Docket Log

Docket: 07-AFC-01C
Project Title: Victorville 2 Hybrid Power Project - Compliance
Generated On: 5/27/2016 7:13:54 AM

TN #Docketed DateDocument TitleExhibit #ToFrom
2005059/17/2013Order Denying Petition to Reconsider

4 page(s)
  California Energy Commission
2004089/6/2013City of Victorville Comments to Landwehr's Petition for Reconsideration of Decision
Comment Letter from Victoville City Attorney
4 page(s)
 CEC Dockets UnitGreen, de Bortnowsky & Quintanilla, LLP
715497/11/2013Robert LandWehr Petition for Reconsideration of Decision to Extend the 5 Year Construction Deadline

10 page(s)
 CEC/Docket UnitPetitioner/ Robert Landwehr
714997/2/2013Order No. 13-0612-8 - Order Approving a Petition to Extend the Deadline for the Start of Construction

2 page(s)
 CEC/Docket UnitCEC/H.Kallemeyn
713626/24/2013Notice of Decision

1 page(s)
 California Resources AgencyCEC/M.Dyas
713376/17/2013R. Landwehr Request for Revocation of Certification and Associated Civil Penalties

11 page(s)
 CECM. DyasR. Landwehr
711305/21/2013Securities and Exchange Commission Complaint - City of Victorville and KND Holdings, Inc.

44 page(s)
 CEC/Docket UnitBob Landwehr
711305/21/2013Securities and Exchange Commission Complaint - City of Victorville and KND Holdings, Inc.

44 page(s)
 CEC/Docket UnitBob Landwehr
710535/31/2013Response to Demand Letter sent by Mr. Landwehr

1 page(s)
 City Council of the City of VictorvilleVictorville City Attorney/A. de Bortnowsky
709515/22/2013Robert Landwehr's Request to Post-Pone Hearing to Extend the 5-Year Construction Deadline for the Victorville 2 Power Plant Project

12 page(s)
 CEC/M.DyasPublic/R.Landwehr
706305/6/2013CEC Staff's Analysis and Recommendation

6 page(s)
 CEC/Docket UnitCEC/K.Bell
703774/17/2013Notice of Receipt - Petition to Extend Deadline for Commencement of Construction

3 page(s)
 CEC/Docket UnitCEC/C.Marxen
701914/2/2013City of Victorville's Letter of Clarification re Petition to Extend the Construction Deadline

1 page(s)
 CEC/Docket UnitCity of Victorville/J.Davidson
701863/28/2013City of Victorville's Petition to Extend the Construction Deadline

10 page(s)
 CEC/Docket UnitCity of Victorville/D.Robertson
532909/21/2009Filing of Notice of Decision in Compliance

1 page(s)
 California Resource AgencyCEC/ M. Dyas
532199/15/2009Order Approving a Petition to Amend

4 page(s)
 CEC/ Docket UnitCEC/ K. Douglas
527138/3/2009BIO-11 Amendment Staff Analysis

6 page(s)
 Interested PartiesCEC/ M. Dyas
526798/3/2009Public Comments-Petition to Amend BIO-11

1 page(s)
 CEC/ M. DyasPublic/ Farris & Cynthia Bruce
523047/6/2009Public Comments to BIO-11 Amendment

1 page(s)
 CEC/ M. DyasPublic/ F. Bruce
521466/24/2009Notice of Receipt -Petition to Amend the CEC Decision

3 page(s)
 CEC/ Docket UnitCEC/ E. Allen
517646/1/2009Petition to Amend Condition of Certification BIO-11

7 page(s)
 CEC/ M. DyasLatham&Watkins/ S. Torgerson
4899110/3/2008Request to Conduct Waste and Geotechnical Sampling on Project Site

2 page(s)
 LATHAM & WATKINS/ M. CarrollCEC/ E. Allen
4887911/4/2008CEC Response to Cultral Resources Monitoring & Mitigation Plan Application for Confidentiality

2 page(s)
 SWCA/ J. BrownCEC/ M. Jones
4857310/14/2008Letter Re Permission to Enter West Mojave Desert Ecological Reserve

5 page(s)
 City of Victorville/ J. RobertsBruce Kinney
4849110/8/2008Application for Confidential Designation - Cultural Resources Mitigation and Monitoring Plan (CRMMP)

109 page(s)
 CEC/M. JonesSWCA/J. Brown