Docket Log

Docket: 79-AFC-03C
Project Title: Compliance - Application for Certification of PG&E Geysers Unit 18
Generated On: 4/26/2024 4:11:10 AM

Include:     
TN #Docketed DateDocument TitleExhibit #ToFrom
2559823/29/2024 CONFIDENTIAL Unit 18 Annual Fire Alarm Inspection Report

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2559813/29/2024 CONFIDENTIAL Unit 18 Semi-Annual Fire Alarm Inspection Report

2 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2559803/29/2024 CONFIDENTIAL Unit 18 Annual Fire Pump Report

18 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2559793/29/2024 CONFIDENTIAL Unit 18 Wet Pipe Fire Sprinkler System Quarterly and Annual Report_Fourth Quarter

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2559783/29/2024 CONFIDENTIAL Unit 18 Deluge Sprinkler Systems Water Spray Quarterly and Annual Report_Fourth Quarter

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2559773/29/2024 CONFIDENTIAL Unit 18 Wet Pipe Fire Sprinkler System Quarterly and Annual Report_Third Quarter

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2559763/29/2024 CONFIDENTIAL Unit 18 Deluge Sprinkler Systems Water Spray Quarterly and Annual Report_Third Quarter

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2559753/29/2024 CONFIDENTIAL Unit 18 Wet Pipe Fire Sprinkler System Quarterly and Annual Report_Second Quarter

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2559743/29/2024 CONFIDENTIAL Unit 18 Deluge Sprinkler Systems Water Spray Quarterly and Annual Report_Second Quarter

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2559733/29/2024 CONFIDENTIAL Unit 18 Wet Pipe Fire Sprinkler System Quarterly and Annual Report_First Quarter

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2559723/29/2024 CONFIDENTIAL Unit 18 Standpipe and Hose System Quarterly and Annual Report_First Quarter

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2559713/29/2024 CONFIDENTIAL Unit 18 Deluge Sprinkler Systems Water Spray Quarterly and Annual Report_First Quarter

5 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2558984/24/2024 CEC's Response Letter to Geysers Power Company re Application for Confidential Designation, dated 3-29-2024

2 page(s)
 Ellison Schneider Harris & Donlan LLP/Chase MaxwellCalifornia Energy Commission
2553683/29/2024 GPC Unit 18_2023 ITM Reports_Repeated Application for Confidential Designation

19 page(s)
  Ellison Schneider Harris & Donlan LLP
2553583/29/2024 GPC Unit 18_Letter to Keith Winstead Regarding Fire Protection-3 Submission

1 page(s)
 CEC/Keith WinsteadEllison Schneider Harris & Donlan LLP
2552113/7/2024 CONFIDENTIAL_U18_GPC 2023 FIRE PROTECTION 4 and 5 Compliance Submission

12 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2552062/16/2024 CONFIDENTIAL Unit 18 GPC Q1 2024 FIRE PROTECTION Compliance Submission

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2551903/20/2024 CEC Response Letter to Applications for Confidential Designation dated Feb 16, 2024 and March 7, 2024

2 page(s)
 Ellison Schneider Harris & Donlan LLP/Chase MaxwellCalifornia Energy Commission
2549133/7/2024 Repeated Application for Confidentiality_U18_GPC 2023 FIRE PROTECTION 4 and 5 Compliance Submission

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2545412/16/2024 GPC Unit 18_Q1 2024 ITM Corrective Action Compliance Submission_Repeated Application for Confidential

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2508786/30/2023 2022 Annual Compliance Report - Socrates (U18)

54 page(s)
 CEC/John HeiserGeysers Power Company, LLC
2498114/19/2023 CEC Response Letter re Application for Confidential Designation dated March 30, 2023

Compliance
2 page(s)
 Ellison Schneider Harris & Donlan LLP/Chase MaxwellCalifornia Energy Commission
2497823/30/2023 Geysers Power Company, Unit 18, 4Q22 ITM Report Wet Sprinkler Inspection

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2497813/30/2023 Geysers Power Company, Unit 18, 4Q22 ITM Report Deluge Inspection

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2497803/30/2023 Geysers Power Company, Unit 18, ITM Report Cover Letter

4 page(s)
 CEC/Keith WinsteadEllison Schneider Harris & Donlan LLP
2495143/30/2023 Geysers Power Company, Unit 18, Repeated Application for Confidential Designation

