21373 | 6/3/2001 |
Letter regarding Energy Commission's Responsibility
1 page(s)
| | Honorable Jim Costa/Dockets | CEC/Larson |
21372 | 3/6/2001 |
Letter regarding Energy Commission's Responsibilty
2 page(s)
| | Honorable Dean Florez/Dockets | CEC/Larson |
20247 | 5/17/2001 |
Public Adviser's Status Report 1st Trimester-2001
3 page(s)
| | Docket | CEC/Mendonca |
20058 | 5/4/2001 |
Letter of notification that GWF Power Systems Co. intends to proceed with the HEPP 95 MW Peaker being permitted under the Commission's expedited 21-day process.
1 page(s)
| | Adams, Broadwell, Joseph & Cordoza/Joseph/dockets | Grattan & Galati/Grattan |
19971 | 4/27/2001 |
Hanford Energy Park Project's Notification if Withdrawal POS
3 page(s)
| | CEC/Dockets | Grattan & Galati/Wheeler |
19931 | 4/26/2001 |
Hanford Energy Park Project's Notification of Withdrawal POS
4 page(s)
| | Docket | Gwf Power Systems/Wheeler |
19840 | 4/20/2001 |
Notice of Determination
3 page(s)
| | Docket | CEC/Caswell |
19832 | 4/20/2001 |
Document Details Report State Clearinghouse Data Base
4 page(s)
| | CEC/Caswell/docket | State Clearinghouse/Roberts |
19800 | 4/18/2001 |
Commission Decision POS
5 page(s)
| | Docket | CEC/Keese, Pernell, Moore, Rosenfield |
19799 | 4/18/2001 |
Mitigated Negative Declaration POS
5 page(s)
| | Docket | CEC/Keese, Pernell, Moore, Rosenfield |
19653 | 1/12/2001 |
Orig and 12 copies of Hanford Energy Project's Request for Extension of the Public Comment Period for the Draft Initial Study POS
1 page(s)
| | CEC/Jacobs/docket | Gwp Power Systems Co/Grattan |
19652 | 4/11/2001 |
Response to 3/20/2001 Comments from the Native American Heritage Commission
3 page(s)
| | Nahm/Wood/docket | CEC/Torres |
19470 | 4/2/2001 |
Commission Hearing on Proposed Decision (Reminder Notice) - POS
3 page(s)
| | Dockets | CEC/Shean |
19469 | 4/3/2001 |
Initial Study
2 page(s)
| | CEC/Torres/dockets | Native American Heritage Commission/Wood |
19315 | 3/22/2001 |
Letter acknowledge that the State Clearinghouse has received environmental document for state review
1 page(s)
| | CEC/Caswell/dockets | Governor's Office Of Planning And Research |
19237 | 3/6/2001 |
Energy's Commissions Responsibility
2 page(s)
| | Kings Co. Board Of Super./Honorable Alene Taylor/d | CEC/Larson |
19215 | 3/16/2001 |
Revised Visible Plume Analysis
4 page(s)
| | Dockets | CEC/Edwards |
19201 | 3/8/2001 |
Notice of Completion & Environmental Document Transmittal
2 page(s)
| | Dockets | |
19153 | 3/6/2001 |
CEC's Responsibility
2 page(s)
| | City Of Hanford/Mayor Lakritz/dockets | CEC/Larson |
19098 | 3/9/2001 |
Notice of Completion & Environmental Document Transmittal
1 page(s)
| | Dockets | |
19093 | 3/9/2001 |
Notice of Intent to Adopt a Mitigated Negative Declaration - POS
1 page(s)
| | CEC/Dockets | Hanfor Energy Park |
19059 | 3/7/2001 |
