Docket Log

Docket: 01-AFC-24C
Project Title: Palomar Energy Project Compliance
Generated On: 3/29/2024 1:13:13 AM

Include:     
TN #Docketed DateDocument TitleExhibit #ToFrom
2544362/13/2024 Palomar Energy Project Compliance
Palomar Energy Center 2023 Annual Report
44 page(s)
 Keith WinsteadSan Diego Gas and Electric
2487982/14/2023 Palomar Energy Center 2022 Annual Compliance Report
Palomar Energy Center 2022 Annual Report
Compliance
47 page(s)
 CEC/Keith WinsteadSan Diego Gas and Electric
2427094/19/2022 Statement of CEC Staff Approval of Post Certification Change
Hydrogen generation and energy storage clean energy project
27 page(s)
 CEC/Docket UnitCalifornia Energy Commission
2421853/1/2022 Petition to Amend - Palomar Hydrogen Project - update

Compliance
117 page(s)
 CEC/Docket UnitSan Diego Gas and Electric
2419692/25/2022 Palomar Energy Center 2021 Annual Compliance Report
Palomar Energy Center 2021 Annual Report
Compliance
47 page(s)
 CEC/Keith WinsteadSan Diego Gas and Electric
2419672/25/2022 SDG&E Palomar Energy Center, LLC
Authority to Construct
Air Quality
31 page(s)
 CEC/Docket UnitCalifornia Energy Commission
24109612/30/2021 STATEMENT OF STAFF APPROVAL OF POST-CERTIFICATION CHANGE
Palomar Energy Center 01-AFC-24C install two nitrogen concentrator systems (NCS), one on each of the PEC’s heat recovery steam generators
Compliance
11 page(s)
 CEC/Docket UnitCalifornia Energy Commission
24063511/18/2021 Notice of Receipt - Petition for Post Certification Project Change

3 page(s)
 CEC/Docket UnitCalifornia Energy Commission
24008510/15/2021 Palomar Energy Center - Petition to Amend
Nitrogen Project
88 page(s)
 Keith WinsteadSan Diego Gas and Electric
2396849/13/2021 Notice of Receipt
Petition for Post Certification Project Change Palomar Energy Center
Compliance
3 page(s)
 CEC/Docket UnitCalifornia Energy Commission
2393308/16/2021 Palomar Energy Center - Petition to Amend - Update
Palomar Hydrogen Project - 08/16/2021 update
Compliance
107 page(s)
 CEC/Keith WinsteadSan Diego Gas and Electric
2392998/12/2021 Palomar Energy Center - Petition to Amend
Palomar Hydrogen Project
Compliance
106 page(s)
 CEC/Keith WinsteadSan Diego Gas and Electric
2369443/1/2021 Palomar Energy Center 2020 Annual Compliance Report
Palomar Energy Center 2020 Annual Compliance Report
Compliance
46 page(s)
 CEC/DocketsSan Diego Gas and Electric
2322442/27/2020 Palomar Energy Center 2019 Annual Compliance Report

Compliance
45 page(s)
 CEC/Docket UnitSan Diego Gas and Electric
23112112/11/2019 Palomar Energy Center 2018 ACR

Compliance
43 page(s)
 CEC/Keith WinsteadSan Diego Gas and Electric
22562710/30/2018 Compliance Docketing Policy

3 page(s)
 Plant ManagerCalifornia Energy Commission
2221061/8/2018 Order Approving Petition to Amend the Facility License

2 page(s)
 CEC/DocketsCalifornia Energy Commission
22196512/13/2017 Notice of Decision for Petition to Amend Regarding Cooling Water
The amendment requests to augment cooling tower makeup water with (1) fire hydrant flushing water, and (2) storm water captured onsite.
1 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22196412/13/2017 Notice of Decision for Petition to Amend Regarding Air Quality
The amendment requests to (1) modify certain air quality conditions of certification to be consistent with the most recent San Diego County Air Pollution Control District (SDAPCD) air permit to operate; and (2) upgrade the advanced gas path technology for two existing General Electric Frame 7-FA combined-cycle gas turbines.
1 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22188812/1/2017 December 13, 2017 Business Meeting Agenda

