38602 | 12/11/2006 |
Notification of PG&E and mirantr agreement contra costa power project unit 8
2 page(s)
| | CEC/ Dockets Unit | CEC/ C. Meyer |
33979 | 8/18/2000 |
Confidential Designation: Request for Confidential Treatment of Offsets Information Response to CEC Data Requests
1 page(s)
| | CEC/Larson | Livingston And Mattesich/Mckinsey |
26540 | 8/27/2002 |
Final Determination of Compliance for Contra Costa Power Plant
98 page(s)
| | Dockets | Baaqmd/Wocasek |
23888 | 9/5/2000 |
Comments Concerning Biological Workshop
15 page(s)
| | CEC/Dockets | Hawkins |
21569 | 7/19/2001 |
Change of Address
1 page(s)
| | CEC/Dockets | Law Office Of L. Daube/Coombs |
20732 | 6/8/2001 |
Commission Decision
193 page(s)
| | CEC/Docket | CEC Cec |
20730 | 6/8/2001 |
Commission Decision - POS
199 page(s)
| | CEC/Dockets | CEC/Commissioners |
20639 | 6/5/2001 |
Committee Conference on Proposed Decisions Project Mailing List
1 page(s)
| | CEC/Dockets | Contra Costa Power Plant |
20636 | 6/5/2001 |
Notice of Decision
2 page(s)
| | Planning & Research/Resource Agency/dockets | CEC/Davis |
20597 | 6/1/2001 |
Commission Decision - Publication # P800-01-18
194 page(s)
| | CEC/Dockets | CEC Cec |
20510 | 5/29/2001 |
Supplemental Comments on the PMPD Response to Staff's Comments POS
12 page(s)
| | CEC/Shean/docket | Livingston & Mattesich/German |
20480 | 5/25/2001 |
Committee Conference on Proposed Decision Project Mailing List
1 page(s)
| | CEC/Dockets | Contra Costa Power Plant Project |
20464 | 5/25/2001 |
Committee Orders on Various CARE Motions
3 page(s)
| | Dockets | CEC/Keese/moore |
20385 | 5/21/2001 |
Plan to attend hearings to voice concerns and present proposal for mitigation
1 page(s)
| | CEC/Keese | California State Senate/Torlakson |
20379 | 5/22/2001 |
Comments on the Presiding Members Proposed Decision POS
12 page(s)
| | CEC/Shean | Livingston & Mattesich/German |
20378 | 5/22/2001 |
Comments on the Commission Staff on the Presiding Member's Proposed Decision POS
12 page(s)
| | Dockey | CEC/Decarlo |
20347 | 5/17/2001 |
COMMENTS ON THE PRESIDING MEMBER'S PROPOSED DECISION POS
38 page(s)
| | Docket | Care/Boyd |
20336 | 5/17/2001 |
DEMAND THAT CEC TERMINATE EXPENDITURE OF PUBLIC FUNDS PENDING RESOLUTION OF THE ENERGY CRISIS POS
3 page(s)
| | Docket | Care/Boyd |
20260 | 5/17/2001 |
Public Adviser's Status Reports 1st Trimester-2001
3 page(s)
| | Docket | CEC/Mendonca |
20218 | 5/14/2001 |
Errata and Clarifications for the Final Determination of Compliance - POS
12 page(s)
| | CEC/Davis/dockets | Baaqmd/Garvey |
20179 | 5/14/2001 |
Notice of Commission Hearing on Proposed Decision - May 30, 2001 - CEC - POS
3 page(s)
| | CEC/Dockets | CEC/Keese/moore |
20106 | 5/10/2001 |
Mirant Delta, LLC's Opposition to CARE's Motion to Deny the AFC - POS
9 page(s)
| | CEC/Dockets | Livingston & Mattesich/German |
20079 | 5/9/2001 |
Notice of Adoption of Renewed Waste Discharge Requirements and Thermal Plan Exception Resolution for Mirant Delta LLC POS
72 page(s)
| | Mirant Delta Llc/Gallo/dockets | California Regional Water Quality Control Board/Va |
20071 | 5/3/2001 |
Motion to reopen the administrative record to fully and fairly search for, identify, analyze evaluate and publicly disclose all charged facts & circumstances stemming from the recent, current and ongoing events involving the energy crisis
3 page(s)
| | CEC/Dockets | Care/Boyd |
20026 | 5/2/2001 |
Notice of Committee Conference on Proposed Decision POS
4 page(s)
| | Dockets | CEC/Keese, Moore |
19992 | 5/2/2001 |
Notice of Availability of Proposed Decision
2 page(s)
| | Dockets | CEC/Keese, Moore |