6 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
24804612/13/2022 November 2022 Monthly Recommissioning Report for Geysers Power Company, LLC Socrates Unit 18 Facility

6 page(s)
 CEC/John Heiser and Keith WinsteadEllison Schneider Harris & Donlan LLP
24759811/21/2022 CEC Response for Confidential Designation Geysers Unit 18, Socrates

2 page(s)
 Ellison Schneider Harris & Donlan LLP/Chase Maxwell California Energy Commission
24757911/4/2022 GPC Unit 18_Q3 2022 Wet Pipe Inspection Report

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
24757811/4/2022 GPC Unit 18_Q3 2022 Deluge Inspection Report

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
24757711/4/2022 GPC Unit 18_Q3 2022 Second Semiannual FireScan Report

10 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
24757611/4/2022 GPC Unit 18_Q3 2022 ITM Report Cover Letter

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
24730211/4/2022 GPC Unit 18_Q3 2022 ITM Reports and Compliance Documents_Repeated Application for Confidential Designation

7 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
24727411/3/2022 CEC Response to Geysers Unit 18 Repeated Application for Confidentiality

2 page(s)
 Ellison Schneider Harris & Donlan LLP/Chase MaxwellCalifornia Energy Commission
24720910/19/2022 GPC Unit 18_Q2 2022 ITM Report Cover Letter_CONFIDENTIAL

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
24719610/20/2022 GPC Unit 18_Wet Pipe Q2 2022 Report_CONFIDENTIAL

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
24719510/20/2022 GPC Unit 18_Deluge Q2 2022 Report_CONFIDENTIAL

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
24719410/20/2022 GPC Unit 18_Q2 2022 ITM Report Cover Letter_CONFIDENTIAL

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
24670210/20/2022 GPC Unit 18_Q2 2022 ITM Reports and Compliance Documents_Repeated Application for Confidential Designation

6 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
24664910/19/2022 GPC Unit 18_Q2 2022 ITM Reports and Compliance Documents_Repeated Application for Confidential Designation

6 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2439106/1/2022 Unit 18_Wet Pipe Fire Sprinkler System Quarterly and Annual Report

10 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2439096/1/2022 Unit 18_Fire Alarm and Life Safety System Inspection Certificate

10 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2439086/1/2022 Unit 18_Electric Fire Pump Annual Report # 3

5 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2439076/1/2022 Unit 18_Electric Fire Pump Annual Report # 2

5 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2439066/1/2022 Unit 18_Electric Fire Pump Annual Report # 1

5 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2439056/1/2022 Unit 18_Electric Fire Pump Annual Report - Fire Pump Performance Test Graph

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2439046/1/2022 Unit 18_GPC Q1 2022 ITM Report Cover Letter_CONFIDENTIAL

6 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2438597/6/2022 CEC Response Geyser Unit 18 Confidential Application June 1, 2022

2 page(s)
 C. Maxwell Ellison Schneider Harris & Donlan LLPCalifornia Energy Commission
2438076/30/2022 2021 Annual Compliance Report - Socrates

Compliance
53 page(s)
 CEC/Docket UnitGeysers Power Company, LLC
2433826/1/2022 Unit 18_GPC Q1 2022 ITM Reports and Compliance Documents Repeated Application for Confidential Designation

12 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2425754/5/2022 2020 Revised Annual Compliance Report - Socrates

Compliance
70 page(s)
 CEC/Eric Veerkamp, CPMGeysers Power Company, LLC
24216511/22/2021 Confidential GPD October 2021 Monthly Recommissioning Report

7 page(s)
  Ellison Schneider Harris & Donlan LLP
24216411/22/2021 Confidential Fire Scan 2021 Report

10 page(s)
  Ellison Schneider Harris & Donlan LLP
24216311/22/2021 Confidential Deluge 2021 Report

5 page(s)
  Ellison Schneider Harris & Donlan LLP
24216211/22/2021 Confidential Wet-Pipe 2021 Report

3 page(s)
  Ellison Schneider Harris & Donlan LLP
24216111/22/2021 Confidential Cover Letter for Geysers Power Company ITM Report Q 3 2021

4 page(s)
  Ellison Schneider Harris & Donlan LLP
24215512/3/2021 Geysers Update 2-8-2019-presentation design plan

8 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24215112/3/2021 U16_U18_U20_Wetting_pump_piping_CEC