6 page(s)
 CEC/DocketsCalifornia Energy Commission
22186911/28/2017 John Price Comments Polution coming out of plant

Air Quality
1 page(s)
 CEC/Docket UnitJohn Price
22171611/9/2017 Staff Analysis of Petition to Amend to Augment Cooling Water

21 page(s)
 CEC/DocketsCalifornia Energy Commission
22170711/9/2017 Staff Analysis of Air Quality Petition to Amend

96 page(s)
 CEC/Docket UnitCalifornia Energy Commission
2205138/2/2017 Notice of Receipt of the Petition to Amend the Energy Commission Decision for the Palomar Energy Center Project

2 page(s)
 CEC/DocketsCalifornia Energy Commission
2204717/31/2017 Petition for Change of the Project Description in the Final Decision to Augment Cooling Tower Makeup Water With Water Reclaimed
Petition for Change of the Project Description in the Final Decision to Augment Cooling Tower Makeup Water With Water Reclaimed Onsite
19 page(s)
 CEC/Docket UnitSan Diego Gas & Electric Company (SDG&E)
2138409/29/2016 SDG&E request not to Include in CEC analysis the SDAPCD Conditions 50 through 55 included in the ATC
On June 21, 2016 SDG&E requested that California Energy Commission not incorporate in the pending amendments analysis the Conditions 50 through 55 imposed by the June 20 2016 Authority to Construct (ATC) issued by San Diego Air Pollution Control District (SDAPCD).
Air Quality
1 page(s)
  California Energy Commission
2130788/30/2016 Report of Conversation Regarding Recycled Water Outage
Communication between Palomar Energy Center and City of Escondido Hale Avenue Resource Recovery Facility (HARRF) regarding Recycled Water Outage
Soil and Water
5 page(s)
 CEC/Docket UnitCalifornia Energy Commission
2119856/27/2016 County of San Diego Air Pollution Control District Authority to Construct for Power Station Unit No.2 (East or Unit No.2)
Authority to Construct is granted pursuant to Rule 20 of the Air Pollution Control District Rules and Regulations for equipment to consist of: Power Station Unit No.2 (East or Unit No.2) consisting of: one 176 MW rated natural-gas fired combined cycle General Electric Power Systems Frame 7FA gas turbine generator (combustion turbine), max heat input 1765 MMBtu/hr, S/N 298257, with dry low-NOx combustors, a heat recovery steam generator, a 195 MMbtu/hr (HHV) auxiliary duct burner, a Peerless Selective Catalytic Reduction unit (SCR) [ with a Cormetech catalyst block, a Peerless Ammonia Vaporizer Skid], an Engelhart oxidation catalyst, a steam turbine generator shared with Power Station Unit No. 1, and an Emerson Ovation control system with lowload emissions and startup fuel gas heating capability.
Air Quality
9 page(s)
 CEC/Dockets UnitCalifornia Energy Commission
2119846/27/2016 County of San Diego Air Pollution Control District Authority to Construct for Power Station Unit No.1 (West or Unit No.1)
Authority to Construct is granted pursuant to Rule 20 of the Air Pollution Control District Rules and Regulations for equipment to consist of: Power Station Unit No.1 (West or Unit No.1) consisting of: one 176 MW rated natural-gas fired combined cycle General Electric Power Systems Frame 7FA gas turbine generator (combustion turbine), max heat input 1765 MMBtu/hr, S/N 298258, with dry low-NOx combustors, a heat recovery steam generator, a 195 MMbtu/hr (HHV) auxiliary duct burner, a Peerless Selective Catalytic Reduction unit (SCR) [with a Cormetech catalyst block, a Peerless Ammonia Vaporizer Skid], an Engelhart oxidation catalyst, a steam turbine generator shared with Power Station Unit No. 2, and an Emerson Ovation control system with lowload emissions and startup fuel gas heating capability
Air Quality
9 page(s)
 CEC/Dockets UnitCalifornia Energy Commission
2105312/25/2016 Request to combine petitions to amend
San Diego Gas & Electric Company – Palomar Energy Center (01-AFC-24) Request to Recombine Petitions to Amend to: (1) Upgrade the Advanced Gas Path Technology of the Combustion Turbine; and (2) Conform Air Quality Conditions with the San Diego Air Pollution Control District’s Permit to Operate
Air Quality, Compliance
2 page(s)
 CEC/Mr. Jonathan Fong Compliance Project ManagerSempra Energy Company/SDGE
2071841/5/2016 Palomar Energy Center 2014 Particulate Emissions Investigation Report

