Docket Log

Docket: 00-AFC-13C
Project Title: AES Huntington Beach Generation Station Retool Project - Compliance
Generated On: 6/30/2016 5:07:32 AM

TN #Docketed DateDocument TitleExhibit #ToFrom
20693312/11/2015Presentation from Site Visit, Environmental Scoping Meeting and Informational Hearing
PowerPoint presentation of the Committee, Staff, and the Public Adviser from the December 8, 2015, Site Visit and Informational Hearing
43 page(s)
 CEC/Dockets UnitEnergy Commission Hearing Office
708995/20/2013CEC's Response to Application for Confidential Designation of Synchronous-Condensers

3 page(s)
 Stoel Rives/K.CastanosCEC/R.Oglesby
704284/19/2013Application for Confidential Designstion - Enclosure A, Information related to the Installation of Equipment at HBGS

4 page(s)
 CEC/R. OgleslbyStoel Rives/ K Castanos
6880812/7/2012Notice of Decision By The California Energy Commission, from Christine Stora, Energy Commission Staff1

1 page(s)
 CEC/ Docket UnitCEC Compliace/ C. Stora
6880212/7/2012Order Approving Petition to Convert Existing Units 3 and 4 to Synchronous Condensers

8 page(s)
 CEC/Docket UnitCEC/H.Kallemeyn
6829011/1/2012Department of Transportation Comment Letter Regarding Generating Stations, Units 3 and 4

2 page(s)
 CEC/C.StoraDepartment of Transportation/C.Herre
6816810/25/2012Staff Analysis of Proposed Modifications to Convert the Existing Units 3 and 4 to Synchronous Condensers

16 page(s)
 Interested PartiesCEC/C.Stora
6807310/24/2012Jane Luckhardt Email to Christine Stora Regarding 3 & 4 Conversion

1 page(s)
 CEC/C.StoraDowney Brand/J.Luckhardt
6807210/18/2012Stephen O'Kane's Email to CEC's Mary Dyas

3 page(s)
 CEC/M.DyasApplicant/AES/S.O'Kane
6799510/23/2012Downey Brand Jane Luckhardt email to C.Stora

1 page(s)
 CEC/C.StoraDowney Brand/J.Luckhardt
6799210/23/2012AES Stephen O'Kane Email Response to M.Dyas

3 page(s)
 CEC/M.DyasAES/Stephen O'Kane
6764910/10/2012Petition to Amend - Notice of Receipt

3 page(s)
 CEC/Docket UnitCEC/C.Marxen
6753810/5/2012Petition to Amend Final Decision to Convert Generating Units to Synchronous Condensers

40 page(s)
 CEC/C.StoraDowny Brand/J.Luckhardt
651445/9/2012Commission Letter to Operate Huntington Beach

1 page(s)
 AES Huntington Beach, LLC/ E.PentergraftCEC/ C.Stora
605315/4/2011Notice of Decision

1 page(s)
 CA. Resources AagencyCEC/ C. Snow
605225/5/2011Approval Letter of Petition to Transfer Ownership

1 page(s)
 AES Huntington Beach LLCCEC/ C. Snow
605035/4/2011Order Approving Transfer of Ownership from AES Huntington Beach to Edison Mission Huntington Beach, LLC

1 page(s)
 CEC/ Docket UnitCEC/ R. Weisenmiller
602784/18/2011Notice of Receipt Request for Ownership Change of Huntington Beach Generating Station Units 3&4

3 page(s)
 CEC/Dockets UnitCEC/C.Marxen
601663/30/2011Petition to Amend Change in Ownership of AES Huntington Beach Generation Station

11 page(s)
 CEC/ Docket UNitStoel Rivers
600263/17/2011Approval Leter to D. Dalton regarding Management Fee Payment

