259540 | 10/15/2024 |
2023 Annual Compliance Report for Pastoria Energy Facility 2023 Annual Compliance Report for Pastoria Energy Facility Air Quality, Biological Resources, Compliance, Hazardous Materials, Visual Resources, Waste Management, Soil and Water 34 page(s)
| | CEC/Docket Unit | California Energy Commission |
239187 | 8/5/2021 |
Pastoria Energy Facility - Non-Petition to Amend Approval Letter - Software Change Pastoria Energy Facility - Non-Petition to Amend Approval Letter - Software Change Compliance 2 page(s)
| | Calpine Corporation/Barbara McBride | California Energy Commission |
239184 | 8/4/2021 |
Pastoria Energy Facility - Non-Petition to Amend Approval Letter Pastoria Energy Facility - Non-Petition to Amend Approval Letter for changes to switchyard. Compliance 2 page(s)
| | Calpine Corporation/Barbara McBride | California Energy Commission |
233362 | 6/8/2020 |
Petition fpr Projects changes - Site Reconfiguration Petition for Changes 1 page(s)
| | CEC/Docket Unit | California Energy Commission |
233361 | 6/8/2020 |
Pastoria Staff Analysis of Proposed Project Modification Staff Analysis of Proposed Modification Conversion from Aqueous to Anhydrous Ammonia 1 page(s)
| | Interested Parties | California Energy Commission |
231094 | 12/11/2019 |
Pastoria Energy Facility - 2018 Annual Compliance Report 2018 Annual Compliance Report for the Pastoria Energy Facility. Compliance 145 page(s)
| | CEC/Mary Dyas | Calpine Corporation |
225630 | 10/30/2018 |
Compliance Docketing Policy
3 page(s)
| | Plant Manager | California Energy Commission |
220865 | 8/23/2017 |
Pastoria Energy Facility - Letter Withdrawing 2016 AQ Amendment 20170822 Letter from Calpine to Withdraw the AQ Petition to Amend filed in 2016 Compliance 1 page(s)
| | CEC/Mary Dyas | Pastoria Energy Facility, L.L.C. |
211820 | 6/15/2016 |
Notice of Receipt of Complete Application Determination of complete application from the San Joaquin Valley Air Pollution Control District Air Quality 2 page(s)
| | Michael Rinehart, Pastoria Energy Facility LLC | Sierra Research |
211182 | 4/22/2016 |
Pastoria Energy Facility Response to SJVAPCD Notice of Incomplete Application Pastoria Energy Facility's Response to SJVAPCD's Notice of Incomplete Application Air Quality 3 page(s)
| | | Sierra Research |
210781 | 3/18/2016 |
Pastoria Energy Facility - Petition to Amend - Notice of Receipt 20160318
Compliance 3 page(s)
| | CEC/Dockets Unit | California Energy Commission |
210637 | 3/8/2016 |
Application to the SJVAPCD for permit amendment Application for modifications to the Permits
to Operate and the Federal Operating Permit Air Quality 222 page(s)
| | Arnaud Marjollet, Director of Permit Services, SJVAPCD | Sierra Research |
210581-1 | 3/1/2016 |
Calpine Pastoira Amendment #11-02.19.2016
Compliance 193 page(s)
| | CEC/Mary Dyas | CH2M Hill |
210581-2 | 3/1/2016 |
Calpine Pastoria Amendment Cover Letter The Air Quality Modeling Files for February 2016 are in the Dockets Unit Compliance 1 page(s)
| | CEC/Mary Dyas | CH2M Hill |