Compliance
12 page(s)
 CEC/Dockets UnitCalifornia Energy Commission
20689512/8/2015 Second Addendum to Petition to Amend Air Quality Conditions of Certification

Air Quality, Compliance
2 page(s)
 California Energy CommissionCalifornia Energy Commission
2041664/14/2015 Palomar Energy Center Addendum to Air Quality Petition to Modify

Air Quality
70 page(s)
 CEC/Docket UnitCalifornia Energy Commission
2040534/3/2015 SDG&E's Request For Business Meeting Continuance
April 8th Business Meeting Continuance Request
1 page(s)
 CEC/Jonathan FongSan Diego Gas & Electric (SDG&E)
2037723/5/2015 Staff Analysis for Palomar Energy Center (PEC) to Amend Air Quality Conditions of Certification
Document
Compliance
63 page(s)
  California Energy Commission
2029478/19/2014 Turbine 1 CEMS Startup Data 2011-2013

8 page(s)
  California Energy Commission
2029468/19/2014 Turbine 2 CEMS Startup Data 2011-2013

10 page(s)
  California Energy Commission
2029458/19/2014 Air Quality E-mail from Project

4 page(s)
 CEC / Dale RundquistCalifornia Energy Commission / Jason Dobbs
2005399/20/2013 Petition to Seperate two Amendments from SDG&E

Compliance
1 page(s)
 Energy CommissionSan Diego Gas & Electric
707615/10/2013 Notice of Decision

1 page(s)
 California Resources AgencyCEC/D.Rundquist
706985/9/2013 Order Approving Petition to Amend Air Quality Condition of Certification - AQ-SC13

2 page(s)
 CEC/Docket UnitCEC/H.Kallemeyn
699393/18/2013 Notice of Receipt - Petition to Amend
Gas Path Technology for two existing GE Frame 7-FA gas turbines
4 page(s)
 CEC/Docket UnitCEC/C.Marxen
697793/4/2013 CEC Staff Analysis of Proposed Modification to Amend Air Quality Condition of Certification AQ-SC13

8 page(s)
 Interested PartiesCEC/ D. Rundquist
696342/22/2013 Petition for Amendment to Upgrade the Advanced Gas Path Technology of the Combustion Turbines and to Conform Air Quality Conditions of Certification with Permit Conditions of the Revised Permit to Operate

65 page(s)
 CEC/Docket UnitSDG&E
690801/9/2013 Notice of Receipt

3 page(s)
 CEC/Docket UnitCEC/C.Marxen
6898212/28/2012 San Diego Gas and Electric Company's Petition for Change in the Hours Allowed for Maintenance and Testing of the Critical Services

5 page(s)
 CEC/Docket UnitSan Diego Gas & Electic Company/J.Dobbs
6895712/21/2012 Notice of DeterminationPetition to Amend the Administration Building

2 page(s)
 CEC/Docket UnitCEC/ C. Marxen
6862311/20/2012 Petition for Change of The Project Description, from Jason T. Dobbs. SDG&E

12 page(s)
 CEC/ Docket UnitSDG&E/ J. Dobbs
6827910/31/2012 Order Approving a Petition to Amend

2 page(s)
 CEC/Docket UnitCEC/H.Kallemeyn
6773510/16/2012 Notice of Decision

1 page(s)
 California Resources AgencyCEC/D.Dundquist
6773110/16/2012 Order Approving a Petition to Amend to Install a New Bridge Crane for Combustion Turbine Maintenance