Applicant's Comments on the Final Initial Study & Proposed Negative Declaration
9 page(s)
| | CEC/Dockets | Grattan & Galati/Carey |
19040 | 3/9/2001 |
Notice of Intent and Staff's Revised Proposed Mitigated Negative Declaration pertaining to the February 2001 Intial Study
4 page(s)
| | Agency Library Distribution/Dockets | CEC/Caswell |
18854 | 2/28/2001 |
Notice of Availability of Proposed Decision - POS
3 page(s)
| | Dockets | CEC/Moore/rosenfeld |
18853 | 2/26/2001 |
Notice of Committee Workshop & Commission Hearing on Proposed Decision - POS
3 page(s)
| | Dockets | CEC/Keese |
18820 | 2/23/2001 |
Request for Agency Comments on the Initial Study
2 page(s)
| | Agency Distribution List/Dockets | CEC/Therkelsen |
18819 | 2/23/2001 |
Notice of Availability Initial Study
2 page(s)
| | CEC/Dockets | CEC/Therkelsen |
18818 | 2/23/2001 |
Document Handling
3 page(s)
| | Librarian/Cec/dockets | CEC/Therkelsen |
18809 | 2/23/2001 |
Proposed Decision - POS
3 page(s)
| | Dockets | CEC/Moore/rosenfeld |
18768 | 2/16/2001 |
Initial Study - POS
274 page(s)
| | CEC/Dockets | CEC Cec |
18597 | 1/16/2001 |
Sign-in Sheet RE: Draft Initial Study Workshop
2 page(s)
| | CEC/Docket | CEC/Staff |
18244 | 2/1/2001 |
Comments on Draft Initial Study - POS
14 page(s)
| | CEC/Dockets | Urs/Stein |
18093 | 1/24/2001 |
Draft Initial Study Workshop Summary - POS
12 page(s)
| | CEC/Dockets | Hanford Energy Park Project |
18081 | 1/23/2001 |
Comments on Draft Initital Study
14 page(s)
| | CEC/Caswell | Urs Corporation/Stein |
18035 | 1/24/2001 |
Hard Copies of the Data Submitted (CEC1.doc; CEC1.dta; CEC.doc; CEC_LST.doc; LNAS68.asc; PSD.xls; PSD1.xls; REVISED.xls)
537 page(s)
| | CEC/Caswell | Saqs/Villavazo |
17928 | 1/11/2001 |
Comments on atmospheric conditions POS
10 page(s)
| | CEC/Dockets | City Of Hanford/Matton |
17916 | 1/3/2001 |
New Docket File - AB 970 Building Standards Update Rulemaking
1 page(s)
| | CEC/Buell/dockets | CEC/Baker |
17890 | 1/19/2001 |
SJVAPCD Modeling
8 page(s)
| | CEC/Docket | CEC/Caswell |
17888 | 1/12/2001 |
Public Adviser's Status Report 2000
41 page(s)
| | CEC/Docket | CEC/Pao |
17832 | 1/11/2001 |
HRGS Steam Plume Assessment - POS
4 page(s)
| | CEC/Knight | Aspen/Walters |
17813 | 1/12/2001 |
Hanford Energy Project's Request for Extension of the Public Comment Period for the Draft Initial Study - POS
3 page(s)
| | CEC/Dockets | Grattan & Galati/Grattan |
17799 | 1/12/2001 |
Air Quality Workshop - 1/22/01
1 page(s)
| | CEC/Dockets | CEC/Moore |
17791 | 1/9/2000 |
Well Survey and Interference assessment - POS
6 page(s)
| | Gwf Power Systems Co. Inc./Wheeler/cec/dockets | Kleinfelder/Warner/johnson |
17726 | 1/11/2001 |
Cooling Tower Plume Assessment
2 page(s)
| | CEC/Knight | Aspen Environmental Group/Walters |
17725 | 1/11/2001 |
HRSG Steam Plume Assessment
4 page(s)