15 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24213312/3/2021 U18 4-22-19-4_ReCx ITM Fire Inspection Report (00484041xBA8E1)

1 page(s)
 CEC/Docket UnitEllison Schneider Harris Donlan
24213212/3/2021 20190402 Geysers Unit #18 BOD ReCx Privileged and Confidential

27 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24213112/3/2021 U18 4-22-19-3_ReCx ITM Fire Inspection Report (00484040xBA8E1)

8 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24213012/3/2021 U18 4-22-19_ReCx ITM Fire Inspection Report (00484037xBA8E1)

8 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24212912/3/2021 U18 4-22-19-2_ReCx ITM Fire Inspection Report (00484038xBA8E1)

8 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24212812/3/2021 20190402 Geysers Unit_CEC Comments

27 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24212712/3/2021 20190402 Geysers Unit #18 BOD ReCx Privileged and Confidential - 1

27 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24210312/3/2021 Geysers Socrates (Unit 18) Review of BOD and Recom Plan_200117

2 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24210212/3/2021 20210929 Geysers Unit 18 FP BOD_Rev0_Privileged and Confidential

15 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24210112/3/2021 20210807 Geysers Unit #18 BOD ReCx Privileged and Confidential_Rev2

130 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24210012/3/2021 20210524 Geysers Unit #18 Socrates BOD ReCx Privileged and Confidential_Rev1

124 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24209912/3/2021 2019 Summary of ReCx CAR Unit 18 Socrates
 CEC/Drew BohanEllison Schneider Harris Donlan
24209812/3/2021 2019 ReCx CAR-18-009 FP Systems Hydraulic Nameplates
 CEC/Drew BohanEllison Schneider Harris Donlan
24209712/3/2021 2019 ReCx CAR-18-008 Wet Sprinkler Piping System
 CEC/Drew BohanEllison Schneider Harris Donlan
24209612/3/2021 2019 ReCx CAR-18-007 Sequence of Operation
 CEC/Drew BohanEllison Schneider Harris Donlan
24209512/3/2021 2019 ReCx CAR-18-006 Removal of NonOperational Systems
 CEC/Drew BohanEllison Schneider Harris Donlan
24209412/3/2021 2019 ReCx CAR-18-005 Fire Alarm System Notification
 CEC/Docket UnitEllison Schneider Harris Donlan
24209312/3/2021 2019 ReCx CAR-18-004 Fire Alarm System Monitoring
 CEC/Drew BohanEllison Schneider Harris Donlan
24209212/3/2021 2019 ReCx CAR-18-003 Fire Alarm System
 CEC/Drew BohanEllison Schneider Harris Donlan
24209112/3/2021 2019 ReCx CAR-18-002 Fire Pump operation
 CEC/Drew BohanEllison Schneider Harris Donlan
24209012/3/2021 2019 ReCx CAR-18-001 Fire Pump Pressure Switches Setting
 CEC/Drew BohanEllison Schneider Harris Donlan
24206512/3/2021 Socrates-ITM-2016 RK0861 QSP
 CEC/Drew BohanEllison Schneider Harris Donlan
24206412/3/2021 Socrates-ITM-2016 RK0861 QFA
 CEC/Drew BohanEllison Schneider Harris Donlan
24206312/3/2021 Socrates-ITM-2016 RK0633 QSP
 CEC/Drew BohanEllison Schneider Harris Donlan
24206212/3/2021 Socrates-ITM-2016 QSP
 CEC/Drew BohanEllison Schneider Harris Donlan
24206112/3/2021 Socrates-ITM-2016 QFA
 CEC/Drew BohanEllison Schneider Harris Donlan
24206012/3/2021 Socrates ITM-2016 fire sprinkler report
 CEC/Drew BohanEllison Schneider Harris Donlan
24205912/3/2021 Socrates ITM 2016 fire alarm report
 CEC/Drew BohanEllison Schneider Harris Donlan
24205812/3/2021 ompliance_Socrates_5_23_16_ITM_Fire-Q
 CEC/Drew BohanEllison Schneider Harris Donlan
24205712/3/2021 Compliance_Sorates_2_29_16_ITM_Fire-A
 CEC/Drew BohanEllison Schneider Harris Donlan
24205612/3/2021 Compliancer_Socrates_2_3_15_ITM_Fire-Sprinkler-A
 CEC/Drew BohanEllison Schneider Harris Donlan
24205512/3/2021 Compliance_Socrates_11_2_15_ITM_Fire-Q
 CEC/Drew BohanEllison Schneider Harris Donlan
24205412/3/2021 Compliance_Socrates_11_28_16_ITM_Fire-Q
 CEC/Drew BohanEllison Schneider Harris Donlan
24205312/3/2021 Compliance_Socrates_11_21_13_ITM_Fire-A
 CEC/Drew BohanEllison Schneider Harris Donlan
24205212/3/2021 Compliance_Socrates_11-21-2013_ITM_Fire-Sprinkler_A
 CEC/Drew BohanEllison Schneider Harris Donlan
24205112/3/2021 Compliance_Socrates_8_3_15_ITM_Fire-Q
 CEC/Drew BohanEllison Schneider Harris Donlan
24205012/3/2021 Compliance_Socrates_8_29_16_ITM_Fire-Q
 CEC/Drew BohanEllison Schneider Harris Donlan
24204912/3/2021 Compliance_Socrates_8_28_14_ITM_Fire-Q
 CEC/Drew BohanEllison Schneider Harris Donlan
24204812/3/2021 Compliance_Socrates_10_28_14_ITM_Fire-Q
 CEC/Drew BohanEllison Schneider Harris Donlan
24204712/3/2021 Compliance_Socrates_6_10_13_ITM_Fire-Q
 CEC/Drew BohanEllison Schneider Harris Donlan
24204612/3/2021 Compliance_Socrates_2_3_15_ITM_Fire-A
 CEC/Drew BohanEllison Schneider Harris Donlan
24204512/3/2021 Compliance_Socrates_2_29_16_ITM_Sprinkler-A
 CEC/Drew BohanEllison Schneider Harris Donlan
24204412/3/2021 Compliance_Scorates__10_28_14_ITM_Fire-Q
 CEC/Drew BohanEllison Schneider Harris Donlan
24204312/3/2021 Compliance_Scorates__8_28_14_ITM_Fire-Q
 CEC/Drew BohanEllison Schneider Harris Donlan
24204212/3/2021 Compliance_Scorates__6_7_13_ITM_Fire-Q
 CEC/Drew BohanEllison Schneider Harris Donlan
2416841/27/2022 U19-Calistoga Dry Pipe 2021 Q4 Report_CONFIDENTIAL

