Docket Log

Docket: 82-AFC-01C
Project Title: Compliance - Application for Certification for PG&E Geysers Unit 20
Generated On: 8/3/2020 3:12:14 AM

Include:     
TN #Docketed DateDocument TitleExhibit #ToFrom
2326934/8/2020 Geysers Power Company, LLC Comments - 2019 Annual Compliance Report

Compliance
21 page(s)
 CEC/DocketsGeysers Power Company, LLC
23132212/26/2019 2018 Annual Compliance Report for the Grant Power Plant (Unit 20)
2018 Annual Compliance Report for the Grant Power Plant (Unit 20) at the Geysers
Compliance
33 page(s)
 Mr Eric VeerkampGeysers Power Company, LLC
23028110/18/2019 RESOLUTION - RE GEYSERS FACILITIES FIRE SYSTEM RECOMMISSIONING
Resolution No: 19-1014-4
1 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22612912/17/2018 Commission Order 20181210 Grant wet down system engine installa
Final Commission Order for Geysers Grant Unit 20, PTA for wet down system permanent diesel engine installation
Compliance
2 page(s)
 CEC/DocketsCalifornia Energy Commission
22593111/20/2018 Revised Air Quality and Worker Safety Conditions of Certification

Air Quality
8 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22573911/1/2018 Memo - Staff Response to Petitioner’s Comments on Staff’s Revised Air District Permit Conditions

6 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22558210/30/2018 Compliance Docketing Policy

3 page(s)
 Plant ManagerCalifornia Energy Commission
22509110/25/2018 Notice of Staff Workshop
November 8, 2018 at 2:00 p.m.
4 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22503610/18/2018 Applicant's Comments on Staff's Revisions to Worker Safety-1 Condition of Certification

14 page(s)
 CEC/Eric Veerkamp and Keith WinsteadEllison Schneider Harris & Donlan LLP
22498710/15/2018 Revised Worker Safety-1 Condition of Certification

2 page(s)
 CEC/Docket UnitCalifornia Energy Commission
2247419/17/2018 Geysers Power Company LLC Comments on the Staff Analysis of the Petition to Amend

9 page(s)
 CEC/Keith WinsteadEllison Schneider Harris & Donlan LLP
2245788/23/2018 Staff Analysis – Permanent Diesel Pump for Cooling Tower Wetting System
On December 21, 2017, the California Energy Commission received a petition from the Geysers Power Company, LLC, to amend the Energy Commission licenses for the Quicksilver (formerly PG&E Geysers Unit 16), Socrates (formerly PG&E Geysers Unit 18), and Grant (formerly PG&E Geysers Unit 20) geothermal power plants. These power plants are located in Lake and Sonoma counties, approximately 25 miles north of the City of Santa Rosa.
220 page(s)
 1516 9th Street, Sacramento CA 95814California Energy Commission
2225392/13/2018 Air Quality Emissions & Impact Anaylsis

Air Quality
3 page(s)
 CEC/Keith WinsteadCalpine
2223351/23/2018 Geysers Power Company, LLC - Consolidated Petition for a Staff Approved Modifications
FOR GEYSERS UNIT 16 (79-AFC-5C), UNIT 18 (79-AFC-3C), and UNIT 20 (82-AFC-1C)
16 page(s)
 CEC/Docket UnitGeysers Power Plant
2222831/19/2018 Notice of Receipt - Petition to Amend the Energy Commission Decisions for Geysers Unit 16, Unit 18 and Unit 20
PETITION TO AMEND THE ENERGY COMMISSION DECISIONS FOR GEYSERS UNIT 16 (79-AFC-5C), UNIT 18 (79-AFC-3C), and UNIT 20 (82-AFC-1C)TO ALLOW MINOR IMPROVEMENTS FOR FIRE PREVENTION COOLING TOWER WET-DOWN
3 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22203512/21/2017 PTA Geysers-16, Quicksilver, Diesel Generator for Cooling Tower Wetting System
Petition to Amend (PTA) to install a permanent diesel generator for the cooling tower wetting system
56 page(s)
 CEC/Eric VeerkampGeysers Power Company, LLC
2102332/8/2016 Final Permission for Exec. Order B-36-16 Expedited Processing & N. Sonoma Air Pollution Control Dist Authority to Construct(ATC)

8 page(s)
 Geysers Power Company, LLC/James KluesenerCalifornia Energy Commission
2071921/5/2016 Expedited Processing Pursuant to Executive Order B-36-15
Approval of Emergency Reconstruction Activities
Air Quality
2 page(s)
 Geysers Power Company, LLC/James KluesenerCalifornia Energy Commission
20710212/22/2015 Geysers Power – Grant (Unit 20) Cooling Tower Replacement Project Description and Request for Expedited Processing

