221764 | 11/14/2017 |
Order Terminating Commission Certification for the Black Rock 1, 2 and 3 Geothermal Power Project Order No: 17-1108-1b 2 page(s)
| | CEC/Dockets | California Energy Commission |
221323 | 9/27/2017 |
Black Rock 123 - Notice of Receipt for Termination Request 20170927 Black Rock 123 - Notice of Receipt for Termination Request 20170927 Compliance 2 page(s)
| | CEC/Dockets | California Energy Commission |
217884 | 6/6/2017 |
Request to Terminate License for Black Rock 1, 2, and 3 Geothermal Project
2 page(s)
| | CEC/Dale Rundquist | CAL Energy Operating Corporation |
203480 | 12/26/2014 |
Order Approving a Petition to Extend the Deadline for Commencement of Construction
4 page(s)
| | | California Energy Commission |
203470 | 12/19/2014 |
Notice of Decision
1 page(s)
| | | California Energy Commission |
203314 | 11/5/2014 |
Staff Analyses of Petition to Extend the Start of Construction
13 page(s)
| | Interested Parties | California Energy Commission |
202618 | 6/26/2014 |
Notice of Receipt for the Petition to Extend Deadline for Commencement of Construction
2 page(s)
| | CEC/Dockets Unit | California Energy Commission |
202460 | 6/16/2014 |
Construction Deadlline Extension Request Petition to Amend to Extend Construction Deadline 2 page(s)
| | CEC / Dale Rundquist | CEOBSIDIAN Energy S. Larson / CEC |
63145 | 12/15/2011 |
Notice of Decision
1 page(s)
| | Air Resources Board | CEC/ D. Rundquist |
63143 | 12/15/2011 |
Order Approving a Petition to Extend the Deadline for Commencement of Construction
2 page(s)
| | CEC/ Docket Unit | CEC/ H. Kallemeyn |
62885 | 11/14/2011 |
Staff's Analysis and Recommendation RE the Requested Ext. of the Deadline for Commencement of Construction
4 page(s)
| | CEC/Dockets Unit | CEC/M.Tran |
62650 | 10/27/2011 |
Notice of Receipt to Extend Deadline for Commentcement of Construction
3 page(s)
| | CEC/ Docket Unit | CEC/ C. Marxen |
62636 | 10/25/2011 |
NOTICE OF RECEIPT PETITION TO EXTEND THE DEADLINE FOR COMMENCEMENT OF CONSTRUCTION
3 page(s)
| | Dockets | CEC/ Marxen |
61689 | 8/3/2011 |
Petition to Request Three Year Extension to License
2 page(s)
| | CEC/ D. Rundquist | CEOBSIDIAN/ S. Larsen |
59628 | 2/7/2011 |
Notice of Decision Compliance
1 page(s)
| | CEC/ Docket Unit | CEC/ D. Rundquist |
59625 | 2/7/2011 |
Order Approving a Petition to Revise the Salton Sea Unit 6 Geothermal Power Plant to become the Black Rock 1,2 and 3 Geothermal Plant
2 page(s)
| | CEC / Docket Unit | CEC/ K. Douglas |
59514 | 1/21/2011 |
Back up Water Supply Amendment *** This document has never existed. A clerical error was made when inputting data. *** 22 page(s)
| | CEC/ Docket Unit | Walnut Energy Center Authority |
59254 | 12/15/2010 |
Document Handling for the Black Rock 1, 2, and 3 Staff Assessment
1 page(s)
| | Library | CEC/ C. Marxen |
59192 | 12/9/2010 |
Notice of Availibility
3 page(s)
| | CEC/Docket Unit | CEC/C. Marxen |
59129 | 12/3/2010 |
Staff Assessment
402 page(s)
| | CEC/ Docket Unit | CEC/ C. Stora |
59007 | 11/15/2010 |
Imperial County Conditional Use Permit
222 page(s)
| | CEC | Imperial County Planning and Development Services |
58474 | 9/15/2010 |
Revised Air Pollution Control District Determination of Compliance
31 page(s)
| | CEC/ Docket Unit | Imperial County Air Pollution Control District |
58473 | 9/15/2010 |
Air Pollution Control District Determination of Compliance
39 page(s)
| | CEC/ Docket Unit | Air Pollution Control District/ T. Brinkerhoff |
57563 | 7/13/2010 |
Air Pollution Control District Determination of Compliance
39 page(s)
| | CEC/M. Layton | Imperial Co. Air Pollution Control District/T. Brinkerhoff |
56969 | 6/2/2010 |
Comments on PDOC.
