264201 | 6/12/2025 |
Enterprise Emergency Peaker Project_Courtesy Notice of Change of Upstream Ownership Courtesy Notice of Change of Upstream Ownership for the CalPeak Power-
Enterprise Project; Dockets 0l-EP-10, 01-EP-l0C 2 page(s)
| | Executive Director Drew Bohan | Latham & Watkins LLP |
262807 | 3/25/2025 |
Supplemental Petition for Post-Certification Amendment - Confidential Cultural Resources Technical Report Volume 3 Includes Volume 3 of the revised Cultural Resources Technical Report which provides South Coastal information center records search results as part of a continued Appendix A (Confidential). 345 page(s)
| | CEC/Drew Bohan | Rincon Consultants, Inc. |
262806 | 3/25/2025 |
Supplemental Petition for Post-Certification Amendment - Confidential Cultural Resources Technical Report Volume 2 Includes Volume 2 of the revised Cultural Resources Technical Report which provides South Coastal information center records search results as part of a continued Appendix A (Confidential).
267 page(s)
| | CEC/Drew Bohan | Rincon Consultants, Inc. |
262805 | 3/25/2025 |
Supplemental Petition for Post-Certification Amendment - Confidential Cultural Resources Technical Report Volume 1 Includes Volume 1 of the revised Cultural Resources Technical Report which addresses cultural resources within the modified layout of the Enterprise BESS Project. Additionally, South Coastal information center records search results are provided as Appendix A (Confidential). 419 page(s)
| | CEC/Drew Bohan | Rincon Consultants, Inc. |
262804 | 3/25/2025 |
Supplemental Petition for Post-Certification Amendment - Confidential Cultural Resources Technical Report Volume 4 Includes Volume 4 of the revised Cultural Resources Technical Report which provides the remaining documents for Appendix A (Confidential). In addition, Volume 4 includes the Native American Heritage Commission Sacred Land Files Search Results as part of Appendix B, and the California Department of Parks and Recreation 523 Series Forms as part of Appendix C (the final Appendix to the Cultural Resources Technical Report). 238 page(s)
| | CEC/Drew Bohan | Rincon Consultants, Inc. |
262803 | 4/25/2025 |
CEC Response Letter Enterprise Emergency Energy - Application for Confidentiality
Cultural Resources 2 page(s)
| | Mark Strother, Project Archaeologist - Rincon | California Energy Commission |
262348 | 3/25/2025 |
Application for Confidential Designation Enterprise BESS Project Appendix E Cultural Resources Technical Report Includes an application for Confidential Designation - Appendix A of the Enterprise BESS Project's Cultural Resources Technical Report. 2 page(s)
| | CEC/Drew Bohan | Rincon Consultants, Inc. |
262239 | 3/18/2025 |
Supplemental Petition for Post-Certification Amendment, Appendices F through H Provides the Applicant's Supplemental Petition submittal for Post-certification Amendment Appendices F through H, which include the Noise and Vibration Study provided as Appendix F, the Vehicle Miles Traveled (VMT) Technical Memorandum provided as Appendix G, and the Fire Safety discussion provided as Appendix H.
Noise and Vibration, Traffic and Transportation, Worker Safety and Fire Protection 77 page(s)
| | CEC/Docket Unit | Rincon Consultants, Inc. |
262238 | 3/18/2025 |
Supplemental Petition for Post-Certification Amendment, Appendices D and E Provides the Applicant's Supplemental Petition submittal for Post-certification Amendment Appendices D and E, which include the Biological Resources Technical Report provided as Appendix D and the Cultural Resources Technical Report (Public Version) provided as Appendix E. Biological Resources, Cultural Resources 224 page(s)
| | CEC/Docket Unit | Rincon Consultants, Inc. |
262237 | 3/18/2025 |
Supplemental Petition for Post-Certification Amendment, Figure 1, Figure 2, Exhibit 1, and Appendices A through C Provides the Applicant's Supplemental Petition submittal for Post-Certification Amendment. Preliminary draft submittal includes an introduction, description of proposed changes, necessity of proposed change, new information or change in circumstances that necessitated the change, analysis of the effects that the proposed change will have on the environment and mitigation measures proposed, modifications impacts on LORS compliance, potential effects on public, property owners, modifications impact on the public and nearby property owners, applicable CEQA exemptions, and conclusions. In addition, this submittal includes a regional location map (Figure 1), Site Layout (Figure 2), photo simulations of Enterprise BESS Project (Exhibit 1), Analysis of the Potential Effects of the Proposed Modification and Proposed Avoidance and Mitigation Measures provided as Appendix A, Enterprise BESS Only Conditions of Certification provided as Appendix B, and the Air Quality and Greenhouse Gas Study provided as Appendix C. Air Quality, Facility Design, Compliance, Introduction 207 page(s)
