205331 | 7/13/2015 |
GWF Alternative Water Staff Analysis Of Petition for Approval of Alternative Water Supplies 36 page(s)
| | Interested Parties | California Energy Commission |
59308 | 12/17/2010 |
Authorization to Begin Site Mobilization
1 page(s)
| | CEC/Docket Unit | CEC/ C. Davis |
57280 | 6/21/2010 |
Final Exhibit List Exhibits 1-98
10 page(s)
| | CEC/ Docket Unit | CEC/ Hearing Office |
56096 | 4/2/2010 |
CEC Notice of Decisions
5 page(s)
| | CEC/ Docket Unit | CEC/ A. Solomon |
56074 | 3/30/2010 |
Final Commission Decision and notice of availability
389 page(s)
| | CEC/Docket Unit | CEC/M.Read |
55966 | 3/17/2010 |
Errata to the Presiding Member's Proposed Decision
6 page(s)
| | CEC/Docket Unit | CEC/M. Read |
55950 | 3/17/2010 |
Staff's Comments on the Presiding Member's Proposed Decision
5 page(s)
| | CEC/Docket Unit | CEC/J. Preis |
55764 | 3/4/2010 |
Applicant's Comments on the Presiding Member's Proposed Decision
6 page(s)
| | CEC/ Docket Unit | Latham & Watkins/ P. Kihm |
55507 | 2/17/2010 |
Notice of Availability of the Presiding Member's Proposed Decision & Notice of Commission Hearing
389 page(s)
| | CEC/ Docket Unit | CEC/ R. Avalos |
54402 | 12/10/2009 |
Letter Requesting to Docket Statement of Support
2 page(s)
| | CEC/ R. Renaud | Hefner, Stark, & Marios/ T. Taron |
54230 | 11/24/2009 |
Air Quality Errata
10 page(s)
| | CEC/K. Douglas/A. Rosenfeld/R. Renaud | CEC/A. Solomon |
54226 | 11/20/2009 |
Declaration of Doug Wheeler as Supplemental Testimony RE Power Plant Efficiency & Greenhouse Gas Emissions
9 page(s)
| | CEC/ Docket Unit | Latham & Watkins LLP/ P. Kihm |
54205 | 11/23/2009 |
CEC Staff's Errata to the Final Staff Assessment
42 page(s)
| | CEC/K. Douglas/A. Rosenfeld/R. Renaud | CEC/A. Solomon |
54188 | 11/19/2009 |
Notice of Committee Intent to Take Official Notice at Evidentiary Hearing
3 page(s)
| | CEC/ Docket Unit | CEC/ R. Renaud |
54170 | 11/18/2009 |
Evidentiary Hearing Order
16 page(s)
| | CEC/ Docket Unit | CEC/ K. Douglas & A. Rosenfeld |
54098 | 11/12/2009 |
Applicant's Prehearing Conference Statement
55 page(s)
| | CEC/ Docket Unit | Latham & Watkins LLP/ P. Kihm |
54060 | 11/12/2009 |
Staff's Prehearing Conference Statement
4 page(s)
| | CEC/ Docket Unit | CEC/ K. Willis |
54059 | 11/11/2009 |
Applicant's Comments on the Final Staff Assessment
8 page(s)
| | CEC/ Docket Unit | Latham & Watkins/ P. Kihm |
53968 | 11/4/2009 |
Revised Notice of Prehearing Conference & Evidentiary Hearing
8 page(s)
| | CEC/ Docket Unit | CEC/ K. Douglas |
53961 | 11/3/2009 |
Library Letter for the Final Staff Assessment
6 page(s)
| | CEC/Docket Unit | CEC/E. Allen |
53960 | 11/3/2009 |
Agency Letter for the Final Staff Assessment
4 page(s)
| | CEC/Docket Unit | CEC/E. Allen |
53959 | 11/3/2009 |
Notice of Availability of the Final Staff Assessment
6 page(s)
| | CEC/Docket Unit | CEC/E. Allen |
53953 | 11/3/2009 |
Notice of Prehearing Conference & Evidentiary Hearing