4 page(s)
| | CEC/ Docket Unit | CEC/ M. Layton |
56394 | 4/23/2010 |
MU Between CEC & Imperial County Planning & Building Dept.
6 page(s)
| | CEC/T. O'Brien | Imperial County/J. Heuberger |
55880 | 3/15/2010 |
Letter from Preston Arrow-Weed to the CA Native American heritage Commission Regarding Obsidian Butte
1 page(s)
| | California Heritage Commission/Dave Singleton | P. Arrow-Weed |
55786 | 3/8/2010 |
Letter Regarding Water Supply for Black Rock 1, 2 & 3
2 page(s)
| | Downey Brand/Z. Walton | Imperial Irrigation District/T. Shields |
55719 | 3/1/2010 |
Ethnographic Assessment of the Importance of Obsidian Butte to the Native American Community, Imperial County, California
43 page(s)
| | CEC | North State Resources, Inc./ Dr. Thosmas Gates/ Kristina Crawford |
55713 | 3/1/2010 |
Addendum to the Petition to Amend Revised Water Use
3 page(s)
| | CEC/ Docket Unit | CE Obsidian Energy/ S. Larsen |
55687 | 2/24/2010 |
Draft Waste Discharge Requirements for the Power Plant Major Amendment Proceeding
80 page(s)
| | CEC/ Docket Unit | CEC/ M. Trask |
54979 | 1/22/2010 |
Sampling Protocol
2 page(s)
| | CEC/ E. Townsend-Hough | Brownfields & Environmental Restoration Program/G. Holmes |
54775 | 1/11/2010 |
E-mail from J. Salami and to Jim Adams
3 page(s)
| | CEC/ Docket Unit | CEC/ J.Adams |
54694 | 1/5/2010 |
Report of Conversation Regarding Project Impact
1 page(s)
| | Imperial County Planning Dept/ J. Minnick | CEC/ J. Adams |
54094 | 11/16/2009 |
Data Responses to Data Request 1 to 64
406 page(s)
| | CEC/ Docket Unit | CH2MHILL |
53780 | 10/26/2009 |
Letter for Document to be Removed
1 page(s)
| | CEC/ Docket Unit | Galati & Blek/ D. Wiseman |
53767 | 10/23/2009 |
Phase II Amendment
297 page(s)
| | CEC/ Docket Unit | Galati Blek/ D. Wiseman |
53701 | 10/20/2009 |
Request for Air Emission Control Technology Change
2 page(s)
| | CEC/ J. Caswell | CE Obsidian Energy LLC/ D. Hackley |
52804 | 8/10/2009 |
Application/ Report of Waste Discharge
34 page(s)
| | State Water Resources Control Board | CE Obsidian Energy |
52668 | 8/3/2009 |
Approval of Request for Project Name Change - Black Rock 1, 2, and 3 Geothermal Project
1 page(s)
| | CE Obsidion Energy/ Doug Hackley | CEC/ J. Caswell |
52667 | 8/3/2009 |
Revised Request for Project Name Change to Black Rock 1, 2, & 3 Geothermal
1 page(s)
| | CEC/ J. Caswell | CE Obsidian Energy/ D. Hackley |
52600 | 7/29/2009 |
Request for Project Name Change to Black Rock 1, 2, & 3
1 page(s)
| | CEC/ J. Caswell | CE Obsidian Energy/ D. Hackley |
52584 | 7/27/2009 |
Application for Confidential - Data Request Responses 39, 41 & 50
11 page(s)
| | CEC/ M. Jones | Paul Hastings/ M. Sanders |
52583 | 7/27/2009 |
E-mail from Greg Holmes of the Department of Toxic Substances Control Clarifying the July 7th Letter to Ellie Townsend RE Phase I Environmental Site Assessment for Amended Salton Sea Unit 6 Project, Imperial County
1 page(s)
| | CEC/ M. Trask | Southern California Cleanup Operations/ G. Holmes |
52580 | 7/27/2009 |
Phase I Environmental Site Assessment for Amended Salton Sea Unit 6 Project, Imperial County
2 page(s)
| | CEC/ E. Townsend-Hough | Department of Toxic Substance Control/ G. Holmes |