202261 | 4/28/2014 |
Notice of Decision Notice of Decision for Pastoria Energy Facility Amendment Approved 04-22-2014 Compliance 1 page(s)
| | CEC | California Energy Commission |
202254 | 4/28/2014 |
Commission Order Approving a Petition to Amend Commission Order 14-0422-3 Approving Elimination of O2 limit in AQ-16 Air Quality 3 page(s)
| | | California Energy Commission |
201517 | 1/7/2014 |
Approval for Additional Brine Crystallizer
Compliance 2 page(s)
| | Pastoria Energy Facility, LLC | California Energy Commission |
201427 | 12/13/2013 |
Pastoria Energy Facility - Notice of Determination for Addition of 2nd Brine Crystallizer
Compliance 4 page(s)
| | | California Energy Commission |
201387 | 12/9/2013 |
Notice of Receipt - AQ Petition to Amend
Compliance 2 page(s)
| | | California Energy Commission |
201319 | 11/25/2013 |
Pastoria Energy Facility Staff Assessment for Air Quality Petititon to Amend
Air Quality 11 page(s)
| | | California Energy Commission |
200634 | 9/27/2013 |
Petition to Amend Air Quality Conditions of Certification Request to remove cold start CO one hour limit Air Quality 30 page(s)
| | CEC/M. Dyas | Calpine Corp./B. McBride |
200113 | 8/2/2013 |
Applicant's Request for Staff Approved Modification Amendment to request approval to install a second brine crystallizer to Pastoria's Zero Liquid Discharge system. Project Description 10 page(s)
| | Mary Dyas | Calpine Corporation |
63773 | 2/24/2012 |
Approval Letter for the Pastoria Energy Facility Staff Approved Project Modification
1 page(s)
| | Calpine Corporation | CEC/M.Dyas |
63489 | 2/1/2012 |
Notice of Determination Regarding Request to Amend
2 page(s)
| | CEC/DOCKET UNIT | CEC/M. Errecart |
63275 | 1/4/2012 |
Petition to Amend - Replacement of Components of AGP on Two Combustion Turbines
6 page(s)
| | CEC/ M. Dyas | Pastoria Energy Facility, LLC |
35384 | 8/25/2005 |
Repeated Application for Confidential Designation: Final Cultural Resources for AFC for Pastoria (previous request granted).
144 page(s)
| | CEC/Blevins/Docket Unit | Calpine Corporation/Argentine |
34488 | 5/31/2005 |
Approval of Conversion of Acreage to Permanent Impacts, and Approval of Bio-11 Verification Change
4 page(s)
| | Calpine Corporation/Argentine | CEC/Tronaas |
33680 | 3/15/2005 |
Final Paleontological Report
142 page(s)
| | CEC/Tronaas/dockets | Calpine/Gonzales |
33291 | 2/7/2005 |
Paleontological Compliance Report
2 page(s)
| | CEC/Tronaas/dockets | Calpine/Argentine |
33018 | 12/28/2004 |
Response to the District's April 12, 2004, Notice of Incomplete Application for modifications proposed to the permits for Pastoria.
8 page(s)
| | Thomas Goff/Docket Unit | Calpine |
33017 | 12/28/2004 |
Responses to the CEC Staff's data requests related to the proposed amendment to the license for Pastoria.
10 page(s)
| | Nancy Tronaas/Docket Unit | Sierra Research/G. Rubenstein |
33016 | 12/28/2004 |
Confirmation of discussions with the District Staff re: the use of SOx ERCs to fulfill the PM10 offset requirement.