| | CEC/Knight | Aspen Environmental Group/Walters |
17651 | 12/28/2000 |
Document Handling - Enclosed Draft Initial Study
3 page(s)
| | Librarian | CEC/Therkelsen |
17621 | 12/28/2000 |
Document Handling
3 page(s)
| | Librarian | CEC/Therkelsen |
17620 | 12/28/2000 |
Request for Agency Comments on the Draft Intitial Study
2 page(s)
| | Agency Distribution List | CEC/Therkelsen |
17610 | 12/21/2000 |
HRSG Steam Plume Assessment
7 page(s)
| | Dockets | Kanemoto |
17605 | 12/18/2000 |
Incompleteness Letter for Hanford Energy Park
4 page(s)
| | CEC/Golden | San Joaquin Valley Air Pollution Control Dist./Swa |
17603 | 12/28/2000 |
Draft Initial Study Workshop - 01/10/01 - Hanford - POS
4 page(s)
| | CEC/Dockets | CEC/Moore |
17602 | 12/28/2000 |
Notice of Availability Draft Initial Study
3 page(s)
| | CEC/Dockets | CEC/Therkelsen |
17557 | 12/22/2000 |
Draft Initial Study
225 page(s)
| | CEC/Dockets | CEC Cec |
17528 | 10/5/2000 |
Public Notice RE: Public Hearing
1 page(s)
| | CEC/Docket | The Hanford Sentinel |
17342 | 12/1/2000 |
Cooling Tower Orientation Revision and Revised SACTI Cooling Tower Plume Modeling
54 page(s)
| | CEC/Dockets | Gwf Hanford Energy Park |
17341 | 12/5/2000 |
Incompleteness letter for Hanford Energy Park
4 page(s)
| | CEC/Golden | San Joaquin Valley Air Pollution Control District/ |
17265 | 12/11/2000 |
Status Report #1 (EPF & EPD Project Schedule)
2 page(s)
| | CEC/Moore/rosenfeld | CEC/Caswell |
16206 | 10/16/2000 |
Hanford Energy Project's Tranmission Route Clarification (Attachment: Proof of Service)
4 page(s)
| | CEC/Docket | Grattan & Galati/Grattan |
15741 | 9/12/2000 |
Request to Review the Biological Resources Section of Application for Exemption to the CEC for the Hanford Energy Park Expansion Project (Attachment: Proof of Service)
3 page(s)
| | Us Dept. Of Interior/Jones | Gwf Power Systems/Wheeler |
15717 | 9/5/2000 |
Responses to Notice of Incomplete Application (Sent to San Joaquin Valley Unified APCD)
169 page(s)
| | CEC/Docket | Urs Corp. |
15639 | 9/1/2000 |
Photosimulations - Electronic Files - POS
3 page(s)
| | CEC/Buell | Urs/Stein |
15625 | 8/28/2000 |
Data Responses Set 2 (CEC Staff Data Request # 67) - CD
77 page(s)
| | CEC/Dockets | Urs/Stein |
15622 | 8/23/2000 |
Data Responses Set 2 (CEC Staff Data Requests # 18 - 91) - POS
290 page(s)
| | CEC/Dockets | Urs/Stein |
15529 | 8/16/2000 |
Order Instituting Electronic Filing Pilot Project
8 page(s)
| | CEC/Dockets | CEC/Moore/pernell |
15497 | 8/21/2000 |
Repeated Application for Confidential Designation: Cultural Resources-CEC Staff Data Response No. 35 & 36 - POS
10 page(s)
| | CEC/Larson | Urs/Stein |
15486 | 8/21/2000 |
Repeated Application for Confidential Designation: Cultural Resources (Attachment: Proof of Service)
3 page(s)
| | CEC/Larson | Urs Corp./Stein |
15463 | 8/17/2000 |