2 page(s)
 CEC/Docket UnitCEC/H.Kallemeyn
670519/7/2012 Staff Analysis Regarding Bridge Crane Comments

2 page(s)
 CEC/ D. RundquistPublic/ M. Rodriguez
664998/7/2012 CEC Staff Analysis of Proposed Modifications

4 page(s)
 Interested PartiesCEC/ D. Rundquist
660597/2/2012 Notice of Determination

2 page(s)
 CEC/Docket UnitCEC/C.Marxen
655926/5/2012 Petition for Change of the Project Description in the Final Decision to Build a New Bridge Crane for Combustion Turbine Maintenance

11 page(s)
 CEC/D.RundquistSan Diego Gas & Electric Company/J.Dobbs
654725/29/2012 Petition for Change - Building of New Bridge Crane for Combustion Turbine Maintenance

11 page(s)
 CEC/D.RundquistSan Diego Gas & Electric/J.Dobbs
644403/27/2012 Notice of Determination - Petition to Install an Elevator for the Unit One Heat Recovery Steam Generator

2 page(s)
 CEC/Dockets UnitCEC/M.Errecart
638762/29/2012 Petition to Modify

14 page(s)
 CEC/Dockets UnitCEC/D.Rundquist
634671/27/2012 Notice of Determination - Petition to Install a New Gantry Crane

2 page(s)
 CEC/ Docket UnitCEC/ C. Marxen
6324812/29/2011 Petition for Change of the Project Description in the Final Decision

11 page(s)
 CEC/D.RundquistSan Diego Gas & Electric/J.Dobbs
6324012/28/2011 Notice of Determination to Expand Existing Cooling Tower Switch Gear

2 page(s)
 CEC/Dockets UnitCEC/C.Marxen
6317912/21/2011 Petition to Amend Project Description in the Final Decision to Expand an Existing Switch Gear Enclosure

10 page(s)
 CEC/ Docket UnitCEC/ D. Rundquist
6299911/28/2011 Petition for Change

8 page(s)
 CEC/ Docket unitSDGE
6289711/15/2011 SDG&E Petition for Change

10 page(s)
 CEC/ Docket UnitSDG&E
6247810/4/2011 Notice of Determination Approval to Expand and Existing Switch Gear Enclosure

1 page(s)
 San Diego Gas & ElectricCEC/ D. Rundquist
6247710/4/2011 Notice of Determination Approval of Electrical Parts Storage Warehouse

1 page(s)
 San Diego Gas and ElectricCEC/ D. Rundquist
622789/19/2011 Notice of Determination - Storage Warehouse

2 page(s)
 CEC/Dockets UnitCEC/M.Errecart
622779/19/2011 Notice of Determination- Switch Gear Enclosure

2 page(s)
 CEC/Dockets UnitCEC/M.Errecart
618918/16/2011 Public Comments from Mark Rodriguez regarding Audio Playback from CEC Website

2 page(s)
 CEC/ K. GraberPublic/ M. Rodriguez
618298/11/2011 SDG&E Petition to Modify Expand Existing Switch Gear Enclosure

13 page(s)
 CEC/ Docket UnitCEC/ D. Rundquist
618288/11/2011 Petiton to Modify Erect and Utilize Electrical Storage Warehouse

13 page(s)
 CEC/ Docket UnitCEC/ D. Rundquist
612436/30/2011 Record of Conversation with Geoff Lesh and Battalion Chief John Tenger

1 page(s)
 CEC/Dockets UnitCEC/D.Rundquist
611946/22/2011 Record of Conversation with Geoff Lesh and Mr.Barthel

1 page(s)
 CEC/Dockets UnitCEC/D.Rundquist
5931812/21/2010 Notice of Decision

1 page(s)
 CEC/ Docket UnitCEC/ D. Rundquist
5931012/15/2010 Order Approving a Petition to Install and Operate an Emergency Engine

3 page(s)
 CEC/ Docket UnitCEC/ Douglas
5894011/2/2010 Notice of Receipt - Petition to Amend - Request to Install Load Commutator Inverter