5 page(s)
| | Mr.thomas Goff/Docket Unit | Calpine |
33012 | 12/27/2004 |
Notice of Decision - Revise the ERC offset package for specific criteria pollutants, modify the quantity of ERCs to be surrendered to the air district for PM10 and SOx, and make conforming changes to the air quality Coditions of Cert
2 page(s)
| | Opr/Resources/cec/docket | CEC/Tronas |
33011 | 12/27/2004 |
Notice of Decision - A temporary increase in hourly and daily oxides of nitrogen and carbon monoxide emissions during the commissioning phases
2 page(s)
| | Opr/Resources/cec/docket | CEC/Tronas |
33003 | 12/24/2004 |
Notice of Decision by the CEC
2 page(s)
| | Office Of Planning And Research/Ca Resources Agnec | CEC/Tronaas |
32993 | 12/23/2004 |
Order Approving Modifications to the Emission Reduction Offset Package and Other Changes That Affect Air Quality Conditions of Certifications
7 page(s)
| | CEC/Dockets | CEC/Keese |
32992 | 12/23/2004 |
Order Approving a Temporary Increase in Emissions During Commissions
3 page(s)
| | CEC/Dockets | CEC/Keese |
32921 | 12/13/2004 |
Petition to Modify Emission Reduction Credit Offsets
5 page(s)
| | Robert Sarvey/Cec/docket Unit | CEC/Tronaas |
32920 | 12/13/2004 |
Addendum to Staff Analysis of Proposed Modifications to Emission Reduction Credit Offsets
4 page(s)
| | Interested Parties/Cec/docket Unit | CEC/Tronaas |
32780 | 11/23/2004 |
Pastoria Energy Facility (99-AFC-7C) Staff Analysis of Proposed Modifications to Emission Reduction Credit Offsets
3 page(s)
| | CEC/Dockets/tronaas | Robert Sarvey |
32770 | 11/19/2004 |
Staff Analysis of Proposed Modifications for a Temporary Increase in Emissions during Commissioning
8 page(s)
| | Interested Parties/Cec/docket Unit | CEC/Tronaas |
32653 | 11/5/2004 |
Staff Analysis of Proposed Modifications to Emission Reduction Credit Offsets
11 page(s)
| | Interested Parties/Cec/docket Unit | CEC/Tronaas |
32644 | 11/3/2004 |
SJVAPCD's Preliminary Revised Determination of Compliance
21 page(s)
| | CEC/Tronaas | Sjvapcd/Waner |
32407 | 9/30/2004 |
Notice of Receipt - Petition to Amend the Energy Commission Decision for the Pastoria Energy Facility
3 page(s)
| | CEC/Docket Unit | CEC/O'brien |
32353 | 9/16/2004 |
Modification to March 19, 2004, Petition to Amend Emission Reduction Credit Offset Package & Other Condition for Certification.
2 page(s)
| | CEC/Docket | Calpine/H. Scarborough |
32352 | 9/16/2004 |
Calpine Corporation Pastoria Energy Facility, LLC (99-AFC-7C) Petition for Post Certification Amendment for Project Commissioning Activities.
93 page(s)
| | CEC/Tronaas | Calpine/Scarborough |
32307 | 9/8/2004 |
Email from Rick Tyler re: the ammonia tank size amendment.
3 page(s)
| | CEC/Docket | Pastoria Energy Facility/Ellison, Schneider & Harr |
32093 | 8/12/2004 |
Repeated Application for Confidential Designation, Pastoria Gas Pipeline Reroutes 2A and 2B - Cultural Resources Materials.
8 page(s)
| | CEC/Therklesen | Urs/Ray |
32090 | 8/11/2004 |
Repeated Application for Confidential Designation Pursuant to Section 2505(a)(4) of Title 20 for the Pastoria Energy Facility (99-AFC-7), Pastoria Gas Pipeline Reroutes 2A and 2B - Cultural Resources Materials.
107 page(s)
| | CEC/Therkelsen | Urs/Ray |
31554 | 5/19/2004 |
Amendment Request 2004-0437 Data Requests - Technical Area on Air Quality
4 page(s)
| | CEC/Dockets | Aspen/Walters |
31174 | 3/30/2004 |
Notice of Receipt - - Petition to Amend The Energy Commission Decision for the Pastoria Energy Facility -- Modifications to the Emission Reduction Credit Offsets
3 page(s)
| | CEC/Dockets | CEC/T. O'brien |
31146 | 3/24/2004 |
Calpine Corporation Pastoria Energy Facility Request to Amend Emission Reduction Credit Package Surrender of Required Emission Reduction Credits Permits S-3636-1-2, S-3636-2-2, S-3636-3-2, S-3636-4-2, S-3636-5-2.