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416831/27/2022 U19-Calistoga Diesel Fire Pump 2021 Q4 Report_CONFIDENTIAL

7 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416821/27/2022 U19-Calistoga Deluge 2021 Q4 Report_CONFIDENTIAL

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416811/27/2022 U20-Grant Wet Sprinkler 2021 Q4 Report_CONFIDENTIAL

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416801/27/2022 U20-Grant Deluge 2021 Q4 Report_CONFIDENTIAL

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416791/27/2022 U19-Calistoga Pre-action 2021 Q4 Report_CONFIDENTIAL

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416781/27/2022 U19-Calistoga Electric Fire Pump 2021 Q4 Report_CONFIDENTIAL

5 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416771/27/2022 U16-Quicksilver Wet Sprinkler 2021 Q4 Report_CONFIDENTIAL

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416761/27/2022 U16-Quicksilver Deluge 2021 Q4 Report_CONFIDENTIAL

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416751/27/2022 U18-Socrates Wet Sprinkler 2021 Q4 Report_CONFIDENTIAL

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416741/27/2022 U18-Socrates Deluge 2021 Q4 Report_CONFIDENTIAL

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416731/27/2022 U17-Lakeview Wet Sprinkler 2021 Q4 Report_CONFIDENTIAL

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416721/27/2022 U17-Lakeview Deluge 2021 Q4 Report_CONFIDENTIAL

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416711/27/2022 U03-Sonoma Deluge 2021 Q4 Report_CONFIDENTIAL

4 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416701/27/2022 U03-Sonoma Wet Sprinkler 2021 Q4 Report_CONFIDENTIAL

3 page(s)
 CEC/Eric VeerkampEllison Schneider Harris & Donlan LLP
2416691/27/2022 U03-Sonoma Pre-action 2021 Q4 Report_CONFIDENTIAL

3 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
2416681/27/2022 Geysers Power Company ITM Report Cover Letter_CONFIDENTIAL

5 page(s)
 CEC/Eric VeerkampEllison Schneider Harris & Donlan LLP
2415632/16/2022 GPC Response to Executive Director's Confidentiality Determination