7 page(s)
| | CEC/ Docket Unit | CEC/ K. Douglas & A. Rosenfeld |
53868 | 10/30/2009 |
Final Staff Assessment
699 page(s)
| | CEC/Docket Unit | CEC/A. Solomon |
52946 | 8/24/2009 |
Table DR 71-1: Cooling Tower Model
4 page(s)
| | CEC/ R. Jones | Grenier & Associates, Inc/ A. Grenier |
52933 | 8/24/2009 |
Final Determination of Complaince
328 page(s)
| | CEC/ A. Solomon | San Joaquin Valley Air Pollution Control District/ D. Warner |
52908 | 8/19/2009 |
Letter from USEPA to San San Joaquin Valley Air Pollution Control District
1 page(s)
| | San Joaquin Valley Air Pollution Control District/ D. Warner | United States Enviornmental Protection Agency/ G. Rios |
52810 | 8/10/2009 |
Letter from BBID to Vince Geronimo about M& I Water Supply
1 page(s)
| | Vince Geronimo | Byron Bethany Irrigation District/ Rick Gilmore |
52809 | 8/10/2009 |
Telephone Conversation Record regarding GWF Tracy Raw Water Allocations from BBID
1 page(s)
| | GWF/ Doug Wheeler | PWA/ Vince Geronimo |
52690 | 8/4/2009 |
CEC Staff's Status Report #6
3 page(s)
| | CEC/K. Douglas/A. Rosenfeld/R. Renaud | CEC/A. Solomon |
52616 | 7/29/2009 |
Report of Conversation(ROC) between A. Wallce and Delta - Mendota Water Authority
5 page(s)
| | San Luis & Delta Mendota Water Authority/ B. Marlin | Anne Wallace |
52615 | 7/29/2009 |
Report of Conversation between A. Wallace and PG&E
1 page(s)
| | PG&E/ G. Parker | Anne Wallace |
52548 | 7/23/2009 |
Appendices to the System Impact Study
224 page(s)
| | CEC/ A. Solomon | GWF Tracy/ J. Salamy |
52542 | 7/23/2009 |
Applicant's Preliminary Staff Assessment(PSA) Workshop Response to Public Comments
15 page(s)
| | CEC/ A. Solomon | GWF Tracy/ J. Salamy |
52536 | 7/23/2009 |
Report of Conversation(ROC) Regarding Measure A & Tracy Hills
1 page(s)
| | City of Tracy/ B. Dean | CEC/ M. McLean |
52431 | 7/15/2009 |
San Joaquin Valley Air Pollution Control District(APCD) E-mail from CEQA-ISR Staff
1 page(s)
| | CEC/ A. Solomon | San Joaquin Valley Air/ J. Willis |
52430 | 7/15/2009 |
Comments of the Tuso Family Presented at the June 23rd PSA Workshop
4 page(s)
| | CEC/ A. Soloman | The Tuso Family |
52355 | 7/9/2009 |
CH2MHILL Comments on the Preliminary Staff Assessment
16 page(s)
| | CEC/ A. Solomon | CH2MHILL/ J. Salamy |
52303 | 7/6/2009 |
Letter from Timothy Taron Representing Tracy Hills, LLC Concerning GWF Tracy
2 page(s)
| | CEC/ A. Soloman | Hefner, Stark & Marois LLP/ T. Taron |
52065 | 6/17/2009 |
FAA Determination of No Hazard and GWF Tracy FAA Form 7460-1
8 page(s)
| | CEC/ A. Solomon | CH2MHILL/ J. Salamay |
52006 | 6/15/2009 |
Applicant's Interconnection System Impact Restudy-Interconnection Facilities Study Report
27 page(s)
| | CEC/ A. Solomon | CH2M Hill/ J. Salamy |
51887 | 6/9/2009 |
Notice of Availability and Notice of Public Workshop to Agencies
9 page(s)
| | Agencies | CEC/T. O'Brien |
51886 | 6/9/2009 |
Notice of Availability and Notice of Public Workshop to Members of the Public