2 page(s)
 CEC/Docket UnitCEC/D. Rundquist
5893911/2/2010 Notice of Receipt - Petition to Amend to Erect Two Small Buildings

2 page(s)
 CEC/Docket UnitCEC/D. Rundquist
5888110/27/2010 Staff Analysis to Install & Operate Emergency Engine

10 page(s)
 Interested PartiesCEC/D. Rundquist
5875810/12/2010 Notice of Receipt - Petition to Amend Commission Decision

3 page(s)
 CEC/Docket UnitCEC/M. Errecart
585109/14/2010 Petition for Change of Project Description - Final Decision to Install & Operate Stirling Solar Dish

18 page(s)
 CEC/Docket UnitSan Diego Gas & Electric Company
585099/14/2010 Petition for Change of Project Description - Erect & Utilize Repair Shop and Water Lab Building

17 page(s)
 CEC/Docket UnitSan Diego Gas & Electric Company
580768/16/2010 Petition for Change of Project Description in Final Decision

14 page(s)
 CEC/Docket UnitSan Diego Gas & Electric Company
577097/22/2010 Staff Analysis & Memo to Interested Parties

9 page(s)
 CEC/ Docket UnitCEC/ D. Rundquist
574937/9/2010 Notice of Receipt

3 page(s)
 CEC/ Docket UnitCEC/ M. Errecart
568385/26/2010 Petition for change of the project description in final decision to install and operate an emergency engine.

24 page(s)
 CEC/ Docket UnitSDG&E/ E. Haury
566425/12/2010 Notice of Receipt, Petition to Amend to Modify Project

2 page(s)
 CEC/Docket UnitCEC/M. Errecart
561854/9/2010 Petition to Amend Final Decision to Install & Operate New Water Treatment Storage Tanks & Related Equipment

37 page(s)
 CEC/Docket UnitCEC/D. Rundquist
455903/6/2008 Order Dismissing Complaint RE: Condition of Certification VIS-4

1 page(s)
 CEC / Docket UnitCEC / J. Byron, K. Douglas
455883/6/2008 Order Dismissing Complaints RE: cooling Tower Operations

1 page(s)
 CEC / Docket UnitCEC / J. Byron, K. Douglas
454012/19/2008 Staff Response Regarding Public Health & Safety Complaints

2 page(s)
 CEC / W. ChamberlainM. Rodriguez
452792/6/2008 Staff response and recomendations to Rodriguez Complaints RE: Cooling Tower Operations.

17 page(s)
 CEC/ Docket UnitCEC/ K. Bell
439751/7/2008 Email from Mark Rodriguez Regarding CEC Staff Request to Consolidate Complaints VIS-8 and Public Health & Safety

1 page(s)
 CEC / Docket UnitMember of Public / M. Rodriguez
439631/4/2008 Staff Response and Recommendations to Rodriguez Complaint Re: VIS-4

24 page(s)
 CEC / Docket UnitCEC / Dale Edwards
439611/4/2008 Staff Response and Recommendations to Rodriguez Complaints re: Cooling Tower Operations

7 page(s)
 CEC / Docket UnitCEC / K. Bell
4391012/31/2007 VIS-8 Non-Compliance Complaint

3 page(s)
 CEC / W/ ChamberlainM. Rodriguez
4390912/31/2007 Non-Compliance Complaint & Public Records Act Request RE: VIS-4

5 page(s)
 CEC/ W. ChamberlainM. Rodriguez
4390812/31/2007 Public Health & Safeth Complaint RE: VIS-8 & PH-1

3 page(s)
 CEC / W. ChamberlainM. Rodriguez
4369612/11/2007 Filing of Notice of Decision Re: Addistion of a Turbine Inlet Air Chiller

1 page(s)
 CEC / Docket UnitCEC / R. Yasny for P. David
4367512/11/2007 Order No. 07-1205-5, Order Approving a Petition to Add a Turbine Inlet Air Chiller

4 page(s)
 CEC/ Docket UnitCEC/ J. Pfannenstiel
4359812/5/2007 Petition for Proposed Change to Certification