1 page(s)
 Spectrum Asset Management Inc./ D. DaltonCEC/ M. Jones
594671/12/2011CEC Letter to Huntington Beach Wetlands Conservancy regarding Approval of Proposal to allocate 75,000 in Accordance with Commission Condition BIO-5

2 page(s)
 Huntington Beach Wetlands ConservancyCEC/ M. Jones
5896411/5/2010Huntington Beach Owner Approval Letter

1 page(s)
 AES Huntington Beach LLC/E. PendergraftCEC/C. Snow
5888910/28/2010Huntington Beach ORDER NO. 10-1020-1

2 page(s)
 CEC/Docket UnitCEC/C. Snow
5885110/25/2010Notice of Decision

1 page(s)
 CA Resources AgencyCEC/C. Snow
5880510/18/2010Orange County Coastkeeper Comment Letter

2 page(s)
 CEC/C. SnowOrange County Coastkeeper/G. Brown
5880410/19/2010Notice of Errata Changes to Conditions of Certification

7 page(s)
 CEc/Docket UnitCEC/C. Snow
584209/8/2010Staff Analysis of Proposed License Extension

8 page(s)
 Interested PartiesCEC/C. Snow
569045/27/2010Approval Letter for Quarterly Management Fee Regarding Wetlands Restoration Project

1 page(s)
 Spectrum Aspect ManagementCEC/ M. Jones
567735/21/2010Pentition to Amend

3 page(s)
 CEC/ Docket UnitAES/ E. Pendergraft
560193/23/2010Notice of Receipt Petition to Extend License Deadline

3 page(s)
 CEC/Docket UnitCEC/C. Marxen
557173/1/2010Applicant's Petition to Amend the License Expiration Date for Units 3 & 4

6 page(s)
 CEC/M. DyasAES/ E. Pendergraft
392582/13/2007Memorandum of Understanding between AES HB LLC, the HB Wetlands Conservancy, and CEC Staff.

12 page(s)
 Docket UnitCEC/ D. Stone
3807110/4/2006HB Commission order and proof of service.

24 page(s)
 CEC/ Dockets UnitCEC/ Commissioners
379469/26/2006E-mail from E. Murphy RE Minute Order regarding Compliance with Condition of Certification BIO-5.

2 page(s)
 CEC/ D. StoneE. Murphy
379459/26/2006Minute Order regarding Compliance with Condition of Certification BIO-5

1 page(s)
 CEC/ D. StoneOcean Outfall Group/ J.D. Vandersloot
379329/25/2006Com. Byron Request for mitigation package that would be based on actual 5 yr. History

1 page(s)
 AES H.B./ E. PendergraftCEC/ J. Byron
379269/22/2006SWRCB comments on the clean water act.

59 page(s)
 CEC/ Dockets UnitCEC/ D. Stone
379179/21/2006AES Huntington Beach Retool Project for Unit 3 &4 Docket No. 00-AFC-13C

13 page(s)
 P. Richins/ CECE. Pendergaft / AES Huntington Beach
379069/20/2006AES Huntington Beach Generating Station Retool Project

2 page(s)
 D. StoneR. Rozzelle / Department of Parks and Water
378889/15/2006Notice of Energy Commission Staff Wordshop for the AES Huntington Beach Retool Project.

1 page(s)
 CEC/ Dockets UnitCEC/ R. Johnson
378699/13/2006CEC Staff Draft Order Regarding Condition BIO -5 and Order Regarding Compliance with Condition of Certification BIO 5

6 page(s)
 Docket UnitJ. Pfannenstiel/J.Boyd/J. Geesman/A. Rosenfield/J. Byron/CEC
378689/13/2006Letter In Response to September 1, 2006 Letter Requesting CEC Consider Compliance Condition Issue Regarding AES H B.

1 page(s)
 Docket UnitJ. Pfannenstiel /CEC
378679/13/2006AES Huntington Beach Retool Project for Units 3 & 4

1 page(s)
 Docket UnitCEC
378599/12/2006Re: Cultural resources application for confidentiality, AES Huntington Beach Generating Station.