9 page(s)
| | Member of the Public | CEC/T. O'Brien |
51885 | 6/9/2009 |
Library Letter with Notice of Availability & Notice of Public Workshop
8 page(s)
| | CEC/Docket Unit | CEC/E. Knight |
51876 | 6/9/2009 |
Preliminary Staff Assessment
581 page(s)
| | CEC/Docket Unit | CEC/A. Solomon |
51873 | 6/8/2009 |
E-mail from CDFG to CEC
2 page(s)
| | CEC/ A. Solomon | Public/ A. Wallace |
51872 | 6/8/2009 |
E-mail from US Fish and Wildlife Service to CEC
3 page(s)
| | CEC/ A. Solomon | Public/ A. Wallace |
51792 | 6/2/2009 |
Letter from United States Enviornmental Protection Agency to San Joaquin Valley Air Pollution Control District
8 page(s)
| | San Joaquin Valley Air Pollution Control District/ D. Warner | United States Enviornmental Protection Agency/ G. Rios |
51724 | 5/28/2009 |
Report of Conversation(ROC) Between J. Hawkins and San Joaquin County Planning Division Director
1 page(s)
| | CEC/ Docket Unit | San Joaquin Co/ C. Martin |
51723 | 5/28/2009 |
Report of Conversation(ROC) Between S. Debauche and Tracy Municipal Airport Coordinator
1 page(s)
| | CEC/ Docket Unit | Public/ S. Debauche |
51722 | 5/28/2009 |
2001 Letter from San Joaquin county to C. Davis Discussing Land Mitigation for TPP
9 page(s)
| | CEC/ C. Davis | San Joaquin County/ B. Hulse |
51638 | 5/21/2009 |
Letter from D. Warner Regarding Air Quality Mitigation Settlement Agreement
2 page(s)
| | CEC/ A. Solomon | San Joaquin Valley/ D. Warner |
51372 | 4/30/2009 |
CEC's Comments on the Preliminary Determination of Compliance Issued by the San Joaquin Valeey Air Pollution Control District
6 page(s)
| | SJVAPCD/D. Warner | CEC/P. David |
51290 | 4/24/2009 |
Applicants Review and Response to Preliminary Determination of Compliance
20 page(s)
| | San Joaquin Valley APCD/ D. Warner | GWF Tracy/ M. Kehoe |
51259 | 4/24/2009 |
Energy Commission Staff's Status Report #5
4 page(s)
| | CEC/K. Douglas/A. Rosenfeld | CEC/A. Solomon |
51031 | 4/14/2009 |
San Joaquin Valley Air Pollution Control District Preliminary Determination of Compliance
281 page(s)
| | CEC/ A. Solomon | San Joaquin APCD/ D. Warner |
50879 | 4/6/2009 |
Letter to Matthew Franklin Native American Community RE Proposed New Power Plant
1 page(s)
| | Chairperson Mathew Franklin | CEC/ Dale Edwards |
50878 | 4/6/2009 |
Letter to Randy Yonemura Native American Community RE Proposed New Power Plant
1 page(s)
| | Randy Yonemura | CEC/ Dale Edwards |
50877 | 4/6/2009 |
Letter to Silvia Burley Native American Community RE Proposed New Power Plant
1 page(s)
| | Silvia Burley | CEC/ Dale Edwards |
50876 | 4/6/2009 |
Letter to Heritage Cultural Committee Native American Community RE Proposed New Power Plant
1 page(s)
| | Heritage Cultural Committee | CEC/ Dale Edwards |
50875 | 4/6/2009 |
Letter to Jay Johnson Native American Community RE Proposed New Power Plant
1 page(s)
| | Jay Johnson Spiritual Leader | CEC/ Dale Edwards |
50874 | 4/6/2009 |