6 page(s)
 CEC / P. DavidBingham / W. Kissinger
4358812/4/2007 Staff Response to Bimbo Bakery USA Comments on the Palomar Energy Center Chiller Amendment

5 page(s)
 CEC / Docket UnitCEC / M. Layton
4354712/3/2007 Staff Response to Comments by Bimbo Bakeries USA Regarding the Petition to Add a turbine Air Inlet Chiller

38 page(s)
 Interested PartiesCEC / Staff
4349911/27/2007 Email from T. Miller re: additional information concerning the inlet air chiller project

2 page(s)
 CEC / Docket UnitSE / T. Miller
4346411/20/2007 Email from T. Miller Re: Response to Bimbo Bakery Comments Dated Nov. 16, 2007

2 page(s)
 CEC / Docket UnitSE / T. Miller
4341711/19/2007 Comments re: Petition for Proposed Change to Certification of the Palomar Energy Center

32 page(s)
 CEC/ P. DavidBimbo Bakeries/ W. Kissinger
4340711/16/2007 Comments re: Proposed Modifications to Condition TSE-10

2 page(s)
 CEC/ P. DavidCalifornia ISO/ G. Rosenblum
4331411/9/2007 Letter Comments of SDG&E Re: Staff Analysis of Petition to Change Project Description and Install Gas Turbine Inlet Air Chiller

2 page(s)
 CEC / P. DavidSE / T. Miller
4306310/26/2007 Staff Analysis of Proposed Modifications To Add Inlet Air Chiller

19 page(s)
 Interested PartiesCEC / P. David
4291210/19/2007 Comments on Palomar Chiller Amendment - Visual Plumes

1 page(s)
 CEC / D. FloresAEG / W. Walters
4258510/1/2007 Letter Regarding the CAISO Approved Maximum Output for the PEP

1 page(s)
 SDG&E/L. BrownCAISO/J. Nickel
419588/17/2007 Notice of Receipt- Petition to Amend the CEC Certification for the Palomar Energy Center Project

3 page(s)
 CECCEC/ R. Johnson
416617/25/2007 Petition for Change of the Project Description in the Final Decision to Install and Operate a Gas Combustion Turbine Inlet Air Chiller In Place Of an Evaporative Chiller System

19 page(s)
 CEC /Docket UnitSempra Energy /T. Miller
396853/20/2007 Notice of Petition to Amend

3 page(s)
 Interested PartiesCEC/R. Johnson
393292/20/2007 Palomar Energy Center Petition for Change of Equipment.

17 page(s)
 CEC/ Docket UnitSempra Energy/ T. Miller
390961/26/2007 Notice of Insignificant Project Change to add inlet chillers for the PIG project

2 page(s)
 Mail List # 7152CEC/ R. Johnson
389991/22/2007 1-19-07 Petition for Change of Equipment from SD Gas & Electric

18 page(s)
 CEC/Dockets UnitSDG&E/T. Miller
367714/18/2006 Notice of Decision by the California Energy Commission.

1 page(s)
 California Resource Agency/CEC/Dockets UnitCEC/C. Bruins
367354/14/2006 ORDER APPROVING a Petition to Allow the Use of Raw Water as a Back-up Supply to Recycled Water

3 page(s)
 CEC/DocketsCEC/Desmond
366744/7/2006 Final Staff Analysis of Proposed Modification to Use Raw Water as a Backup Supply to Recycled Water

1 page(s)
 CEC/Docket unitCEC/C Bruins
366604/4/2006 Preliminary Staff Analysis of Proposed Amendment Petition to Use Raw Water as a Backup Supply to Recycled Water.

6 page(s)
 Ms. Connie Bruins/CEC/Docket UnitSDG&E
366594/4/2006 Notification that San Diego Gas & Electric has assumed operational control of the Palomar Energy Center.

2 page(s)
 San Diego Air Pollution Control Dist/CEC/Docket UnitSDG&E/Palomar Energy
366584/4/2006 Notification that SDG&E has assumed operational control of the Palomar Energy Center.