52369 | 7/9/2009 |
Data Response Set 1A, Responses to CEC Staff Data Requests 47-53
7 page(s)
| | CEC/ M. Trask | CH2M Hill/ M. Finn |
51975 | 6/15/2009 |
Letter from Dept of Toxic Substance in Response to Agency Participation Request
2 page(s)
| | CEC/ M. Trask | Dept of Toxic Substance/ G. Holmes |
51756 | 5/29/2009 |
Amendment Data Request 1-64
27 page(s)
| | CalEnergy/ D. Hackley | CEC/ M. Trask |
51561 | 5/13/2009 |
Request for Agency Participation in the Review of the Petition for a Major Amendment
5 page(s)
| | Agency Distribution List | CEC/ E. Allen |
50765 | 4/1/2009 |
Notice of Receipt Petition to Amend
3 page(s)
| | CEC/ Docket Unit | CEC/ E. Allen |
50484 | 3/13/2009 |
aIR quality Modeling and Health Files
1 page(s)
| | CEC/ Dale Rundquist | CE Obsidian Energy/ Doug Hackley |
50483 | 3/13/2009 |
Amendment Petition VOL 1 & 2
1000 page(s)
| | CEC/ Dale Rundquist | CE Obsidian Energy/ Doug Hackley |
46635 | 6/9/2008 |
Order No. 07-1219-4, Order Approving Extension of the Deadline for Commencement Construction
1 page(s)
| | CEC/ Docket Unit | CEC/ J. Pfannenstiel |
43420 | 11/19/2007 |
Notice of Receipt- Request to extend the Commencement of Construction Deadline.
2 page(s)
| | CEC | CEC/ R. Johnson |
43381 | 11/15/2007 |
Notice of Receipt Petition to Amend the Energy Commission Decision for the Salton Sea Unit 6 Project
5 page(s)
| | CEC / Docket Unit | CEC / R. Johnson |
43334 | 11/13/2007 |
Letter requesting a three year extension to an existing permit.
2 page(s)
| | CEC / D. Rundquist | CALENERGY / S. Larsen |
39999 | 4/13/2007 |
CO Obsidian Application for Certification Extender
2 page(s)
| | CEC/C. Bruins | CalEnergy/V. Signorotti |
34966 | 7/18/2005 |
Minor Amendment No 1 to Cup 02-0028 For Obsidian Salton Sea Unit #6 APS #020-110-08-01/185 MW Power Plant
220 page(s)
| | Docket Unit | Imperial Co. Planning & Development Services / R. Cabanilla |
34626 | 6/15/2005 |
Notice of Decision by the CEC for Salton Sea
1 page(s)
| | CA Resources Agency/CEC/Dockets | CEC/Bruins |
34211 | 5/4/2005 |
Final Decision of Compliance
40 page(s)
| | CEC/Docket Unit | Ce Obsidian Energy/Imperial County Air Pollution C |
33971 | 4/20/2005 |
230kV System Impact Study Power Flow Impacts
71 page(s)
| | CEC/Docket Unit | Kr Saline & Associates Plc |
33970 | 4/20/2005 |
Staff Analysis of Proposed Modifications to add a Binary-cycle Turbine and Increase Generation
72 page(s)
| | Interested Parties/Cec/docket Unit | CEC/Bruins |
33932 | 4/15/2005 |
Amendment 1 Comments to Air Pollution Control District
4 page(s)
| | Dockets | Cd Obsidian Energy |
33931 | 4/15/2005 |
Notice Determination of Compliance with Air Emissions Rules & Regulations
46 page(s)
| | Dockets | Ce Obsidian Energy |
33930 | 4/15/2005 |
SSU6 Brun Cessation Data
23 page(s)
| | CEC/Bruins | Aspen/Walters |
33010 | 12/27/2004 |
Salton Sea Unit 6 License Amendment 1
242 page(s)
| | CEC/Docket | Ch2mhill |
31559 | 5/20/2004 |
Establishment of Post-Certification mailing list for Salton Sea Unit 6 Project.
2 page(s)
| | CEC/Dockets | CEC/C. Bruins |
30724 | 1/13/2004 |
Adoption of the Decision of the Salton Sea Project and incorporates the PMPD.
2 page(s)
| | CEC/Dockets | CEC/Commissioners |