20487 | 10/12/1999 |
October 13th Special Business Meeting
2 page(s)
| | Commissioners/Docket | Chamberlain |
20486 | 10/14/1999 |
Issuance of Amended Permit PRT-828741 to Take Tidewater Goby at Morro Bay, CA
3 page(s)
| | U.s. Fish & Wildlife Service/O'brian/dockets | Ca. Regional Water Quality Conrol Board/Briggs |
18020 | 1/12/2001 |
Public Adviser's Status Reports 2000
41 page(s)
| | CEC/Docket | CEC/Pao |
16128 | 10/10/2000 |
Comments RE: the "Unresolved Traffic Related Issues"
5 page(s)
| | CEC/Adams | Dept. Of Transportation/Figge |
14632 | 5/26/2000 |
Energy Commission Order - Order # 00-0523-03
5 page(s)
| | CEC/Dockets | CEC/Keese |
14194 | 4/13/2000 |
Request to Loan a Copy of the Morro Bay Power Plant.
1 page(s)
| | Urs Greiner Woodward Clyde/Murphy | CEC/Buell |
13735 | 2/23/2000 |
Concerns from various groups representing Native American interests in the Morrro Bay area. (Attachments: Notes of calls received; Fax cover sheet)
3 page(s)
| | CEC/Matthews | Playano Salinan/Burch |
13734 | 2/23/2000 |
San Luis Obispo County Chumash Council Concerns.
3 page(s)
| | City Of Morro Bay/Fuz | Law Office Of Tarren Collins/Collins |
13733 | 2/23/2000 |
Native American Representation and Cultural Resource Management at the Duke Energy Morro Bay Power Plant.
2 page(s)
| | CEC/Matthews | Playano Salinan/Burch |
13731 | 2/23/2000 |
Letter to Mr. Hoffman from Patti Dunton, descendent of the Playano Salinan RE: Hire of an archaeologist to do a Cultural Resource Impact study of the Morro Bay area.
3 page(s)
| | CEC/Mendonca | Patti Dunton |
13730 | 2/23/2000 |
Letter RE: Modernization of the Existing Morro Bay Power Plant in San Luis Obispo County.
4 page(s)
| | Salinan Council/Castro/john Burch | Duke Energy North America/Goschke |
13729 | 2/23/2000 |
2/14/00 Morro Bay City Council Meeting: Duke Energy and Cultural Resource Concerns (Attachment: Fax Cover Sheet)
2 page(s)
| | CEC/Matthews | Playano Salinan Cultural Resource Mgmt./Burch |
13229 | 1/11/2000 |
E-mail thanking Ms. Leizear for her comments
1 page(s)
| | Mary Leizear | CEC/Mendonca |
13203 | 1/7/2000 |
Request to Loan Morro Bay Power Plant AFC.
1 page(s)
| | Livingston & Mattesich/Bibell | CEC/Buell |
13180 | 1/5/2000 |
Morro Bay Power Plant Proposal - (January 8, 2000)
1 page(s)
| | Concerned Citizens | CEC/Mondonca |
12980 | 12/20/1999 |
Comments of the Independent Energy Producers Association on Changes to the power plant Siting Process. (Attachment: Proof of Service)
4 page(s)
| | CEC/Docket | Independent Energy Producers Assoc. |
12790 | 11/22/1999 |
Notice of Siting Committee Hearing on Energy Facility Permitting and Changes to the Siting Process - Attachments
29 page(s)
| | CEC/Docket | CEC/Laruie/rohy |
12597 | 11/2/1999 |
1999 First Quarterly Report
21 page(s)
| | CEC/Buell | Duke Energy North America/Hoffman |
12551 | 11/2/1999 |
1999 First Quarterly Report for the Morro Bay Power Plant
20 page(s)
| | CEC/Buell | Duke Energy North America |
12545 | 10/29/1999 |
Duke Energy Morro Bay, LLC has Agreed to Accomodate the City's Request and Postpone the Data Adequacy Hearing Currently Scheduled for November 17, 1999.
2 page(s)
| | CEC/Smith | Ellison & Schneider/Ellison |
12517 | 10/25/1999 |
Report of Conversation - W/John Torrey, et al. (Duke Energy North America) RE: Data Adequacy for Morro Bay Power Project.
