| 269480 | 4/14/2026 |
Monthly Compliance Report No 10 DCEP Monthly Compliance Report for March 2026 reporting month
Compliance 194 page(s)
| | CEC/Docket Unit | Rincon |
| 269402 | 3/5/2026 |
Option Agreement BAAH
31 page(s)
| | CEC/Brett Fooks | Intersect |
| 269401 | 4/2/2026 |
CEC Response to IP Darden I, LLC and Affiliates co Intersect USA, LLC's Application for Confidentiality Response to TN 268945 2 page(s)
| | IP Darden I, LLC and Affiliates c/o Intersect USA, LLC c/o Will Lutkewitte | California Energy Commission |
| 269194 | 3/13/2026 |
MCR No 9 Appendix C Appendix C for DCEP February MCR.
77 page(s)
| | CEC/Docket Unit | Rincon |
| 269193 | 3/13/2026 |
Monthly Compliance Report No 9 DCEP Monthly Compliance Report for February reporting month
110 page(s)
| | CEC/Docket Unit | Rincon |
| 268945 | 3/5/2026 |
Confidentiality Request Option Agreement
2 page(s)
| | CEC/Brett Fooks | Intersect |
| 268743 | 2/20/2026 |
Application for Confidential Designation of DCEP Local Investment Program Implementation Progress Report Jan 2026 ***Applicant requested to withdraw Application on 3/23/26 and approved by A. Mayer - ks***
Application for confidential designation of DCEP Local Investment Program Implementation Progress Report as required to be reported to the DCEP CPM per COCs CBA-1 and CBA-2 3 page(s)
| | Joseph Douglas, CPM | Intersect |
| 268644 | 2/13/2026 |
Monthly Compliance Report No 8 DCEP Monthly Compliance Report for January reporting month.
Compliance 26 page(s)
| | CEC/Docket Unit | Rincon |
| 268643 | 2/13/2026 |
MCR No 8 Appendices Appendices for DCEP January MCR. Compliance 95 page(s)
| | CEC/Docket Unit | Rincon |
| 268642 | 2/13/2026 |
MCR No 8 Appendix C Appendix C for DCEP January MCR. Compliance 98 page(s)
| | CEC/Docket Unit | Rincon |
| 268296 | 1/23/2026 |
Darden Clean Energy Project 23-OPT-02C Full Notice to Proceed with Construction Activities Compliance 2 page(s)
| | CEC/Docket Unit | California Energy Commission |
| 268233 | 1/14/2026 |
Harlan BAAH MCR #7 DCEP Dec MCR: Appendix C Harlan BAAH MCR Compliance 83 page(s)
| | CEC/Docket Unit | Rincon |
| 268232 | 1/14/2026 |
Monthly Compliance Report No 7 DCEP Monthly Compliance Report for December reporting month. Compliance 89 page(s)
| | CEC/Docket Unit | Rincon |
| 268079 | 12/30/2025 |
CBA-02_Local Investment Program Progress Report January 2026 progress report providing updates on the Darden Project's Local Investment Program in compliance with the requirements in condition of certification CBA-2 Compliance 80 page(s)
| | CEC/Docket Unit | Rincon Consultants |
| 267905 | 12/12/2025 |
Monthly Compliance Report No 6 DCEP November Monthly Compliance Report 146 page(s)
| | CEC/Docket Unit | Rincon |
| 267890 | 12/11/2025 |
LNTP-substation and BESS pad LNTP 2 page(s)
| | Intersect Power/Marisa Mitchell | CEC |
| 267754 | 11/26/2025 |
Darden Clean Energy Project (23-OPT-02C) Limited Notice to Proceed with Construction Activities Letter to Marisa Mitchell, Intersect Power Compliance 3 page(s)
| | CEC/Dockets | California Energy Commission |
| 267596 | 11/17/2025 |
Monthly Compliance Report No 5 Monthly Compliance Report No. 5 Reporting Period October 2025 77 page(s)
| | CEC/Docket Unit | Rincon |
| 266993 | 10/21/2025 |
IP Darden Fire Service Agreement Signed agreement between IP Darden and Fresno County Fire Protection District. 22 page(s)
| | Dr. Drew Bohan | Fresno County Fire Protection District |
| 266992 | 11/3/2025 |
CEC Response to Fresno County Fire's Repeated Application for Confidentiality Automatically Approved pursuant to California Code of Regulations title 20, section 2505(b). 1 page(s)
| | Joseph Andrew Cosentino / Fresno Co. Fire | California Energy Commission |
| 266837 | 10/24/2025 |
Letter to Marisa Mitchell Intersect Power Darden Clean Energy Project (23-OPT-02C) Limited Notice to Proceed with Construction Activities 2 page(s)
| | CEC/Docket Unit | California Energy Commission |
| 266721 | 10/21/2025 |
FCFPD Request for Confidentiality Application Confidentiality Application 2 page(s)
| | Dr. Drew Bohan | Fresno County Fire Protection District |
| 266619 | 10/15/2025 |
Monthly Compliance Report No 4 Monthly Compliance Report No. 4 Reporting Period September 2025 Compliance 102 page(s)
| | CEC/Docket Unit | Rincon Consultants |
| 266019 | 9/15/2025 |
Darden Clean Energy Project 23-OPT-02C Monthly Compliance Report no. 3 Reporting Period August 2025 84 page(s)
| | Joseph Douglas, Compliance Project Manager | Intersect |
| 265738 | 8/21/2025 |
Darden Clean Energy Project 23-OPT-02C Monthly Compliance Report no. 2 Reporting Period July 2025 Compliance 88 page(s)
| | | California Energy Commission |
| 265179 | 7/31/2025 |
CEC Memo Open Darden Compliance
1 page(s)
| | CEC/Docket Unit | California Energy Commission |