Docket Log

Docket: 07-SPPE-01
Project Title: Chevron Power Plant Replacement Project
Generated On: 12/26/2024 4:44:49 PM

Include:     
TN #Docketed DateDocument TitleExhibit #ToFrom
4850310/10/2008 Order Terminating Proceedings

3 page(s)
 CEC/ Docket UnitCEC/ J. Pfannenstiel
481069/22/2008 Request for Withdrawal Application for Small Power Plant Exemption

3 page(s)
 CEC/ M. JonesChevron/ P. Miller
480459/17/2008 Committee Order Terminating Proceedings

3 page(s)
 CEC/ R. AvalosCEC/ J. Byron
470297/14/2008 Chevron Richmond Power Plant Replacement Project Status Report

4 page(s)
 CEC / Docket UnitCH2MHill / J. Putrich
463965/14/2008 Chevron Richmond Power Plant Replacement Project Status Report

4 page(s)
 CEC / Docket UnitCH2MHill / D. Stein, J. Salamy
458144/1/2008 Notice of Continued Special Meeting and Special Meeting Agenda from the City Planning Commission

2 page(s)
 CEC/ Docket UnitCity of Richmond
454422/22/2008 Errata to CIty of Richmond Final EIR, POS attached

5 page(s)
 POS ListCEC/ M. Dyas
446411/18/2008 Change of Contact for Communities for a Better Environment

3 page(s)
 CEC / Docket UnitCFABE / A. Bloch
442841/14/2008 Chevron Richmond Power Plant Replacement Project Status Report

4 page(s)
 CEC/ Docket UnitCH2MHILL/ D. Stein
439111/2/2008 Comments from Attorney General RE: Chevron Energy and Hydrogen Renewal Project

17 page(s)
 COR / L. ThompsonAG / E. Brown
4336811/15/2007 Committee Order Granting Motion for Stay or Suspension, POS attached

3 page(s)
 POSCEC/ J. Byron/ A. Rosenfeld
4303410/26/2007 Applicant's Motion for Stay of Suspension

7 page(s)
 CEC/M. DyasA&K/E. Kahl/N. Sheriff
4291910/19/2007 Contra Costa Building and Construction Trades Council Data Requests - Set Two

9 page(s)
 CEC / Docket UnitAdams Broadwell Joseph & Cardoza / S. Peesapati
4290310/18/2007 Communities for a better environment Data Requests - Set One

24 page(s)
 CEC / Dockets UnitCBE / A. Bloch
4286510/17/2007 CBE Data Requests - Set One

24 page(s)
 CEC / Dockets UnitCBE / A. Torres
4286410/16/2007 Chevron Data Requests (Set 2) 84-94

9 page(s)
 SPPE Permitting Manager / G. CarrCEC / M. Dyas
4275410/11/2007 Committee Order Granting Petition to Intervene

4 page(s)
 CEC / Docket UnitCEC / J. Byron / A. Rosenfeld
4274810/11/2007 Data Response to Data Request 37 and Additional Workshop Query

6 page(s)
 CEC / M. DyaasAlcantar & Kahl, LLP / E. Kahl / N. Sheriff
4274610/11/2007 Objection to Contra Costa Building and Construction Trades Council Data Requests - Set One

5 page(s)
 CEC / Docket UnitAlcantar & Kahl, LLP / N. Sheriff
425389/27/2007 Public Comment Letter from Ruth Gilmore With Attachment

18 page(s)
 City of Richmond/L. ThompsonAttorney General/J. Jefferson/E. Brown, Jr.
425279/26/2007 Petition to Intervene by CBE

5 page(s)
 CEC / Docket OfficeCommunities for A Better Environment / A. Bloch Staff Attorney
425199/26/2007 Data Response, Set 1B Chevron Power Plant Replacement Project (07-SPPE-1)

72 page(s)
 CEC/Mary DyasCH2M Hill/D. Stein
425009/25/2007 Contra Costa Building and Construction Trades Council Data Requests-Set One

11 page(s)
 CEC / Docket UnitAdams Broadwell Joseph & Cardozo / S. Peesapati
422979/13/2007 Notice of Data Response & Issues Resolution Staff Workshop for the Cevron Power Plant Replacement Project (07-SPPE-1)

6 page(s)
 CEC / Docket UnitCEC / T. O'Brien
422718/24/2007 Committee Order Granting CCBCTC Petition to Intervene

9 page(s)
 CEC / Docket UnitChevron Richmond SPPE Committee / J. Byron / A. Rosenfeld
422449/11/2007 Committee Scheduling Order, POS attached