12 page(s)
| | CEC/Docket | CEC/Buell |
12507 | 10/18/1999 |
Air Quality Potential Offsets Temporary Confidentiality Application
4 page(s)
| | Duke Energy Morro Bay Llc/Mason | CEC/Smith |
12502 | 10/27/1999 |
Agenda Input Form - W/Attached Memo to CEC/Kent Smith - Agenda Item for the November 17 Business Meeting - RE: Commission Consideration of the Executive Director's Data Adequacy Recommendation
4 page(s)
| | CEC/Smith | CEC/Therkelsen |
12501 | 10/27/1999 |
Agenda Input Form - W/Attached Memo to Kent Smith - Agenda Item for the November 17, 1999 Business Meeting - RE: Committee Assignment for the Morro Bay Power Plant Project Application for Certification
3 page(s)
| | CEC/Smith | CEC/Therkelsen |
12368 | 10/12/1999 |
RE: October 13th Special Business Meeting (Attachment: Letter from Chris Ellison, dated October 6, 1999)
2 page(s)
| | CEC/Commissioners/smith | CEC/Chamberlain |
12359 | 10/12/1999 |
Acceptable Meteorological Data for the Morro Bay Power PLant AFC - District Application Number 2870
1 page(s)
| | CEC/Buell | San Luis Obispo Apcd/Buell |
12346 | 10/12/1999 |
Applicant, Duke Energy Morro Bay LLC Requesting that the Data Adequacy Hearing (currently scheduled for October 13th) be Deferred to November 17th. Attachment: Proof of Service)
1 page(s)
| | CEC/Chamberlain | Ellison & Schneider/Ellison |
12280 | 10/5/1999 |
Letter of Concern RE: Steam Clouds Generated by the Present Plant.
1 page(s)
| | CEC/Buell | John W. Mcdonald |
12277 | 10/5/1999 |
Letter RE: Review of Morro Bay AFC.
1 page(s)
| | CEC/Buell | Co. Of San Luis Obispo County Apcd/Willey |
12276 | 10/5/1999 |
Application for a Prevention of Significant Deterioration Permit for Duke Energy's Morro Bay Power Plant
1 page(s)
| | Epa/Haber | Sierra Research/Matthews |
12272 | 10/5/1999 |
Data Inadequate (Morro Bay Homeowner's Response) (Attachment: Proof of Service)
3 page(s)
| | CEC/Public Advisor/ross | Tauras Sulaitis |
12271 | 10/7/1999 |
Data Adequacy Findings RE: Cultural Data - Review Application MBPP - Cultural Resources Review
3 page(s)
| | CEC/Public Advisor | Tauras Sulaitis |
12180 | 10/1/1999 |
Acceptable Meteorological Data for the Morro Bay Powe Plant AFC
1 page(s)
| | CEC/Buell | San Luis Obispo Apcd/Willey |
12158 | 10/1/1999 |
Letter providing the required demonstration of compliance with the District's Rule 219, Toxics New Source Review
3 page(s)
| | Slo Co. Air Pollution Control District, G. Willey/ | Sierra Research/Gary Rubenstein |
12150 | 9/30/1999 |
Data Adequacy Recommendation For the Morro Bay Power Plant Project
158 page(s)
| | CEC/Keese/laurie/moore/pernell/rohy | CEC/Smith |
12123 | 9/29/1999 |
CEC Mailing list: Duke Energy and Morro Bay Power Plant
1 page(s)
| | CEC Cec Mailing List | Morro Bay Veteran's Hall |
12116 | 9/28/1999 |
Letter to Provide the Required Demonstration of Compliance with the District's Rules 219, Toxics New Source Review
4 page(s)
| | San Luis Obispo Air Pollution Control Dist/Will | Sierra Research/Rubenstein |
12088 | 9/15/1999 |
Document Handling for the Morro Bay Power Plant
2 page(s)
| | Librarian | CEC/Therkelsen |
12055 | 9/9/1999 |
Notice of Receipt
3 page(s)
| | CEC/Docket | CECTCectherkelsen |
12044 | 9/8/1999 |
Cultural Resources Technical Report
2 page(s)
| | Duke Energy Morro Bay/Mason | CEC/Smith |
12027 | 9/21/1999 |
Receptor Map - Figure 6.2-15
2 page(s)
| | CEC/Franco | Sierra Research/Gary Rubenstein |
11995 | 9/8/1999 |
Request for Agency Particiption in the Review of Morro Bay AFC
3 page(s)
| | Agency Distribution List | CEC/Therkelsen |
11984 | 9/8/1999 |
Request for Agency Participation in the Review of the Morro Bay Power Plant Application for Certification
3 page(s)
| | Agency Distribution List | CEC/Therkelsen |
11977 | 9/9/1999 |
Application for Confidential Designation: Appendix 6.2-7 Offset Status for Duke Energy Morro Bay Power Plant (3 pages).
3 page(s)
| | CEC/Docket | Trc For Duke Energy/Mason |
11889 | 8/31/1999 |
Application for Certification - Binders 1A, 1B, II and III; 6 copies of CD Disk and 6 Topographical Maps
2500 page(s)
| | CEC/Smith | Duke Energy North America/Hall |
11874 | 8/31/1999 |
Application for Confidential Designation Confidential Filing
2 page(s)
| | CEC/Docket | Duke Energy Morro Bay Llc/Robert C. Mason |
1308-0 | 12/22/1999 |
Stakeholder Hearings on Energy Fac. Permitting Changes to Siting Process
71 page(s)
| | | CEC |