Letter to Anthony Brochini Native American Community re Proposed Tracy Plant
1 page(s)
| | Chairperson Anthony Brochini | CEC/ Dale Edwards |
50873 | 4/6/2009 |
Letter to Les James Native American Community RE Proposed Tracy Plant
1 page(s)
| | Les James Spiritual Leader | CEC/ Dale Edwards |
50872 | 4/6/2009 |
Letter to Katherine Erolinda Perez Native American Community re Proposed Power Plant
1 page(s)
| | Katherine Erolinda Perez | CEC/ Dale Edwards |
50667 | 3/25/2009 |
Applicant's Status Report #3
6 page(s)
| | CEC/ Docket Unit | Latham&Watkins/ P. Kihm |
50648 | 3/25/2009 |
California Energy Commission Staff Status Report #4
3 page(s)
| | CEC/K. Douglas/A. Rosenfeld | CEC/A. Solomon |
50286 | 2/26/2009 |
San Joaquin Count Environment Health Department Comments
4 page(s)
| | CEC/ T. O'Brien | San Joaquin County EHD/ Rodney Estrada |
50257 | 2/25/2009 |
All Parties Letter
4 page(s)
| | CEC/ Docket Unit | CEC/ M. Read |
50045 | 2/10/2009 |
Status Report #3
1 page(s)
| | CEC/K. Douglas/A. Rosenfeld/R. Renaud | CEC/A. Solomon |
49841 | 1/23/2009 |
Workshop Data Responses Set 1
23 page(s)
| | CEC/ Alan Solomon | CH2MHILL/ Jerry Salamy |
49710 | 1/15/2009 |
Applicant's Status Report #2
5 page(s)
| | CEC/ Docket Unit | Latham&Watkins/ P. Kihm |
49702 | 1/14/2009 |
Staff's Status Report 2
1 page(s)
| | CEC/K. Douglas | CEC/A. Solomon |
49700 | 1/12/2009 |
Data Response Set 1A
10 page(s)
| | CEC/ C. Meyer | CH2M Hill/ J. Salamy |
49662 | 1/8/2009 |
E-mail with Estimate Air-Cooled Condenser Mass Flow & Operating Data from Jerry Salamy
1 page(s)
| | Aspen Enviornmetal Group/ W. Walters | CH2MHill/ J. Salamy |
49337 | 12/10/2008 |
Committee Order Granting Petition to Intervene and Partially Granting Petiton for Financial Hardship
3 page(s)
| | CEC/ Interested Parties | CEC/ K. Douglas/ A. Rosenfeld |
49271 | 12/4/2008 |
Applicant's Status Report #1
5 page(s)
| | CEC/ Docket Unit | Latham&Watkins/ P. Kihm |
49256 | 12/4/2008 |
GWF Tracy Status Report #1
1 page(s)
| | CEC/ K. Douglas | CEC/ C. Meyer |
49161 | 11/26/2008 |
Notice of Staff Data Response & Issue Resolution Workshop
5 page(s)
| | CEC/Docket Unit | CEC/T. O'Brien |
49102 | 11/21/2008 |
Petition to Intervene & Petition for Financial Hardship
2 page(s)
| | CEC/ Docket Unit | Public/ R. Sarvey |
49055 | 11/19/2008 |
Data Response Set 1
44 page(s)
| | CEC/ C. Meyer | CH2MHILL/J. Salamy |
48876 | 11/4/2008 |
Letter to Senior Planner
4 page(s)
| | City of Tracy/ V. Lombardo | CEC/ D. Edwards |
48875 | 11/4/2008 |
Letter to Community Development Department
60 page(s)
| | San Joaquin/ C. Martin | CEC/ D. Edwards |
48856 | 10/31/2008 |
Committee Scheduling Order
4 page(s)
| | CEC/ Docket Unit | CEC/ K. Douglas |
48843 | 10/30/2008 |
Tracy Informational Hearing & Site Visit Powerpoint Presentation
11 page(s)
| | CEC/ Docket Unit | CEC/ E. Miller |
48786 | 10/28/2008 |
Committee Order Granting Petition to Intervene
4 page(s)
| | CEC/ Docket Unit | CEC/ K. Douglas |
48778 | 10/28/2008 |