List of Property Owners Between 50 and 500 Feet of the Linear Facilities Associated with the GWF Hanford Energy Park (Attachment: Proof of Service)
23 page(s)
| | CEC/Docket | Urs/Stein |
15440 | 8/4/2000 |
Sign-in Sheet RE: Data Request and Response Workshop (August 3, 2000)
4 page(s)
| | CEC/Docket | CEC/Staff |
15439 | 8/4/2000 |
Sign-in Sheet RE: Informational Hearing (August 2, 2000)
5 page(s)
| | CEC/Docket | CEC/Staff |
15438 | 8/4/2000 |
Slide Presentation RE: Informational Hearing (August 2, 2000)
21 page(s)
| | CEC/Docket | CEC/Buell |
15437 | 8/1/2000 |
Letter of Support (Attached: Proof of Service)
3 page(s)
| | CEC/Buell | Kings Co. Economic Development Cop./Lehn |
15436 | 8/1/2000 |
Letter of Support (Attachment: Proof of Service)
3 page(s)
| | CEC/Buell | Hanford Chamber Of Commerce/Tucci |
15435 | 7/27/2000 |
Comments RE: Positive Relationship With G.W.F. Power System Project (Atachment: Proof of Service)
4 page(s)
| | CEC/Buell | Pat Davis |
15434 | 7/28/2000 |
Letter of Support (Attachment: Proof of Service)
3 page(s)
| | CEC/Buell | Environmental Oversight Committee/Ham |
15433 | 8/1/2000 |
Letter of Support (Attachment: Proof of Service)
3 page(s)
| | CEC/Buell | Judi Freitas |
15432 | 7/27/2000 |
Repeated Application for Confidential Designation: Paleontologic Resources - CEC Staff Data Response No. 4 (Attachment: Proof of Service)
3 page(s)
| | CEC/Larson | Urs/Stein |
15431 | 7/27/2000 |
Data Responses: Set 1 (CEC Stafff Data Requests Nos. 1-17) (Attachment: Proof of Service)
68 page(s)
| | CEC/Docket | Gwf Power Systems Co. Inc./Urs Corp./stein |
15430 | 7/28/2000 |
Letter of Support (Attached: Proof of Service)
3 page(s)
| | CEC/Buell | Jim Verboon |
15429 | 7/27/2000 |
Letter of Support (Attachment: Proof of Service)
3 page(s)
| | CEC/Buell | Driskell's Appliance & T.v./Jones |
15428 | 7/31/2000 |
Letter of Support of the Proposed Project. (Attachment: Proof of Service)
3 page(s)
| | CEC/Buell | Co. Of Kings/Board Of Supervisors/taylor |
15427 | 7/18/2000 |
Letter of Support
1 page(s)
| | CEC/Moore | Pirelli Tire Co./Micconi |
15414 | 8/15/2000 |
Payment of Deposit for the CEQA Related Work on the Hanford Energy Park.
1 page(s)
| | CEC/Baude | Gwf/Wheeler |
15413 | 8/4/2000 |
APPLICATION for Authority to Construct and Permit to Operate.
582 page(s)
| | CEC/Docket | Urs/Stein |
15275 | 7/20/2000 |
Data Request and Respose Workshop (Attachment: Map of Meeting Locatiion, Proof of Service)
4 page(s)
| | CEC/Docket | CEC/Moore |
15274 | 7/20/2000 |
Memorandum in Response to Letter Dated 13, 2000 Requesting Comments on on Potential Issues of Concern. (Attachment: Proof of Service)
3 page(s)
| | CEC/Buell | The Resources Agency/Ramirez |
15273 | 7/25/2000 |
Agreement with G.W.F Power Systems to Mitigitate their Anticipated Increase in Groundwater Use.
