Docket Log

Docket: 08-AFC-01C
Project Title: Avenal Energy Project-Compliance
Generated On: 4/16/2014 9:17:42 AM

TN #Docketed DateDocument TitleExhibit #ToFrom
694002/6/2013Order No. 13-0109-7 - Order Approving a Petition to Modify Five and Add One Air Quality Conditions of Certification
Order No. 13-0109-7 - Order Approving a Petition to Modify Five and Add One Air Quality Conditions of Certification
4 page(s)
 CEC/Docket UnitCEC/H.Kallemeyn
692841/24/2013Notice of Decision
Notice of Decision
1 page(s)
 California Natural Resources AgenyCEC/ Camille Remy -Obad
690471/7/2013Email submittal by Downey Brand on behalf of Avenal Power Center LLC, Regarding Response to Comments from the Center on Race, Poverty and The Environment
Email submittal by Downey Brand on behalf of Avenal Power Center LLC, Regarding Response to Comments from the Center on Race, Poverty and The Environment
12 page(s)
 CEC/C. Remy-ObadDowneyBrand/ J. Luckhardt
690321/4/2013CEC Staff's Response to CRPE Comments
CEC Staff's Response to CRPE Comments
3 page(s)
 CEC/CommissionersCEC/R.Ratliff /M.Layton
6898512/28/2012Center on Race, Poverty & the Environments Comments and Associated Attachments on the Staff's Analysis of Proposed Modifications
Center on Race, Poverty & the Environments Comments and Associated Attachments on the Staff's Analysis of Proposed Modifications
36 page(s)
 CEC/Docket UnitCenter on Race, Poverty & The Environment/I.Brostrom
6860111/20/2012Staff Analysis- Petition to Amend
Staff Analysis- Petition to Amend
20 page(s)
 Interested PartiesCEC/C.Remy-Obad
6827210/30/2012Avenal Power Center LLC's Letter Request to Defer a Construction Deadline Extension Amendment
Avenal Power Center LLC's Letter Request to Defer a Construction Deadline Extension Amendment
1 page(s)
 CEC/C.Remy-ObadDowney Brand LLP/J.Luckhardt
651785/11/2012Corrected Notice of Receipt
Corrected Notice of Receipt
3 page(s)
 CEC/Docket unitCEC/J.Walter
640763/9/2012Notice of Receipt-Petition to Amend the Energy Commission Decision
Notice of Receipt-Petition to Amend the Energy Commission Decision
3 page(s)
 CEC/Dockets UnitCEC/C.Marxen
639653/5/2012Petition for Post Certification Amendment to Extend the Construction Deadline
Petition for Post Certification Amendment to Extend the Construction Deadline
29 page(s)
 CEC/ J. WalterDowney Brand/ L. Navarrot
638802/29/2012Petition for Post Certification Amendment to Extend the Construction Deadline
Petition for Post Certification Amendment to Extend the Construction Deadline
21 page(s)
 CEC/Dockets UnitDowney Brand/L.Navarrot
607335/24/2011Notice of Receipt Petition to Amend the Energy Commission Decision for the Avenal Energy Project
Notice of Receipt Petition to Amend the Energy Commission Decision for the Avenal Energy Project
3 page(s)
 CEC/Dockets UnitCEC/C.Marxen
606645/17/2011Avenal Power Center, LLC's Petition for Post Certification Amendment to Allow Construction and Operation of the Avenal Energy Project as Minor Source
Avenal Power Center, LLC's Petition for Post Certification Amendment to Allow Construction and Operation of the Avenal Energy Project as Minor Source
287 page(s)
 CEC/ Dokcet UnitDowney Brand LLP
606195/11/2011Avenal's Petition for Post Certification Amendmentto Allow Construction and Operation of the Avenal Energy Project as a Minor Source
Avenal's Petition for Post Certification Amendmentto Allow Construction and Operation of the Avenal Energy Project as a Minor Source
287 page(s)
 CEC/ Docket UnitDowney Brand
580398/13/2010USFWS Letter Regarding Biological Opinion
USFWS Letter Regarding Biological Opinion
39 page(s)
 US Environmental Protection Agency/G. RiosUS Fish & Wildlife Service/S. Moore
503142/27/2009MOU-Between CEC and Aims Corporation for Design Review, Plan Check and Construction Inspection
MOU-Between CEC and Aims Corporation for Design Review, Plan Check and Construction Inspection
6 page(s)
 CEC/ Docket UnitCEC/ T. O'Brien/ AIMS/ D. Wimberly