2 page(s)
 URS Corp/ J. DivenCEC/ B. B. Blevins
378349/8/2006Minute Order Regarding Compliance with Condition of Certification BIO-5

1 page(s)
 CEC/Docket UnitCEC/J. Geesman/J. Byron
378029/6/2006Application for confidential designation and report- AES Huntington Beach Generating Station Retool Project Final Cultural Resources Report (Condition of certification CUL-7)

56 page(s)
 CEC/Docket unitJ.L. Diven/URS Corp.
377959/5/2006Letter requesting AES HB Retool Project to be put over for 30 days to allow time for an Appropriate Consultation Process.

2 page(s)
 CEC/ J. PfannenstielAES HB, LLC/ E. Pendergraft
377578/30/2006Huntington Beach Units 3&4 Entrainment and Impingement Study Results, Mitigation Options, Staff and Working Group Recommendations, and AES' Response and Objections to the Recommendation.

45 page(s)
 CECCEC/ N. Davis, P. Raimondi, R. York, and J. Reinhardt
377568/30/2006Staff Analysis of Extension Review Request to Operate Units 3 & 4 of the Generating Station through September 30, 2011.

3 page(s)
 Interested PartiesCEC/ D. Stone
376058/7/2006RE a Comment Letter sent to P. Richins/ CEC, Commenting on the July 14, 2006 Staff Analysis - H. B. Units 3 & 4 Entrainment and Impingement Study Results , Mitigation Options, Staff and Working Group Recommendations, and the July 25, 2006 Presentation.

14 page(s)
 CEC/ Docket UnitBingham McCutchen/ R. C. Horton
376018/7/2006Assessment of Feasibility of Closed-Cycle Wet Cooling and Impact of Desalination at Huntington Beach Generating Station.

21 page(s)
 Coast Law Group LLC/ T. CardiffPowers Engineering/ B. Powers
376008/7/2006Thank you and Comments Letter RE the AES Huntington Beach Impingement/ Entrainment Study and Proposed Mitigation Plan.

4 page(s)
 CEC/ J. ReinhardtCalifornia Coastal Commission/ T. Luster
375998/7/2006Letter from the O.C. Coastkeeper RE the Reduction of Impacts the AES Huntington Beach Generating Station has on the Coastal Environment.

2 page(s)
 CEC/ J. ReinhardtOrange County Coastkeeper/ R. Hiemstra
375888/7/2006Committee Workshop Held In Huntington Beach On July 25, 2006, Re: AFC AES Huntington Beach Generating Station Retool Project.

118 page(s)
 CEC/Dockets UnitCEC Facility Siting Committee
375097/31/2006Residents For Responsible Desalination (R4RD). Comments regarding information received from the AES representatives.

1 page(s)
 CEC/J. GeesmanE. Murphy
374537/18/2006Huntington Beach Units 3&4 Entrainment and Impingement Study Results, Mitigation Options, Staff and Working Group Recommendations, and AES's Response and Objections to the Recommendation

37 page(s)
 Docket UnitN. Davis, P. Raimondi, R. York, J. Reinhardt
373757/11/2006Notice of Siting Committee Workshop for The AES Hunting Beach Retool Project 00-AFC-13C to Discuss The Impingement and Entrainment Study and Staff Impacts

4 page(s)
 CECJ. L. Geesman / J. Byron /CEC
366413/28/2006Notice of Receipt "Five Year Extension Review."

3 page(s)
 General Dist./CEC/Docket UnitCEC/R. Johnson
364773/6/2006Annual Compliance Report & 5-Year Compliance Verfication.