4 page(s)
 POS ListCEC/ J. Byron/ A. Rosenfeld
422419/10/2007 Data Response, Set 1A; Data Response CUL-31; Data Response GEO-35 (COGEN 3000); Data Response GEO-35 (Hydrogen); POS attached

305 page(s)
 CEC/ M. Dyas/ POSCH2M HILL/ S. Madams for D. Stein
421228/29/2007 Letters to Native American Community re: Interest in the Proposed Contruction and Operation of a Power Plant at the Chevron USA Richmond Refinery

7 page(s)
 J. Kehl/ K. Perez/ M. Zimmer/ I. Zwierlein/ A. Sayers/ A. Galvan/R. GariCEC/ P. Richins
420438/24/2007 Committee Order Granting CCBCTC Petition to Intervene

9 page(s)
 CEC / Docket UnitChevron Richmond SPPE Committee / J. Byron / A. Rosenfeld
420408/24/2007 Chevron U.S.A. Proposed Schedule for Exemption Process

4 page(s)
 CEC / Docket UnitAlcantar & Kahl LLP / E. Kahl / N. Sheriff
420208/23/2007 Cheveron USA Inc. Proposed Schedule for Exemption Process

4 page(s)
 CECCounsil to Cheveron U.S.A. Inc. / N. Kahl
420028/23/2007 Cheveron PPRP - Issue Identification Report

9 page(s)
 CEC / CommissionersCEC / M. Dyas
419348/16/2007 Letter from staff to NAHC regarding notifying Native American Communities in Contra Costa County of proposed Chevron project.

1 page(s)
 CNAHC/ D. SingletonCEC/ B. Bastian
419068/8/2007 Chevron PPRP Data Requests 1 to 83

35 page(s)
 SPPE Permitting Managaer / G. CarrCEC / M. Dyas
418678/10/2007 Notice of Public Informational Hearing and Site Visit

8 page(s)
 CEC / Docket UnitCEC / J. Byron / A. Rosenfeld
418498/8/2007 Data Request and Pre-Filing Conversations

2 page(s)
 CECCEC / M. Dyas
418468/8/2007 Memorandum: Hearing Office Assignment

1 page(s)
 CEC/ CommissionersCEC/ Chairman Pfannestiel
418048/6/2007 Commision Appointment of Committee re: Application for Small Power Plant Exemption for Chevron Richmond

1 page(s)
 CECCEC/ J. Boyd
416507/25/2007 Cheveron Engery and Hydrogen Renewel Project Draft EIR Volume 1 Volume 2

856 page(s)
 CEC/ M. DyasCity of Richmond
416497/25/2007 Comments of Chevron Renewal Project and Draft EIR from Attorney General

14 page(s)
 City of Richmond/ L. ThompsonDepartment of Justice/J. Jefferson
414497/10/2007 AGenda Item for hte August 1, 2007 Business Meeting-Assignment of a Siting Committee

1 page(s)
 CEC/B.B. BlevinsCEC/T. O'Brien/R. Johnson
414057/5/2007 Updated Petition to Intervene by CCBCTC.

7 page(s)
 CEC/ Dockets UnitAdams Broadwell Joseph & Cardozo/ S. Peesapati/ B. Heeley
413847/3/2007 Notice of Receipt - Application for SPPE.

4 page(s)
 The PublicCEC/ E. Allen for R. Johnson
413837/3/2007 Request for Agency Participation in the Review of the Chevron's Application for a SPPE.

3 page(s)
 Agency Distribution ListCEC/ E. Allen for R. Johnson
413827/3/2007 Document Handling for the Chevron PPRP Application for a SPPE.

4 page(s)
 LibrarianCEC/ E. Allen for R. Johnson
413477/2/2007 Petition to Intervene by CCBCTC

5 page(s)
 CEC/Docket UnitContra Costa Building & Construction Trades Council/M. Joseph
411466/22/2007 Application for Small Power Plant Exemption- Appendix 8.5-A Detailed Noise Monitoring Data

1 page(s)
 CEC/ B. BlevinsChevron/ T. Lizarraga
411446/22/2007 Application for Small Power Plant Exemption- Air Dispersion Modeling Files (Sec. 8.1 AQ)

1 page(s)
 CEC/ B. BlevinsChevron/ T. Lizarraga
411436/22/2007 Application for Small Power Plant Exemption- HARP Modeling Files for Section 8.6: Public Health

1 page(s)
 CEC/ B. BlevinsChevron/ T. Lizarraga
411426/22/2007 Application for Small Power Plant Exemption-Chevron Richmond Power Plant Replacement Project

1 page(s)
 CEC/ B. BlevinsChevron/ T. Lizarraga
2196-09/12/2007 Informational Hearing and Site Visit

1 page(s)
  CEC