2 page(s)
  Ellison Schneider Harris & Donlan LLP
2413752/2/2022 CEC Response Letter Geysers #3 Confidential Application May 25, 2018, Nov 19 and Dec 10, 2021, and Jan 10 and 27, 2022

Compliance
11 page(s)
 J Harris of Ellison Schneider Harris & Donlan LLPCalifornia Energy Commission
2413031/27/2022 Application for Confidential Designation

8 page(s)
 CEC/Drew BohanEllison Schneider Harris & Donlan LLP
24099812/20/2021 Annual Compliance Report - Socrates

Compliance
84 page(s)
 CEC/Mr. Eric W. Veerkamp, Compliance Project ManagerGeysers Power Company, LLC
24081012/3/2021 Unit 18 Socrates Application for Confidential Designation - applications-fire suppression docs-2018

33 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24080812/3/2021 Unit 18 Socrates Application for Confidential Designation - applications-fire suppression docs-2018

33 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24080712/3/2021 Unit 18 - Socrates Application for Confidential Designation

33 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24080412/3/2021 Unit 18 Socrates Application for Confidential Designation - applications-fire suppression docs-2018

33 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24080012/3/2021 applications-fire suppression docs-2018

33 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24079712/3/2021 applications-fire suppression docs-2018

33 page(s)
 CEC/Drew BohanEllison Schneider Harris Donlan
24067811/22/2021 Application for Confidential Designation

9 page(s)
  Ellison Schneider Harris & Donlan LLP
24066011/22/2021 GPC October 2021 Monthly Recommissioning Report

3 page(s)
 CEC/Eric VeerkampEllison Schneider Harris & Donlan LLP
24055911/10/2021 June 2021 Monthly Recommissioning Report

Compliance
3 page(s)
 CEC/Eric VeerkampEllison Schneider Harris Donlan
24055311/10/2021 Monthly Recommissioning Report_August 2020_PUBLIC

3 page(s)
 CEC/Docket UnitCalifornia Energy Commission
24053111/9/2021 December 2020 Geysers Monthly Recommissioning Report

4 page(s)
 CEC/docket unitCalifornia Energy Commission
24052511/9/2021 November 2020 Geysers Monthly Recommissioning Report

3 page(s)
 CEC/docket unitCalifornia Energy Commission
24051911/9/2021 October 2020 Geysers Monthly Recommissioning Report

3 page(s)
 CEC/docket unitCalifornia Energy Commission
24051311/9/2021 September 2020 Geysers Monthly Recommissioning Report

5 page(s)
 CEC/docket unitCalifornia Energy Commission
24050711/9/2021 Monthly Recommissioning Report_July 2020

3 page(s)
 CEC/docket unitCalifornia Energy Commission
24050111/9/2021 Monthly Recommissioning Report (June 2020)

3 page(s)
 CEC/docket unitCalifornia Energy Commission
24049511/9/2021 Monthly Recommissioning Report (May 2020)

3 page(s)
 CEC/docket unitCalifornia Energy Commission
24048511/9/2021 GPC Monthly Recommissioning Report - April 2020

3 page(s)
 CEC/Docket UnitCalifornia Energy Commission
24047611/9/2021 August 2021 Monthly Recommissioning Report
Fire System Recommissioning Report for Geysers
Compliance
3 page(s)
 CEC/Eric VeerkampCalifornia Energy Commission
24047511/9/2021 July 2021 Monthly Recommissioning Report
Fire System Recommissioning Report for Geysers
Compliance
3 page(s)
 CEC/Eric VeerkampCalifornia Energy Commission
24047411/9/2021 September 2021 Monthly Recommissioning Report
Fire System Recommissioning Report for Geysers
Compliance
3 page(s)
 CEC/Eric VeerkampCalifornia Energy Commission
24047211/9/2021 May 2021 Monthly Recommissioning Report
Fire System Recommissioning Report for Geysers
Compliance
3 page(s)
 CEC/Eric VeerkampCalifornia Energy Commission
24047111/9/2021 February 2021 Monthly Recommissioning Report
Fire System Recommissioning Report for Geysers
Compliance
4 page(s)
 CEC/Eric VeerkampCalifornia Energy Commission
24047011/9/2021 April 2021 Monthly Recommissioning Report
Fire System Recommissioning Report for Geysers
Compliance
3 page(s)
 CEC/Eric VeerkampCalifornia Energy Commission
24046911/9/2021 March 2021 Recommissioning Report
Fire System Recommissioning Report for Geysers
Compliance
3 page(s)
 CEC/Eric VeerkampCalifornia Energy Commission
24046811/9/2021 January 2021 Monthly Recommissioning Report
Fire System Recommissioning Report for Geysers
Compliance
4 page(s)
 CEC/Eric VeerkampCalifornia Energy Commission
23570011/19/2020 ORDER APPROVING SETTLEMENT