Applicant's Power Point Presentation at Informational Hearing
21 page(s)
| | CEC/ Docket Unit | CEC/ C. Meyer |
48680 | 10/21/2008 |
Data Requests Set 1 (#s 1-37)
15 page(s)
| | GWF/D. Wheeler | CEC/C. Meyer |
48675 | 10/21/2008 |
Receipt of letter dated Oct 14 re Request for Intervention
receipt of letter dated Oct. 14, 08 requestibg Intervention
7 page(s)
| | Seligman & Willett/ H. Seligman | CEC/ R. Renaud |
48656 | 10/17/2008 |
Document Handling for the Application for Certification - Supplemental Information
2 page(s)
| | CEC/Docket Unit | CEC/E. Knight |
48651 | 10/17/2008 |
Request for Agency Participation in the Review of the Application for Certification - Supplemental Information
1 page(s)
| | Agency Distribution List | CEC/E. Knight |
48650 | 10/17/2008 |
Notice of Receipt Supplemental Information for the Application for Certification
3 page(s)
| | CEC/Docket Unit | CEC/E. Knight |
48597 | 10/15/2008 |
Issues Identification Report
6 page(s)
| | CEC/ K. Douglas | CEC/ C. Meyer |
48588 | 10/15/2008 |
Letter RE Application for Certification for GWF Tracy Combined Cycle Power Plant Project
5 page(s)
| | CEC/ Public Advisors | Seligman & Willett INC/ H. L. Seligman |
48297 | 10/1/2008 |
Letter in response to Cultural Resources Application for Confidentiality
2 page(s)
| | CH2MHILL/ J.Salamy | CEC/ M. Jones |
48293 | 10/1/2008 |
Letter i nResponse to Paleontological Resources Application for Confidentiality
2 page(s)
| | CH2MHILL/ Jerry Salamy | CEC/ Melissa Jones |
48197 | 9/26/2008 |
Notice of Informational Hearing and Site Visit
7 page(s)
| | CEC/ Docket Unit | CEC/ M. Read |
48194 | 9/26/2008 |
Agricultural Mitigation Plan
15 page(s)
| | County of San Joaquin/ B. Hulse | CEC/ C. Huntley |
48151 | 9/23/2008 |
Applicant's Statement RE GW ReCharge Lead Time
3 page(s)
| | CEC/ J. Kessler | Latham&Watkins/ M. Carroll |
48150 | 9/23/2008 |
CEC Letter in Response to Application for Confidentiality - Cultural
20 page(s)
| | CH2MHill/ J. Salamy | CEC/ M. Jones |
48125 | 9/22/2008 |
Senator Notification of GWF Tracy Application for Certification to D. Perata
1 page(s)
| | CA State Senate/D. Perata | CEC/M. Jones |
48124 | 9/22/2008 |
Assemblymember Notification of GWF Tracy Application for Certification to C. Galgiani
1 page(s)
| | CA State Assembly/C. Galgiani | CEC/M. Jones |
48123 | 9/22/2008 |
Assemblymember Notification of GWF Tracy Application for Certification to G. Houston
1 page(s)
| | CA State Assembly/G. Houston | CEC/M. Jones |
48122 | 9/22/2008 |
Vice Chairman Notification of GWF Tracy Application for Certification
1 page(s)
| | SJ County Board of Supervisors/L. Ornellas | CEC/M. Jones |
48121 | 9/22/2008 |
Mayor Notification of GWF Tracy Application for Certification
1 page(s)
| | City of Tracy/B. Ives | CEC/M. Jones |
48120 | 9/22/2008 |
Senator Notification of GWF Tracy Application for Certification to D. Cogdill
1 page(s)
| | CA State Senate/D. Cogdill | CEC/M. Jones |
