TN #Docketed DateDocument TitleExhibit #ToFrom
220438/21/2001121 Day Permit Application
121 Day Permit Application
1 page(s)
 Electricity Provider Inc./Wilburn/docketsAntelope Valley Air Polluton Control District/Heas
216707/24/2001Withdrawal of Application from the 21-day Permitting Process
Withdrawal of Application from the 21-day Permitting Process
1 page(s)
 CEC/Moore/docketsElectricity Provider Inc./Wilburn
216687/23/2001Requesting a suspension of the 21-Day permitting process.
Requesting a suspension of the 21-Day permitting process.
1 page(s)
 CEC/Moore/docketsElectricity Provider Inc./Wilburn
215337/17/2001Comments on proposed permit for Lancaster facility #1
Comments on proposed permit for Lancaster facility #1
3 page(s)
 CEC/Glaviano/docketNrdc/Masters
215407/17/2001Opposes the approval of the Certification, on the grounds that the facility cannot obtain a legal Authority to Construct permit from the Antelope Valley Air Pollution Control District
Opposes the approval of the Certification, on the grounds that the facility cannot obtain a legal Authority to Construct permit from the Antelope Valley Air Pollution Control District
2 page(s)
 CEC/Moore/docketPlanning And Conservation League/Spelliscey
214417/16/2001Special Meeting
Special Meeting
2 page(s)
 CEC/DocketCEC Cec
214077/10/2001Copies of recent correspondence with the State Water Board
Copies of recent correspondence with the State Water Board
9 page(s)
 CEC/Eller/docketElectricity Provider Inc./Wilburn
214117/10/2001Copies of recent correspondence with SCE's 12 point request
Copies of recent correspondence with SCE's 12 point request
18 page(s)
 CEC/Eller/docketElectricity Provider Inc./Wilburn
214147/10/2001Notice of Date Change-Adoption Hearing
Notice of Date Change-Adoption Hearing
1 page(s)
 CEC/DocketCEC/Glaviano
214137/3/2001Requests an additional ten-day extension to the 21-day emergency permitting process from July 5th, 2001 to Jul 15th, 2001.
Requests an additional ten-day extension to the 21-day emergency permitting process from July 5th, 2001 to Jul 15th, 2001.
1 page(s)
 CEC/Eller/docketElectricity Provider Inc./Wilburn
210676/22/2001Executive Summary
Executive Summary
93 page(s)
 CEC/DocketCEC Cec
214596/21/2001Requesting a ten-day extension to the CEC 21-day review process
Requesting a ten-day extension to the CEC 21-day review process
1 page(s)
 CEC/Eller/docketElectricity Provider Inc./Wilburn
20246/20/2001Before the Energy Resources Conservatio

102 page(s)
   
210606/19/2001Review of proposed Lancaster Energy Facility consistent with Executive Orders D-28-01 and D-26-01.
Review of proposed Lancaster Energy Facility consistent with Executive Orders D-28-01 and D-26-01.
6 page(s)
 CEC/Scofield/keese/docketDept. Fish And Games/Raysbrook
208656/15/2001Comments from the Hazardous Waste Management and the Site Mitigation Program of DTSC.
Comments from the Hazardous Waste Management and the Site Mitigation Program of DTSC.
4 page(s)
 CEC/Eller/docketDepartment Of Toxic Substances Control/Lowry
208666/15/2001Analysis based on the submitted application.
Analysis based on the submitted application.
4 page(s)
 CEC/Eller/docketState Water Resources Control Board/Innes
208676/15/2001Comments pursuant to the Department's role as a trustee for fish and wildlife resources.
Comments pursuant to the Department's role as a trustee for fish and wildlife resources.
6 page(s)
 CEC/Eller, Scofied/docketsDepartment Of Fish And Game/Raysbrook
208836/15/2001Application for Authority to Construct Lancaster #1 Project
Application for Authority to Construct Lancaster #1 Project
430 page(s)
 CEC/Eller/docketEpi/Wilburn
208436/14/2001Fax-Letter in Support
Fax-Letter in Support
1 page(s)
 CEC/Keese/docketAssembly California Legislature/Rummer
208426/13/2001Notice of Time Change Commission Adoption Hearing
Notice of Time Change Commission Adoption Hearing
1 page(s)
 CEC/DocketCEC/Glaviano
208456/12/2001Sign in Sheet for June 11th Site Visit, Informational and Adoption Hearing
Sign in Sheet for June 11th Site Visit, Informational and Adoption Hearing
6 page(s)
 CEC/DocketCEC Cec
208446/5/2001Notice of Site Visit, Informational Hearing and Adoption Hearing
Notice of Site Visit, Informational Hearing and Adoption Hearing
28 page(s)
 CEC/DocketCEC/Glaviano
208376/4/2001Notice of Receipt of the Emergency Permitting Proposal
Notice of Receipt of the Emergency Permitting Proposal
3 page(s)
 CEC/DocketCEC/Therkelsen
208386/4/2001Document Handling
Document Handling
5 page(s)
 LibrarianCEC/Therkelsen
208396/4/2001Request for Agency Participation in the Review of Electricity Provider
Request for Agency Participation in the Review of Electricity Provider
3 page(s)
 Agency Distribution ListCEC/Therkelsen
208416/4/2001Data Adequacy for the Electricity Provider Lancaster Energy Facility
Data Adequacy for the Electricity Provider Lancaster Energy Facility
9 page(s)
 CEC/Commissioners/docketCEC/Larson