3 page(s)
 CEC/DocketsCalifornia Energy Commission
2326944/8/2020 Geysers Power Company, LLC Comments - 2019 Annual Compliance Report

Compliance
18 page(s)
 CEC/DocketsGeysers Power Company, LLC
23132312/26/2019 2018 Annual Compliance Report for the Socrates Power Plant (Unit 18)
2018 Annual Compliance Report for the Socrates Power Plant (Unit 18) at the Geysers
Compliance
16 page(s)
 Mr Eric W VeerkampGeysers Power Company, LLC
23027910/18/2019 RESOLUTION - RE GEYSERS FACILITIES FIRE SYSTEM RECOMMISSIONING
Resolution No: 19-1014-4
1 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22612812/17/2018 Commission Order for Socrates 20181210 wet down system engine i
Final Commission Order for Geysers Socrates Unit 18, PTA for wet down system permanent diesel engine installation
Compliance
2 page(s)
 CEC/DocketsCalifornia Energy Commission
22593011/20/2018 Revised Air Quality and Worker Safety Conditions of Certification

Air Quality
8 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22573811/1/2018 Memo - Staff Response to Petitioner’s Comments on Staff’s Revised Air District Permit Conditions

6 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22566210/31/2018 Compliance Docketing Policy

3 page(s)
 CEC/DocketsCalifornia Energy Commission
22509310/25/2018 Notice of Staff Workshop
November 8, 2018 at 2:00 p.m.
4 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22503410/18/2018 Applicant's Comments on Staff's Revisions to Worker Safety-1 Condition of Certification

14 page(s)
 CEC/Eric Veerkamp and Keith WinsteadEllison Schneider Harris & Donlan LLP
22498610/15/2018 Revised Worker Safety-1 Condition of Certification

2 page(s)
 CEC/Docket UnitCalifornia Energy Commission
2247409/17/2018 Geysers Power Company LLC Comments on the Staff Analysis of the Petition to Amend

9 page(s)
 CEC/Keith WinsteadEllison Schneider Harris & Donlan LLP
2245778/23/2018 Staff Analysis – Permanent Diesel Pump for Cooling Tower Wetting System
The Geysers Power Company, LLC requests the Energy Commission to approve this petition to make identical modifications at each of the facilities to replace temporary portable emergency diesel engines with stationary permanent emergency diesel engines for the cooling tower wet down systems to aid in fire prevention at the Quicksilver, Socrates, and Grant geothermal power plants.
220 page(s)
 California Energy Commission 1516 9th Street. Sacramento, CA 95814California Energy Commission
2225372/13/2018 Air Quality Emissions & Impact Anaylsis

3 page(s)
 CEC/Ketih WinsteadCalpine
2223341/23/2018 Geysers Power Company, LLC - Consolidated Petition for a Staff Approved Modifications
FOR GEYSERS UNIT 16 (79-AFC-5C), UNIT 18 (79-AFC-3C), and UNIT 20 (82-AFC-1C)
16 page(s)
 CEC/Docket UnitGeysers Power Plant
2222851/19/2018 Notice of Receipt - Petition to Amend the Energy Commission Decisions for Geysers Unit 16, Unit 18 and Unit 20
PETITION TO AMEND THE ENERGY COMMISSION DECISIONS FOR GEYSERS UNIT 16 (79-AFC-5C), UNIT 18 (79-AFC-3C), and UNIT 20 (82-AFC-1C) TO ALLOW MINOR IMPROVEMENTS FOR FIRE PREVENTION COOLING TOWER WET-DOWN
3 page(s)
 CEC/Docket UnitCalifornia Energy Commission
22203712/21/2017 PTA Geysers-16, Quicksilver, Diesel Generator for Cooling Tower Wetting System
Petition to Amend (PTA) to install a permanent diesel generator for the cooling tower wetting system
56 page(s)
 CEC/Eric VeerkampGeysers Power Company, LLC
2071911/5/2016 Expedited Processing Pursuant to Ex Order B-36-15
Approval of Emergency Reconstruction Activities
Air Quality
7 page(s)
 Geysers Power Company, LLC/James KluesenerCalifornia Energy Commission
20675611/24/2015 Socrates (Unit 18) 1980 Final Decision