48118 | 9/22/2008 |
Senator Notification of GWF Tracy Application for Certification to M. Machado
1 page(s)
| | CA State Senate/M. Machado | CEC/M. Jones |
48040 | 9/15/2008 |
Application for Confidential Designation - Cultural Resources Reports
544 page(s)
| | CEC/M. Jones | CH2M Hill/J. Salamy |
47999 | 9/11/2008 |
Hearing Officer Assignment
1 page(s)
| | CEC/ Commissioners | CEC/ J. Pfannenstiel |
47997 | 9/10/2008 |
Application for Confidential Designation - Paleontological Figures PAL-1 and PAL-2
5 page(s)
| | CEC/M. Jones | CH2MHill/J. Salamy |
47928 | 9/5/2008 |
Response to Data Adequacy Review
60 page(s)
| | CEC/ Docket Unit | CH2MHILL |
47918 | 9/5/2008 |
GWF Tracy Combined Cycle Project Revising Data Adequacy
44 page(s)
| | CEC/ C. Meyers | CEC/ M. Jones |
47718 | 8/25/2008 |
Letter from San Joaquin Valley APCD RE: Notice of Receipt of Complete Applications
2 page(s)
| | GWF Energy / M. Kehoe | SJVAPCD / D. Warner |
47549 | 8/14/2008 |
GWF Tracy Data Adequacy Recommendation
91 page(s)
| | CEC / J. Pfannenstiel / J. Byron / J. Boyd / K. Douglas / A. Rosenfeld | CEC / M. Jones |
47486 | 8/7/2008 |
Application for Confidential Designation - Cultural Resources Reports
3 page(s)
| | CEC/M. Jones | CH2MHill/J. Salamy |
47469 | 8/6/2008 |
Application for Confidential Designation - Paleontological Resources Report
26 page(s)
| | CEC/M. Jones | CH2MHill/J. Salamy |
47393 | 8/4/2008 |
Notice of Receipt of an Application for Certification for the GWF Tracy Combined Cycle Power Plant (08-AFC-7)
3 page(s)
| | CEC/Docket Unit | CEC/E. Allen |
47392 | 8/4/2008 |
Request for Agency (Local) Participation in the Review of the GWF Tracy Combined Cycle Power Plant Application for Certification (08-AFC-7)
4 page(s)
| | CEC/Docket Unit | CEC/E. Allen |
47391 | 8/4/2008 |
Request for Agency (State & Local) Participation in the Review of the GWF Tracy Combined Cycle Power Plant, Application Certification
4 page(s)
| | CEC/Docket Unit | CEC/E. Allen |
47390 | 8/4/2008 |
Document Handling for the GWF Tracy Combined Cycle Power Plant Application for Certification (08-AFC-7)
5 page(s)
| | CEC/Docket Unit | CEC/E. Allen |
47109 | 7/18/2008 |
Appendix 5.14A Phase I environmental Site Assessment
309 page(s)
| | CEC / Docket Unit | GWF / D. Wheeler |
47108 | 7/18/2008 |
Appendix 3A System Impact Study Report
574 page(s)
| | CEC / Docket Unit | GWF / D. Wheeler |
47107 | 7/18/2008 |
Air Quality Modeling Files
1 page(s)
| | CEC / Docket Unit | GWF / D. Wheeler |
47106 | 7/18/2008 |
Public Health Modeling Files
1 page(s)
| | CEC / Docket Unit | GWF / D. Wheeler |
47105 | 7/18/2008 |
Application for Certification for GWF Tracy Combined Cycle Power Plant Project
1000 page(s)
| | CEC/ M. Jones | GWF Energy LLC/ D. Wheeler |
2531-0 | 1/25/2010 |
Evidentiary Hearing
29 page(s)
| | | CEC |
2518-0 | 12/15/2009 |
Prehearing Conference
47 page(s)
| | | CEC |
2365-0 | 11/5/2008 |
Transcript of Informational Hearing
50 page(s)