29 page(s)
| | CEC/Thomas Goff | Calpine/Mcbride |
31145 | 3/24/2004 |
Calpine Corporation Pastoria Energy Facility Petition to Amend Emission Reduction Credit Offset Package and other Conditions of Certification 99-AFC-7C.
19 page(s)
| | CEC/Tronaas | Calpine/Mcbride |
31139 | 3/23/2004 |
Petition to Reroute Segment 2A of the Natural Gas Pipeline.
1 page(s)
| | Office Of Planning And Research | CEC/Tronaas |
31117 | 3/17/2004 |
Approval of Petition to reroute Natural Gas Pipeline segment 2A and Approval of Changes to Verifications for Soils & Water-1, -2, & -7
3 page(s)
| | Pastoria Energy Facility/Salzmann | CEC/Tronaas |
31103 | 3/12/2004 |
Notice of Exemption - Petition to Reroute Segment 2Bof the Natural Gas Pipeline
1 page(s)
| | Office Of Planning And Research/Dockets | CEC/Tronaas |
31072 | 3/8/2004 |
Approval of Petition to Modify Natural Gas Pipeline Reroute 2B
2 page(s)
| | Pastoria Energy Facility/Salzmann/dockets | CEC/Tronaas |
31063 | 3/5/2004 |
Notice of Insignificant Project Change - Natural Gas Pipeline Reroute 2A
1 page(s)
| | CEC/Docket | CEC/O'brien |
30977 | 2/25/2004 |
Transmittal of Amendment to CEC License Petition for Pastoria Energy Facility--Pastoria Gas Pipeline Reroute 2A.
3 page(s)
| | CEC/N. Tronaas/dockets | R. Ray, Urs |
30964 | 2/20/2004 |
Notice of Insignificant Project Change Natural Gas Pipeline Reroute 2B
1 page(s)
| | CEC/Docket | CEC/O'brien |
30931 | 2/18/2004 |
Transmittal of Petition for a Minor Modification to PEF Decision 99-AFC-7 for Pastoria Gas Pipeline Reroute 2A
48 page(s)
| | CEC/Tronaas | Urs/Ray |
30888 | 2/10/2004 |
Petition to CEC License for the Pastoria Energy Facility - Reroute 2B of the Gas Pipeline.
36 page(s)
| | CEC/Dockets | Pastoria Energy Facility |
27682 | 12/18/2002 |
Commission Order Approving Project Modification
3 page(s)
| | CEC/Dockets | CEC/Keese |
27650 | 12/13/2002 |
Notice of Decision by CEC-Filing of Notice in Compliance with Public Resources Decision
1 page(s)
| | Office Of Planning And Research/Calif Resources Ag | CEC/Tronaas |
27591 | 12/6/2002 |
Emission Reduction Credit Reconciliation
7 page(s)
| | CEC/Trask/dockets | Calpine/Mcbride |
27238 | 11/1/2002 |
Staff Analysis of Petition to Modify VIS-7-- Plume Abatement
7 page(s)
| | Interested Parties/Dockets | CEC/Tronaas |
26280 | 7/24/2002 |
Notice of Revised Determination of Compliance
60 page(s)
| | CEC/Tronaas/dockets | San Joaquin Valley Air Pollution Control District/ |
26173 | 7/15/2002 |
Applicant's Petition to Delete Condition VIS-7
2 page(s)
| | CEC/Tronaas/dockets | Tejon Ranch Company/Mullins |
25981 | 6/21/2002 |
Notice of Receipt
2 page(s)
| | CEC/Dockets | CEC/O'brien |
25957 | 6/19/2002 |
Commission Order Approving Project Modifications
3 page(s)
| | CEC/Dockets | CEC/Keese |
25929 | 6/13/2002 |
Notice of Decision by CEC-Modification of Conditions of Certification for Minor Increase in Cooling Tower PM10 Emissions
2 page(s)
| | Office Of Planning & Research/Calif Resources Agen | CEC/Tronaas |
25796 | 6/3/2002 |
