Docket Log

Docket: 08-AFC-01C
Project Title: Avenal Energy Project-Compliance
Generated On: 3/29/2024 7:38:24 AM

Include:     
TN #Docketed DateDocument TitleExhibit #ToFrom
2411231/10/2022 Solar SME.INC Comments - Avenal Energy Project

Efficiency
1 page(s)
 CEC/Docket UnitSolar SME.INC
2053607/15/2015 Avenal's Intent Letter to Allow Its License to Expire on September 16, 2015 (Spanish Version)

Compliance
1 page(s)
 CEC/ Camille Remy ObadDay Carter & Murphy LLP
2051706/26/2015 Avenal Energy Project's Notice of its Intent to Let the License for the Project Expire on September 16, 2015

1 page(s)
 CEC/Camille Remy-ObadDay Carter & Murphy LLP
2051696/26/2015 Determination of Compliance for Avenal Power Center LLC

2 page(s)
 San Joaquin Valley Air Pollution Control District/Arnaud MarjolletDay Carter & Murphy LLP
2036022/4/2015 Avenal Status Report Letter

1 page(s)
 CEC/C. Remy-ObadAvenal Power Center, LLC
20348912/30/2014 Avenal Notice of Decision

1 page(s)
 CEC/Dockets UnitCalifornia Energy Commission
20348812/30/2014 Avenal Notice of Decision

1 page(s)
 CEC/Dockets UnitCalifornia Energy Commission
20348712/30/2014 Avenal Final Order #14-1210-6 Approval of Nine-Month Extension of Construction Commencement Deadline

4 page(s)
  California Energy Commission
20342512/9/2014 Arnaud Marjollet Comments: San Joaquin Valley APCD Comment

Air Quality
3 page(s)
 CEC/Camille Remy-ObadArnaud Marjollet
20332811/13/2014 Proyecto Energético Avenal (08-AFC-1C) Análisis del personal sobre la solicitud de postergar nueve (9) meses el inicio de la con

18 page(s)
 Interested PartiesCalifornia Energy Commission
20332111/7/2014 PROYECTO ENERGÉTICO AVENAL (08-AFC-1C) Extensión del Período de Comentarios Públicos hasta el 8 de diciembre 2014 para el Anális
PROYECTO ENERGÉTICO AVENAL (08-AFC-1C) Extensión del Período de Comentarios Públicos hasta el 8 de diciembre 2014 para el Análisis Personal de la Petición de Prórrogar el Inicio de la Construcción de Nueve (9) Meses
3 page(s)
 Interested PartiesCalifornia Energy Commission
20332011/7/2014 Extension of the Public Comment Period Until December 8, 2014
Avenal Energy Project (08-AFC-1C) Extension of the Public Comment Period Until December 8, 2014 for the Staff Analyses of Nine (9) Month Petition to Extend the Start of Construction
3 page(s)
 Interested PartiesCalifornia Energy Commission
20331611/5/2014 Avenal Energy Project (08-AFC-1C) Staff Analyses of Nine (9) Month Petition to Extend the Start of Construction

17 page(s)
 Interested PartiesCalifornia Energy Commission
20329310/31/2014 Notice of Receipt (Spanish Version)
Solicitud de Prórroga de la Fecha Límite Para Iniciar la Construcción del Proyecto Energético Avenal
3 page(s)
  California Energy Commission
20329210/31/2014 Notice of Receipt
Petition to Extend the Commencement of Construction Deadline
3 page(s)
  California Energy Commission
20323410/22/2014 Avenal Power Center, LLC's Petition for Post Certification Amendment to Extend the Construction Deadline

9 page(s)
 CEC/ Docket UnitDay Carter Murphy LLP
694002/6/2013 Order No. 13-0109-7 - Order Approving a Petition to Modify Five and Add One Air Quality Conditions of Certification

4 page(s)
 CEC/Docket UnitCEC/H.Kallemeyn
692841/24/2013 Notice of Decision

1 page(s)
 California Natural Resources AgenyCEC/ Camille Remy -Obad
690471/7/2013 Email submittal by Downey Brand on behalf of Avenal Power Center LLC, Regarding Response to Comments from the Center on Race, Poverty and The Environment

12 page(s)
 CEC/C. Remy-ObadDowneyBrand/ J. Luckhardt
690321/4/2013 CEC Staff's Response to CRPE Comments

3 page(s)
 CEC/CommissionersCEC/R.Ratliff /M.Layton
6898512/28/2012 Center on Race, Poverty & the Environments Comments and Associated Attachments on the Staff's Analysis of Proposed Modifications

36 page(s)
 CEC/Docket UnitCenter on Race, Poverty & The Environment/I.Brostrom
6860111/20/2012 Staff Analysis- Petition to Amend

20 page(s)
 Interested PartiesCEC/C.Remy-Obad
6827210/30/2012 Avenal Power Center LLC's Letter Request to Defer a Construction Deadline Extension Amendment

1 page(s)
 CEC/C.Remy-ObadDowney Brand LLP/J.Luckhardt
651785/11/2012 Corrected Notice of Receipt

3 page(s)
 CEC/Docket unitCEC/J.Walter
640763/9/2012 Notice of Receipt-Petition to Amend the Energy Commission Decision

3 page(s)
 CEC/Dockets UnitCEC/C.Marxen
639653/5/2012 Petition for Post Certification Amendment to Extend the Construction Deadline

29 page(s)
 CEC/ J. WalterDowney Brand/ L. Navarrot
638802/29/2012 Petition for Post Certification Amendment to Extend the Construction Deadline

21 page(s)
 CEC/Dockets UnitDowney Brand/L.Navarrot
607335/24/2011 Notice of Receipt Petition to Amend the Energy Commission Decision for the Avenal Energy Project

3 page(s)
 CEC/Dockets UnitCEC/C.Marxen
606645/17/2011 Avenal Power Center, LLC's Petition for Post Certification Amendment to Allow Construction and Operation of the Avenal Energy Project as Minor Source

287 page(s)
 CEC/ Dokcet UnitDowney Brand LLP
606195/11/2011 Avenal's Petition for Post Certification Amendmentto Allow Construction and Operation of the Avenal Energy Project as a Minor Source

287 page(s)
 CEC/ Docket UnitDowney Brand
580398/13/2010 USFWS Letter Regarding Biological Opinion

39 page(s)
 US Environmental Protection Agency/G. RiosUS Fish & Wildlife Service/S. Moore
503142/27/2009 MOU-Between CEC and Aims Corporation for Design Review, Plan Check and Construction Inspection

6 page(s)
 CEC/ Docket UnitCEC/ T. O'Brien/ AIMS/ D. Wimberly