s)
 CEC/Diamond/docketsCh2mhill/Yusuf
311924/6/2004 Supplement Filing -- Evaluation of Indirect & Induced Economic Effects from Construction & Operation of the Roseville Energy Park. POS

6 page(s)
 CEC/B. EllerCh2mhill/D. Davy, Project Manager
311864/1/2004 Data Response and Issue Resolution Workshop - Roseville Energy Park

6 page(s)
 CEC/DocketCEC/O'brien
311804/2/2004 APPLICANT'S RESPONSES TO CEC STAFF DATA REQUESTS 72-85. POS

288 page(s)
 CEC/DocketsRoseville Energy Park/Ch2mhill
311583/25/2004 Applicant's Status Report #2 for the Roseville Energy Park (03-AFC-1).

6 page(s)
 CEC/Dockets/rodriguezGalati & Blek Llp/Phelps
311573/25/2004 Roseville Energy Park (03-AFC-1) Status Report #2. POS

6 page(s)
 CEC/Geesman/rosenfeldCEC/Eller
311503/24/2004 Air Emission Offsets, Revised Request for Confidential Designation, Roseville Energy Park, Docket No. 03-AFC-1

6 page(s)
 Scott A. Galati, Esq.CEC/Therkelsen
3112910/30/2003 Application for Certification Volumes I & II

0 page(s)
 CEC/Therkelsen/docketRoseville Electric/Habashi
310783/9/2004 Roseville Energy Park Second Round Data Requests - POS

10 page(s)
 Roseville Electric/Hren/cec/docketsCEC/Eller
310473/4/2004 Responses to CEC questions regarding the Screening Study dated June 24, 2003

4 page(s)
 CEC/Ng/docketWapa/Farm
310403/3/2004 Report of Conversation with Stuart Itoga regarding Biology Data Responses Round 1

2 page(s)
 CEC/EllerCh2mhill/Davy
310313/1/2004 Applicant's RESPONSES to CEC Staff Data Requests 70-71. POS

85 page(s)
 CEC/DocketsCh2mhill/D. Davy, Ph.d.
310032/26/2004 Air Emission Offsets, Revised Confidentiality & Supplemental Application.

1 page(s)
 CEC/S. Galati, Esq./docketsCEC/F. Deleon
310022/26/2004 Letter from Charles E. Schneider, Enron, to Tom Habashi, City of Roseville, Re: Purchase & Sale of Emission Reduction Credits, dated February 25, 2004. POS

3 page(s)
 CEC/DocketsS. Galati, Roseville Energy Park
310012/26/2004 Applicant's Status Report #1. POS

5 page(s)
 CEC/DocketsS. Galati, Roseville Energy Park
309952/26/2004 Status Report # 1 for Roseville Energy Park - POS

6 page(s)
 CEC/Geesman/rosenfled/docketsCEC/Eller
309752/24/2004 Applicant's Response to CEC Staff Data Request 57--Spill Prevention, Control, & Countermeasures Plan for Operation. POS

28 page(s)
 CEC/DocketsCh2mhill/D. Davy
309732/24/2004 Report of Conversation between Joe Diamond, CEC, and Captain Noel Neves, Roseville Police Dept., re: Additional law enforcement information for socioeconomics for the Roseville Energy Park Project.

1 page(s)
 CEC/DocketsCEC/J. Diamond
309702/23/2004 CONFIDENTIAL --- Applicant's Revised Request for Confidential Designation: Air Quality ERC Table.

5 page(s)
 CEC/DocketsRoseville Energy Park/Galati & Blek Llp
309522/19/2004 Applicant's Response to CEC Staff Data Request 55 Storm Water Pollution Prevention Plan for Construction for the Roseville Energy Park

128 page(s)
 CEC/Eller/docketsCh2mhill/Davy
308662/9/2004 Roseville Energy Park Proof of Service List/POS

4 page(s)
 All PartiesCEC/Read
308572/6/2004 Applicant's Responses to CEC Staff Data Requests 1-71, Roseville Energy Park

278 page(s)
 CEC/EllerCh2mhill/Davy
308212/3/2004 Committee Scheduling Order - POS

6 page(s)
 CEC/DocketsCEC/Rosenfeld/geesman
307981/29/2004 Comment re: Roseville Electric and the City of Roseville on their effort to build a 160-megawatt generation facility.