Petition to Amend Pastoria Energy Facility's Condition of Certification (VIS-7) Regarding the Prevention of Cooling Tower Plume Formation
42 page(s)
| | CEC/Tronnas/dockets | Calpine/Joseph |
25723 | 5/21/2002 |
Staff Analysis of Proposed Project Modification: Request to Increase Cooling Tower PM10 Emissions
4 page(s)
| | CEC/Dockets | CEC/Tronnas |
25467 | 4/30/2002 |
Notice of Receipt - Request to Amend the CEC Decision for the Pastoria Energy Facility - Petition to Increase Cooling Tower PM 10 Emissions
2 page(s)
| | CEC/Dockets | CEC/Therkelsen |
25351 | 4/19/2002 |
Petition to amend conditions of certification AQ-55 and AQ-64 proposal to increase calculated cooling tower PM10 emissions
6 page(s)
| | CEC/Tronaas/dockets | Calpine/Rodriguez |
25164 | 3/20/2002 |
Notice of Exemption-Project Change: Increase in Height Transmission Towers
1 page(s)
| | Office Of Planning And Research/Dockets | CEC/Tronaas |
24218 | 1/16/2002 |
Notice of Decision by the California Energy Commission
1 page(s)
| | Office Of Planning & Research/Dockets | CEC/Tronaas |
24217 | 1/16/2002 |
Approval of Changes to Anhydrous Ammonis Storage Tanks - Revision to Condition of Certification Facility Design
1 page(s)
| | Office Of Planning & Research/Dockets | CEC/Tronaas |
24084 | 1/14/2002 |
Approval of Revisions Conditions of Certification AQ-17, -18, -19, -20, -24 and -26
3 page(s)
| | Pastoria Energy Facility/Salzmann/dockets | CEC/Therkelsen |
24082 | 1/15/2002 |
Notice of Insignficant Project Change (Transmission Tower Height and Reconfiguration)
2 page(s)
| | CEC/Dockets | CEC/Therkelsen |
24027 | 1/11/2002 |
Approval of Modification to Anhydrous Storage Tanks - Revision to Condition of Certification Facility Design - Gen-2
2 page(s)
| | Pastoria Energy Facility/Salzmann/dockets | CEC/Therkelsen |
23902 | 1/8/2002 |
Petition to Amend Condition of Certification AQ-2 regarding the submittal timing of design details
2 page(s)
| | CEC/Tronaas/dockets | Calpine/Rodriguez |
23901 | 1/8/2002 |
Approval of Vertification Change AQ-2
1 page(s)
| | Pastoria Energy/Salzmann/dockets | CEC/Tronaas |
23688 | 12/27/2001 |
Petition to Amend Pastoria Energy Facility's Condition of Certification (GEN-4) Table 1, Equipment List Regarding Anhydrous Ammonia Storage Facility
3 page(s)
| | CEC/Tronaas/dockets | Calpine/Rodriguez |
23387 | 12/7/2001 |
Petition to Amend Transmission Tower Height Referenced in Pastoria Facility's Commission Decision
3 page(s)
| | CEC/Tronnas/dockets | Calpine/Rodriguez |
22740 | 10/19/2001 |
Staff Information Request Regarding Pastoria Energy Facility Petition to Modify Offset Package and Remove Co Catalyst
39 page(s)
| | CEC/Tronaas/dockets | Calpine/Salzmann |
22672 | 10/11/2001 |
Approval of Revisions to Conditions of Certification AQ-24 and AQ-27; Approval of Verfication Changes AQ-25 and AQ-26
2 page(s)
| | Pastoria Energy Facility/Salzmann/dockets | CEC/Therkelsen |
22671 | 10/11/2001 |
Approval of Changes to Conditions of Cert. AZ-24 & -27
1 page(s)