2 page(s)
 City of Escondido/CEC/Docket UnitSDG&E/Palomar Energy
366574/4/2006 Notice of Transfer of Ownership and Operational Control.

1 page(s)
 CEC/Docket UnitPalomar Energy / San Diego Gas & Electric
366564/4/2006 Opposition to Amendment to Palomar Energy Project License to Allow Use of Raw Water Back-up for Cooling System.

10 page(s)
 Connie Bruins/CEC/Docket UnitBorder Power Plant-Working Grp/B. Powers
366554/4/2006 Comments re: the applicant and the public.

10 page(s)
 Connie Bruins/CEC/Docket UnitM. Rodriguez
366453/30/2006 Preliminary Staff Analysis of Proposed Modification to Use Raw Water as a Backup Supply to Recycled Water

24 page(s)
 Interested Parties/CEC/Docket UnitCEC/Bruins
366273/23/2006 Notice of Siting Committee workshop for the Palomar Energy Center Project to Allow the use of Raw Water as a Back-up to Recycled Water

1 page(s)
 CEC/Docket UnitCEC/J. Geesman and J. Boyd
366123/20/2006 Order Approving Transfer of Ownership and Operational Control to San Diego Gas and Electric.

1 page(s)
 Docket UnitCEC
364693/2/2006 Notice of Decision by The CEC

1 page(s)
 Docket UnitCEC
364683/3/2006 Order Approving a Petition to Modify Air Quality Transcription Errors.

2 page(s)
 Docket UnitCEC
364643/3/2006 Order Approving a Petition to Correct Noise Level limits

2 page(s)
 Docket UnitCEC
364072/27/2006 Notice of Receipt Petition to Transfer Ownership and Operational Control of the Palomar Energy Project 01-AFC-24C

2 page(s)
 Docket UnitCEC / Compliance Marci
363602/9/2006 Petition to Amend - The CEC's Decision for the Palomar Energy Project

4 page(s)
 General DistributionCEC/R. Johnson
363342/6/2006 Request for Temp Approval to Use Raw Water.

2 page(s)
 Robert C. Jackson/CEC/Docket UnitCEC/T. O'Brien
363282/6/2006 Request to Make Temporary Use of Potable Water

2 page(s)
 Sempra Energy/R. JacksonCEC/T. O'BRIEN
363272/6/2006 Emergency Variance for Commissioning Phase of Project Construction

2 page(s)
 Sempra Energy/R. JacksonCEC/C. Bruins
361801/11/2006 Petition for Soil and Water Condition-5 Modification

37 page(s)
 CEC/Docket UnitPalomar Energy/Miller
361401/4/2006 Palomar Energy Project Request to Make Temporary Use of Portable Water.

2 page(s)
 Docket UnitCEC
3613612/29/2005 Response to letter dated 12/12/05 to BB Blevins regarding potential changes to Palomar Energy project

2 page(s)
 Jeff SwitzerCEC/O'BRIEN
3613512/29/2005 Response to BB Blevins letter dated 10/20/2005 regarding significant planned changes to Palomar Energy Project

9 page(s)
 CEC/BlevinsJeff Switzer
3612412/22/2005 Palomar Energy Center Project - Notice of Receipt of Petition to modify allowable noise levels and public review of Staff Analysis

8 page(s)
 Interested PartiesCEC/Bruins
3599712/5/2005 Request for Modification of CEC Condition of Certification NOISE-6 (attachments)

8 page(s)
 Connie Bruins/CEC/Docket UnitPalomar Energy/R. Kelly
3292212/13/2004 Approval of Petition to Modify a Portion of the Brine Return Pipeline Route

2 page(s)
 Sempra Energy/Kelly/cec/docket UnitCEC/Bruins
3278111/23/2004 Notice of Insignificant Project Change to modify a portion of the Brine Return Pipeline Route for the Palomar Energy Project.

2 page(s)
 CEC/DocketsCEC/O'brien
2079-04/10/2006 Standing Siting Committee Workshop

127 page(s)