1 page(s)
 CEC/DocketsTim Leslie, Assemblyman, 4th Dist., California Leg
307901/28/2004 Sign-in Sheets from the Walnut Energy Park Data Request Workshop held on January 28, 2004

3 page(s)
 CEC/DocketCEC Cec
307701/22/2004 Email Comments re: Roseville Energy Park.

1 page(s)
 CEC/Public Advisor/docketsBruce Singer, Resident
307521/16/2004 Roseville Energy Park Issue Identification Report/POS

10 page(s)
 Geesman/RosenfeldCEC/Eller
307451/14/2004 Order Granting Petition to Intervene/POS

4 page(s)
 CEC/DocketsCEC/Geesman
307281/13/2004 Roseville Energy Park -- Commission Determination that the Application for Certification is Complete.

2 page(s)
 CEC/DocketsCEC Cec
307051/7/2004 Data Requests - POS

32 page(s)
 Roseville/Hren/cec/docketsCEC/Eller
306931/5/2004 Notice of Public Informational Hearing and Site Visit (1/28/04) - POS

8 page(s)
 CEC/DocketsCEC/Geesman/rosenfeld
3069012/31/2003 Petition To Intervene by California Unions for Reliable Energy (CURE)

5 page(s)
 CEC/DocketAdams Broadwell Joseph & Cardozo/Heeley
3064512/19/2003 Roseville Energy Park --- Hearing Officer Assignment.

1 page(s)
 CEC/DocketsCEC Cec
3063012/17/2003 Commission Determination that the Application for Certification is Complete

2 page(s)
 CEC/DocketThe Commissioners
3061112/17/2003 Librarian Distribution Letter for the Roseville Energy Park Application for Certification.

3 page(s)
 CEC/DocketsCEC/P. Richins
3061012/17/2003 Agency Distribution Letter for the Roseville Energy Park Application for Certification.

2 page(s)
 CEC/DocketsCEC/P. Richins/
3059612/12/2003 Denial of the Air Emission Offsets, Confidentiality and Supplemental Application

3 page(s)
 Galati & Blek/Galati/cec/docketsCEC/Deleon
3059512/12/2003 Roseville Energy Park Data Adequacy Recommendation

43 page(s)
 CEC/Commissioners/docketsCEC/Therkelsen
3054212/9/2003 Commission Determination that the Application for Certification is Incomplete, Order No. 03-1203-02

2 page(s)
 CEC CecCEC/Pernell
3054112/9/2003 Cultural & Paleontological Resources Applications for Confidentiality

2 page(s)
 Galati & Blek/GalatiCEC/Therkelsen
3054012/8/2003 Supplement in Response to Data Adequacy Comments

65 page(s)
 CEC/DocketRoseville Electric/Habashi
3048211/26/2003 Placer County APCD Completeness Letter

1 page(s)
 CEC/EllerPlacer Couinty Apcd/Christofk
3048111/26/2003 Data Adequacy Recommendation for Roseville Energy Park (03-AFC-1)

71 page(s)
 CEC/Keese/pernell/rosenfeld/geesman/boydCEC/Therkelsen
3046711/24/2003 Application for Confidential Designation and Table 8.1G-1, the November 24, 2003 Updated ERC Table for Roseville Energy Park

2 page(s)
 CEC/DocketsGalati & Blek/Galati
3044611/19/2003 Application for Confidential Designation and Supplement to Section 8.1.6.3 and Appendix 8.1-I, Emission Reduction Credits

4 page(s)
 CEC/DocketsGalati & Blek/Galati
3044511/19/2003 Application for Confidential Designation and Appendix 8.8-A, Paleontological Resources Location Data and Map

4 page(s)
 CEC/DocketsGalati & Blek/Galati
3044411/19/2003 Application for Confidential Designation and Appendix 8.1-I, Emission Reduction Credits

4 page(s)
 CEC/DocketGalati & Blek/Galati
3044311/19/2003 Application for Confidential Designation and Appendices 8.3-C, 8.3-D and 8.3-E for Roseville Energy Park

4 page(s)
 CEC/DocketsGalati & Blek/Galati
3026910/30/2003 Request for Agency Participation in the review of the Roseville Energy Park

3 page(s)
 Agency Distribution ListCEC/Richins
3026810/30/2003 Document Handling for Roseville Electric, Roseville Energy Park

3 page(s)
 CEC/DocketCEC/Richins
3026710/30/2003 Notice of Receipt-Application for Certification (AFC)-Roseville Energy Park (03-AFC-1)

2 page(s)
 CEC/DocketCEC/Richins
1796-02/5/2004 Committee Hearing

87 page(s)
  CEC