20 page(s)
 CEC/Robert OglesbyGeysers Power Company, LLC
20676611/24/2015 Grant (Unit 20) 1983 Final Decision

274 page(s)
  California Energy Commission
20675811/24/2015 Grant (Unit 20) Compliance Plan

106 page(s)
  California Energy Commission
20670111/19/2015 Permission to Obtain and Implement County-Issued Demolition Permits to Abate Fire Damage to Structures at Geysers 16, 18, and 20
*** SEE PREVIOUSLY FILED LETTER. TN 206307 ***
2 page(s)
  California Energy Commission
20630710/8/2015 Executive Director's Permission Letter for Cooling Tower Demolition after the 2015 Valley Fire

2 page(s)
 Calpine Corporation/Bruce CarlsenCalifornia Energy Commission
319547/23/2004 REVIEW OF RECLAIMED WATER USES AT THE GEYSERS FACILITIES- - GEYSERS POWER COMPANY, LLC

4 page(s)
 CEC/DocketsRtp Environmental Assoc
319417/23/2004 Comments to "Engineering Report for the Use of Recycled Water at The Geysers" Power Plant Units.

42 page(s)
 CEC/K. Defolo/docketsCa Rwqcb
311043/12/2004 Approval of Petition to Use Reclaimed Wastewater and Approval of Verification Changes

5 page(s)
 Calpine/Carlsen/docketsCEC/Tronaas
311013/12/2004 Notice of Exemption - Petition to Allow the Use of Reclaimed Wastewater

1 page(s)
 Office Of Planning And Research/DocketsCEC/Tronaas
309612/20/2004 Notice of Insignificant Project Change for Geysers Unit 3 (80-AFC-1C), Unit 16 (79-AFC-5C), Unit 17 (79-AFC-1C), Unit 18 (79-AFC-3C), Unit 19 (81-AFC-1C), and Unit 20 (82-AFC-1C) to Allow for Use of Reclaimed Wastwater.

2 page(s)
 CEC/DocketsCEC/O'brien
304808/15/2003 Comments on the petition to the CEC to amend the Energy Commission Decisions for Geysers Unit 3, 16, 17, 18, 19 and 20 to allow selected uses of reclaimed wastewater

3 page(s)
 O'brien/CecCalifornia Regional Water Quality Control Board/Ma
296858/15/2003 Comments on the petition to the CEC to amend the Energy Commission Decisions for Geysers Unit 3, 16, 17, 18, 19 and 20 to allow selected uses of reclaimed wastewater

3 page(s)
 O'brien/CecCalifornia Regional Water Quality Control Board/Ma
291596/27/2003 Notice of Receipt, Petition to Amend the Energy Commission Decisions (82-AFC-1C)

3 page(s)
 DocketsCEC/O'brien
291366/25/2003 License Amendments

40 page(s)
 CEC/Tronaas/docketsCh2mhill/Salamy
117694/22/1999 Commission Order Approving Ownership Transfers

1 page(s)
 CEC/Docket FileCEC/Keese
107303/30/1999 Notice of Receipt - The CEC has received a petition requesting an ownership change for the Geysers Power Plant Units 16, 17, 18, and 20.

2 page(s)
 CEC/Docket FileCEC/Therkelsen
88825/25/1995 Order Approving Modifications to Biology Condition 5-5, Waste Management Condition 11-7, and Deletion of Power Plant Efficiency and Reliability Condition 17-9.

3 page(s)
 CEC/Docket FileCEC Cec
26474/12/1996 Notice of Post-Certification Change for the PG&E's Geysers Unit 20 Project

1 page(s)
 CEC/Docket FileCEC/Therkelsen
6593/14/1995 LETTER REQUESTING THAT MODIFICATIONS BE GRANTED BY CEC STAFF AFTER REVIEW OF THE REQUEST 9/14/95

3 page(s)
 CEC/BrandPg&e
6583/13/1995 LETTER RE COMMENTS ON THE CEC STAFF DRAFT RECOMMENTDATIONS REGARDING (3) PG&E REQUESTS FOR CONDITIONS OF CERTIFICATION AMENDMENTS

1 page(s)
 CEC/Docket FileFriends Of Cobb Mountain
65710/19/1994 NOTICE OF RECEIPT - REQUEST TO AMEND DECISION - ASSESS IMPACTS ON ENVIRONMENTAL QUALITY, PUBLIC HEALTH & SAFETY AND CONSIS TENCY OF PROPOSED CHANGES

1 page(s)
 CEC/Docket FileCEC/Therkelsen
6569/22/1994 PG&E GEYSERS POWER PLANT - MODIFICATION REQUESTS TO COMPLIANCE MONITORING PLANS FOR UNIT 16-20

1 page(s)
 CEC/BrandPg&e