48 page(s)
  California Energy Commission
20675511/24/2015 Socrates (Unit 18) Compliance Plan

56 page(s)
  California Energy Commission
20674011/23/2015 Socrates (Unit 18) Executive Director's Approval of Expedited Processing for Cooling Tower Replacement

2 page(s)
  California Energy Commission
20673211/23/2015 Geysers Power Socrates (Unit 18) - Cooling Tower Replacement Project Description and Request for Expedited Processing

19 page(s)
  California Energy Commission
20670011/19/2015 Permission to Obtain and Implement County-Issued Demolition Permits to Abate Fire Damage to Structures at Geysers 16, 18, and 20
*** SEE PREVIOUSLY FILED LETTER. TN 206306 ***
2 page(s)
  California Energy Commission
20630610/8/2015 Executive Director's Permission Letter for Cooling Tower Demolition after the 2015 Valley Fire

2 page(s)
 Calpine Corporation/Bruce CarlsenCalifornia Energy Commission
319517/23/2004 REVIEW OF RECLAIMED WATER USES AT THE GEYSERS FACILITIES - - GEYSERS POWER COMPANY, LLC

4 page(s)
 CEC/DocketsRtp Environmental Assoc.
319437/23/2004 Comments to "Engineering Report for the Use of Recycled Water at The Geysers" Power Plant Units.

42 page(s)
 CEC/K. Defolo/docketsCa Rwqcb
311093/12/2004 Approval of Petition to Use Reclaimed Wastewater and Approval of Verification Changes

3 page(s)
 Calpine/Carslen/docketsCEC/Tronaas
310983/12/2004 Notice of Exemption - Petition to Allow the Use of Reclaimed Wastewater

1 page(s)
 Office Of Planning And Research/DocketsCEC/Tronaas
309602/20/2004 Notice of Insignificant Project Change for Geysers Units to Allow for Use of Reclaimed Wastewater
Unit 3 (80-AFC-1C), Unit 16 (79-AFC-5C), Unit 17 (79-AFC-1C), Unit 18 (79-AFC-3C), Unit 19 (81-AFC-1C), and Unit 20 (82-AFC-1C)
2 page(s)
 CEC/Docket UnitCEC/O'brien
296898/15/2003 Comments on the petition to the California Energy Commission to amend the Energy Commission Decisions for Geysers Unit 3, 16, 17, 18, 19 and 20 to allow selected uses of reclaimed wastewater

3 page(s)
 O'brien/CecCalifornia Regional Water Quality Control Board/Ma
291577/10/2003 Notice of Receipt, Petition to Amend the Energy Commission Decisions (79-AFC-3C)

3 page(s)
 DocketsCEC/O'brien
291336/25/2003 License Amendments

43 page(s)
 CEC/Tronaas/docketsCh2mhill/Salamy
117734/22/1999 Commission Order Approving Ownership Transfers

1 page(s)
 CEC/Docket FileCEC/Keese
107313/30/1999 Notice of Receipt - The CEC has received a petition requesting an ownership change for the Geysers Power Plant Units 16, 17, 18 and 20.

2 page(s)
 CEC/Docket FileCEC/Therkelsen
55779/22/1994 PG&E GEYSERS POWER PLANT - MODIFICATION REQUESTS TO COMPLIANCE MONITORING PLANS FOR UNITS 16-20

1 page(s)
 CEC/BrandPg&e/Speer
6523/14/1995 LETTER REQUESTING THAT MODIFICATIONS BE GRANTED BY CEC STAFF AFTER REVIEW OF REQUEST DATED 9-14-95

3 page(s)
 CEC/BrandPg&e
65110/19/1994 NOTICE OF RECEIPT - REQUEST TO AMEND CHANGES - IN DECISION - ASSESS IMPACTS ON ENVIRENMENTAL QUALTIY, PUBLIC HEALTH & SAFETY, AND CONSISTENCY OF PROPOSED CHANGES

1 page(s)
 CEC/Docket FileCEC/Therkelsen