| | CEC/Docket Unit | Rincon Consultants, Inc. |
257584 | 7/3/2024 |
Data Request for Enterprise Emergency Peaker Project Data Request for Enterprise Emergency Peaker Project Compliance 2 page(s)
| | CEC/Docket Unit | California Energy Commission |
256058 | 4/30/2024 |
Notice of Receipt Petition for Post Certification Change
Enterprise Emergency Peaker Project Compliance 3 page(s)
| | CEC/Docket Unit | California Energy Commission |
255920 | 3/14/2024 |
Enterprise Emergency Peaker Project Confidential Appendix A - South Coastal Information Center Records Search Results - Part 3
401 page(s)
| | CEC/Drew Bohan | Ellison Schneider Harris & Donlan LLP |
255919 | 3/14/2024 |
Enterprise Emergency Peaker Project Confidential Appendix A - South Coastal Information Center Records Search Results - Part 2
404 page(s)
| | CEC/Drew Bohan | Ellison Schneider Harris & Donlan LLP |
255918 | 3/14/2024 |
Enterprise Emergency Peaker Project Confidential Appendix A - South Coastal Information Center Records Search Results - Part 1
356 page(s)
| | CEC/Drew Bohan | Ellison Schneider Harris & Donlan LLP |
255903 | 4/24/2024 |
CEC's Response Letter to Calpeak Power-Enterprise, LLC’s Application for Confidential Designation, dated 3-14-2024
2 page(s)
| | Ellison Schneider Harris & Donlan, LLP/Samantha Neumyer | California Energy Commission |
255290 | 3/26/2024 |
Petition for Post-Certification Amendment - Part 1 ***This Document Supersedes TN 255070-1*** 194 page(s)
| | CEC/Docket Unit | Ellison Schneider Harris & Donlan LLP |
255072 | 3/14/2024 |
Application for Confidential Designation for PTA Cultural Resources Appendix
3 page(s)
| | CEC/Drew Bohan | Ellison Schneider Harris & Donlan LLP |
255070-1 | 3/14/2024 |
Petition for Post-Certification Amendment - Part 1 ***This Document Has Been Replaced By TN 255290*** 194 page(s)
| | CEC/Docket unit | Ellison Schneider Harris & Donlan LLP |
255070-2 | 3/14/2024 |
Petition for Post-Certification Amendment - Part 2
243 page(s)
| | CEC/Docket unit | Ellison Schneider Harris & Donlan LLP |
233363 | 6/8/2020 |
Energy Commission Adoption Order Order 4 page(s)
| | CEC/Docket Unit | California Energy Commission |
229112 | 7/29/2019 |
Enterprise Emergency Peaker Project Notice of Staff Approval Operational Control Change Notice of Staff Approval of Change in Operational Control of Enterprise Emergency Peaker Project Compliance 2 page(s)
| | CEC/Dockets | California Energy Commission |
228953 | 7/12/2019 |
Enterprise Emergency Peaker Project Notice of Receipt Notice of Receipt for a Petition to Change Operational Control of the Enterprise Emergency Peaker Project. Compliance 2 page(s)
| | CEC/Docket Unit | California Energy Commission |
228884 | 7/2/2019 |
CalPeak Power Enterprise LLC Notice of Project Name Change and Petition to Transfer Operational Control
2 page(s)
| | CEC/Dockets | Ellison Schneider Harris & Donlan LLP |
227464 | 4/2/2019 |
Courtesy Notice of Acquisition Enterprise Courtesy notice of upstream change in ownership of CalPeak Power-Enterprise, LLC Compliance 2 page(s)
| | Drew Bohan, Executive Director | King & Spalding |
227321 | 3/12/2019 |
CalPeak Power Border Project Operational Control Change - Notice of Approval Notice of Staff Approval - Petition for Change of Operational Control Compliance 2 page(s)
| | CEC/Docket Unit | California Energy Commission |
227177 | 2/26/2019 |
Notice of Receipt - Petition for Change of Operational Control for the Calpeak Enterprise Project 2 page(s)
| | CEC/Docket Unit | California Energy Commission |
226514 | 2/13/2019 |
CalPeak_Power_Enterprise_Operational_Control_Change_Petition CalPeak_Power_Enterprise_Operational_Control_Change_Petition Compliance 7 page(s)
| | | CalPeak Power – Enterprise, LLC |
225694 | 10/31/2018 |
Compliance Docketing Policy
1 page(s)
| | Plant Manager | California Energy Commission |
225677 | 10/31/2018 |
Compliance Docketing Policy
3 page(s)
| | CEC/Dockets | California Energy Commission |
64745 | 4/13/2012 |
Order Affirming Extension of Operational Licenses
4 page(s)
| | CEC/ Docket Unit | CEC/ H. Kallemeyn |
64737 | 4/11/2012 |
Notice of Decision
4 page(s)
| | California Resource Agency | CEC/ R. Johnson |
64714 | 4/11/2012 |
Notice of Exemption
1 page(s)
| | Office of Planning and Research | CEC/R.Johnson |
63744 | 2/23/2012 |
Emergency Peaker Notice
3 page(s)
| | CEC/Dockets Unit | CEC/C.Hoffman |
63743 | 2/23/2012 |
Emergency Peaker Report
8 page(s)
| | CEC/Dockets Unit | CEC/C.Hoffman |
22775 | 10/3/2001 |
Withdrawal of Petition to Extend Deadline for On-Line Date
1 page(s)
| | CEC/Huntley/dockets | Calpeak Power/Sampson |
22774 | 9/25/2001 |
Requesting an amendment to the certification for Calpeak Power-Enterprise LLC Project to extend the onlind date for the project
11 page(s)
| | CEC/Johnson/dockets | Calpeak Power/Sampson |