35 page(s)
 Donna Stone/CEC/Docket UnitAES/E. Pendergraft
278391/12/2003Forms CEC -1304 Power Plant Owner Report Schedule 1 Part A & B and Schedule 2 Part a & B for the Fouth Quarte of 2002

12 page(s)
 CEC/Larson/docketsAes Huntington Beach/Vogt
244172/6/2002Visual Screening Plan (Condition of Certification VIS-2)

4 page(s)
 Aes/Huntington Beach Generating Station Retool/triCEC/Stone
2411910/19/2001Amendment to CEC License for AES Huntington Beach Generating Station Retool Project

20 page(s)
 CEC/DocketsAes Huntington Beach/Urs/diven
2319911/26/2001Petition for Amendment

69 page(s)
 CEC/DocketsMccutchen/Mcdonough
2304911/13/2001Approval of Request to Modity Huntington Beach Gen. Station Retool Project Conditions of Certification AQ-3 and AQ-4 to Require AES to Cease Operating Unit 5, or Retrofit it with Proper Emission Controls, by 9/30/02

1 page(s)
 Office Of Planning And Research/DocketsCEC/Stone
2301511/9/2001Approval of Request to Amend Language in Conditions of Certification AQ-3 and AQ-4

2 page(s)
 Aes/Blackford/docketsCEC/Stone
2276410/18/2001Amendment to the CEC License for the Hunting Beach Generation Station Retool Project

20 page(s)
 CEC/Stone/docketsMccutchen/Rothman
219408/16/2001Notice of Exemption-Addition of Condition of Certification to Ensure Coordinated Integration of New Generating Unit with California's Electricity Grid

1 page(s)
 Office Of Planning And Research/DocketsCEC/Bruins
217178/1/2001Letter in response to Gov. Davis letter

1 page(s)
 Choctaw Crude Oil Company/Curtis/docketsCEC/Keese
215257/18/2001Order on Petition for Reconsideration POS

7 page(s)
 CEC/DocketCEC/Commissioners
214917/17/2001Order on Petition for Reconsideration - POS

7 page(s)
 CEC/DocketsCEC/Commissioners
213947/12/2001AES' Response to Comments - POS

9 page(s)
 CEC/DocketsMccutchen, Doyle, Brown & Enersen/Rothman
213607/6/2001Response to Petition by AES Huntington Beach for Reconsideration of Certification Decision

11 page(s)
 CEC/DocketsAdams Broadwell Joseph & Cardozo/Joseph
213537/6/2001Response to City of Huntington Beach to Applicant's Petition for Reconsideration

13 page(s)
 CEC/DocketsJeffer, Mangels, Butler & Marmaro/Romero
213117/5/2001Response to Petition by AES Huntington Beach, LLC for Reconsideration of Certification Decision POS

10 page(s)
 CEC/DocketCure/Joseph
213047/2/2001CEC Staff's Response to Applicant's Petition for Reconsideration - POS

14 page(s)
 CEC/DocketsCEC/Kramer
209456/18/2001AES Request to remove requirement to sell electric to CA

1 page(s)
 Public Advisor's Office/Cec/docketsSmith
209416/18/2001Response to the Petition of AES Huntington Beach LLC for Reconsideration of Specific Condition of Certification Decision

7 page(s)
 DocketsUwua Local 246/Reid
208886/14/2001Notice of Commission Hearing on AES's Petition for Reconsideration

3 page(s)
 CEC/DocketCEC/Keese
208876/15/2001AES Request to remove requirement to sell electric to CA

1 page(s)
 CEC/Pao/docketSmith
207576/11/2001Petition of AES Huntington Beach, LLC for Reconsideration of Specific Conditions of Certification Decision

9 page(s)
 CEC/DocketsMccutchen/Rothman
207366/11/2001Petition for Recondiseration of Specific Condition of Certification Decision

8 page(s)
 DocketsMccutchen, Doyle, Brown, & Enersen/Rothman
204115/24/2001Letter stating that no record of a prior draft EIR or Negative Declaration having been submitted to the State Clearinghouse

1 page(s)
 CEC/Caswell/docketsGov. Office Of Planning & Research/Roberts