3 page(s)
| | CEC/Buell | Kcwd/Mills |
15259 | 7/28/2000 |
Letter of Support RE: Review Process
1 page(s)
| | Environmental Oversight Comm./Ham | CEC/Buell |
15222 | 7/26/2000 |
Staff Issue Identification Report (Attachment: Proof of Service)
13 page(s)
| | CEC/Moore/rosenfeld | CEC/Buell |
15221 | 7/26/2000 |
Hanford's Energy Project's Proposed Schedule (Attachment: Proof of Service)
4 page(s)
| | CEC/Nash | Grattan & Galati/Grattan |
15193 | 7/14/2000 |
Emergency Permitting Request for 95 MW Power Barge in San Francisco
11 page(s)
| | CEC/Therkelsen | Pg&e/Filippelli |
15159 | 7/19/2000 |
Data Requests Numbers 18 - 91 - POS
25 page(s)
| | Wheeler | CEC/Buell |
15147 | 7/20/2000 |
Order Granting Petition to Intervene - POS
6 page(s)
| | CEC/Docket | CEC/Moore |
15044 | 7/13/2000 |
Petition to Intervene by CURE - POS
7 page(s)
| | CEC/Dockets | Cure/Joseph/wolfe |
15036 | 6/30/2000 |
Project Description and Energy Commission's Facility Review Process
2 page(s)
| | Member Of The Assembly/Hon. Florez | CEC/Keese |
15034 | 6/30/2000 |
Project Description and Energy Commission's Facility Review Process
2 page(s)
| | Kings Co. Brd. Of Supervisors/Hon. Taylor | CEC/Keese |
15033 | 6/30/2000 |
Project Description and Commission's Facility Review Process
2 page(s)
| | Member Of The Senate/Hon. Costa | CEC/Keese |
15032 | 6/30/2000 |
Project Description and Review Process
2 page(s)
| | Hanford City Mayor/Hon. Lakritz | CEC/Keese |
14969 | 6/29/2000 |
Data Requests Number 1 throught 17 - POS
10 page(s)
| | D.wheeler | CEC/Buell |
14958 | 6/27/2000 |
Notice of Public Informational Hearing and Site Visit (August 2, 2000) (Attachment: Proof of Service)
5 page(s)
| | CEC/Docket | CEC/Moore/rosenfeld |
14928 | 6/19/2000 |
Request for Agency Participation in the Review of the Hanford Energy Park Application for a Small Power Plant Exemption
2 page(s)
| | Agency Distribution List | CEC/Therkelsen |
14927 | 6/19/2000 |
Notice of Receipt - Application For Small Power Plant Exemption
1 page(s)
| | CEC/Dockets | CEC/Therkelsen |
14923 | 6/19/2000 |
Report of Conversation - Hanford Generating and Efficiency
1 page(s)
| | CEC/Dockets | CEC/Steve Baker |
14914 | 6/26/2000 |
Report of Conversation with Gib Bosworth (General Electric Industrial & Power System Sales) RE: Hanford Generating Capacity and Efficiency
1 page(s)
| | CEC/Docket | CEC/Baker |
14898 | 6/19/2000 |
Public Participation in the Review of the Hanford Energy Park Project
2 page(s)
| | Members Of The Public | CEC/Therkelsen |
14870 | 6/13/2000 |
CEC's Letter in Response to Application for Confidentiality - Cultural and Paleontological Resources Technical Appendices
2 page(s)
| | URS/D. Stein | CEC/S. Larson |
14869 | 6/12/2000 |
Request to Loan a Copy of the Hanford Energy Park Project Application for Small Power Plant Exemption.
1 page(s)
| | Cure/Texier | CEC/Caswell |
14836 | 6/15/2000 |
Hearing Officer Assignment - Garret Shean to Assist the Committee in Conducting Proceedings on the Small Power Plant Exemption for the Hanford Energy Park Project
1 page(s)
| | CEC/Docket | CEC/Keese |
14715 | 5/31/2000 |
Application for Small Plant Exemption
0 page(s)
| | CEC/Larson | Gwf Power Systems/Nelsen |
14714 | 5/31/2000 |
Air Quality and Public Health Modeling Files - 6 CD's
6 page(s)
| | CEC/Larson | Urs/Stein |
14694 | 5/31/2000 |
Application for Confidential Designation Cultural Resources Technical Appendix C
1 page(s)
| | CEC/Larson | Urs/Stein |
14693 | 5/31/2000 |
Application for Confidential Designation - Paleontologic Resources Inventory/Impact Assessment Report
1 page(s)
| | CEC/Larson | Urs/Stein |
1486-0 | 3/26/2001 |
Committee Workshop
37 page(s)
| | | CEC |
1373-0 | 8/10/2000 |
Informational Hearing and Site Visit
59 page(s)
| | | CEC |