| | Office Of Planning And Research/Dockets | CEC/Tronaas |
22519 | 9/28/2001 |
CEC License Amendment
77 page(s)
| | CEC/Tronaas/dockets | Urs/Scholl |
22516 | 10/1/2001 |
Petition to Amend Conditions of Certification AQ-24 and AQ-27 Regarding the Timing of Emission Reduction Credits Surrendering
3 page(s)
| | CEC/Tronaas/dockets | Calpine/Rodriguez |
21921 | 8/16/2001 |
Notice of Exemption-Addition of Condition of Certification to Ensure Coordinated Integration of New Generating Unit with California's Electricity Grid
1 page(s)
| | Office Of Planning And Research/Dockets | CEC/Bruins |
21350 | 7/3/2001 |
Commission Order Approving Ownership Transfer
1 page(s)
| | Dockets | CEC/Keese |
21349 | 7/9/2001 |
Notice of Exemption - Approval of Project Change: Site Recommendation
1 page(s)
| | Office Of Planning & Research/Dockets | CEC/Tronaas |
21348 | 7/9/2001 |
Approval of Project Changes: Site Recommendation; New Condition of Certification TRANS-9
2 page(s)
| | Pastoria Energy Facility/Salzmann/dockets | CEC/Therkelsen |
21339 | 7/9/2001 |
Notice of Receipt - Request to Amend the CEC Decision for the Pastoria Energy Facility - Ammonia Conversion
2 page(s)
| | CEC/Dockets | CEC/Therkelsen |
21286 | 6/22/2001 |
Socioeconomic Clarifications
2 page(s)
| | Dockets | Urs/Scholl |
21284 | 6/22/2001 |
Commission Order Approving Ownership Transfer
1 page(s)
| | Dockets | CEC/Keese |
21231 | 6/20/2001 |
Changes to Conditions of Certtification BIO-05, BIO-08, and BIO-10
10 page(s)
| | Pastoria Energy Facility/Salzmann/dockets | CEC/Therkelsen |
21011 | 6/20/2001 |
Notice of Exemption
1 page(s)
| | Office Of Planning & Research/Dockets | CEC/Tronaas |
20962 | 6/19/2001 |
Commission Order Approving Ownership Transfer
1 page(s)
| | CEC/Dockets | CEC/Keese |
20934 | 6/18/2001 |
Notice of Receipt: Request to Amend the CEC Decision - Site Reconfiguration and Ammonia Conversion
2 page(s)
| | CEC/Dockets | CEC/Therkelsen |
20925 | 6/12/2001 |
General Arrangement Changes License Amendment
250 page(s)
| | CEC/Tronnas/docket | Urs/Scholl |
20577 | 6/1/2001 |
Construction Laydown Area Expansion Submittal
20 page(s)
| | CEC/Tronaas/dockets | Urs/Scholl |
19843 | 4/20/2001 |
Notice of Post-Certification Change in Ownership
1 page(s)
| | CEC/Docket | Pastoria Energy Center/King |
19413 | 3/20/2001 |
Insignificant Project Change: Revision to Soil & Water 5
1 page(s)
| | Office Of Planning & Research/Dockets | CEC/Therkelsen |
19412 | 3/30/2001 |
Approval of Project Change - Soil & Water 5, Back-up Water Supply Clarification
2 page(s)
| | Pastoria Energy Facility/When/dockets | CEC/Therkelsen |
19253 | 3/19/2001 |
Petition to Amend Condition of Certification Soils & Water 5
33 page(s)
| | CEC/Tronaas/dockets | Pastoria Energy Facility |
18643 | 2/16/2001 |
Transmittial of Phase I Environmental Site Assessment
1 page(s)
| | CEC/Richens/dockets | Urs Greiner Woodward Clyde/Scholl |
18440 | 2/5/2001 |
Establishment of Post-Certification Mailing List
2 page(s)
| | Interested Parties | CEC/Tronaas |