19982 | 4/30/2001 |
Presiding Member's Proposed Decision POS
195 page(s)
| | Docket | CEC/Keese, Moore |
19977 | 4/30/2001 |
Order Granting Petition to Intervene
5 page(s)
| | Docket | CEC/Keese |
19919 | 4/20/2001 |
Testimony of Valorie Zambiton, Mark Strehlow and Dr. Stephens R. J. Shepherds - POS
24 page(s)
| | Dockets | Livingston & Mattesich/German |
19857 | 4/23/2001 |
Order Granting Petition to Intervene-POS
4 page(s)
| | Dockets | CEC/Keese |
19848 | 4/20/2001 |
Notice of Teleconference Number for Evidentiary Hearing - POS
2 page(s)
| | Dockets | CEC/Shean |
19817 | 4/18/2001 |
City of Antioch Comments on the Tentative NPDES CA0004863, Waste Discharge Requirements and Monitoring and Reporting Program for Mirant Delta, LLC
4 page(s)
| | Valley Reg. Water Quality Control Brd/Ericson/dock | Public Works Department/Bernal |
19813 | 4/19/2001 |
Petition for Intervention as an Agency POS
7 page(s)
| | CEC/Docket | Care/Barry |
19802 | 4/18/2001 |
Supplemental Comments from the City of Antioch on CEC's Staff's Final Staff Assessment
9 page(s)
| | CEC/Shean/docket | CEC/Davis |
19776 | 4/17/2001 |
Study Conclusions and Recommendations
8 page(s)
| | Mirant Americas Development/Harrer | California Iso/Miller |
19757 | 4/16/2001 |
Motion to Deny for Certification for Incontrovertible Evidence of Prejudice by the Commission and It's Staff
8 page(s)
| | Care/Boyd/dockets | Hawkins |
19728 | 4/13/2001 |
Two CD-ROMs containing the Air Quality Modeling Files for the Enhanced Site Plan - POS
2 page(s)
| | CEC/Davis/dockets | Livingston & Mattesich/German |
19721 | 4/12/2001 |
Info Requested at recent workshops of FSA 1. Sound Levels 2. Responses to CEC questions
9 page(s)
| | CEC/Davis/docket | Livingston & Mattesich/German |
19685 | 3/30/2001 |
Public Letter-Evidence for Siting Cases (EMail)
29 page(s)
| | Docket | Thrasher |
19647 | 4/12/2001 |
1. Sound Levels assoc with enhanced Site Plan 2. Responses to CEC questions POS
8 page(s)
| | CEC/Davis/dockets | Livingston & Mattesich/German |
19585 | 4/10/2001 |
Submittal of Enhanced Site Plan Air Quality Impact Analysis
9 page(s)
| | CEC/Ngo/baaqmd/wocasek/dockets | Urs/Strehlow |
19576 | 4/10/2001 |
Notice of Evidentiary Hearing - 4/25/01 - CEC - POS
4 page(s)
| | Dockets | CEC/Moore/keese |
19572 | 4/4/2001 |
Committee Order Draft Findings & Discussion - POS
3 page(s)
| | Dockets | CEC/Moore/keese |
19452 | 4/2/2001 |
Motion to Deny the AFC for BAAQMD's Loss of Permitting Authority to Construct
3 page(s)
| | Dockets | Boyd |
19448 | 4/3/2001 |
Letter supporting MEC
1 page(s)
| | CEC/Laurie/dockets | Contra Costa Council/Jakel |
19442 | 4/4/2001 |
Committee Order re: Draft Findings & Discussion - POS
3 page(s)
| | Dockets | CEC/Keese/moore |
19436 | 3/30/2001 |
Finding of Failure to Attain EPA Region 9 Approval and Promulgation of Ozone Attainment Plan by the BAAQMD
5 page(s)
| | Dockets | Hawkins |
19432 | 4/3/2001 |
Continuance of Committee Workshop - 4/4/01 - CEC
1 page(s)
| | CEC/Dockets | CEC/Keese |
19399 | 3/27/2001 |
Objection to Sportsmen Yacht Club Data Requests, dated 3/11/01
5 page(s)
| | CEC/Shean/docket | Livingston & Mattesich/German |
19141 | 3/12/2001 |
Data Request - Set 8
8 page(s)
| | Mirant Energy Delta/Harrer/dockets | Sportsmen Yacht Club/Chapman |
19132 | 3/13/2001 |
Comments
3 page(s)
| | Dockets | Hawkins |
19023 | 3/5/2001 |
Replacement copies of Appendices E and F
14 page(s)
| | CEC/Davis/dockets | Baaqmd/Wopcasek |
19016 | 3/5/2001 |
Replacement copies of the Administrative Changes for pages 1-2, 17-18, 19-2- and 35-36.
9 page(s)
| | CEC/Davis/dockets | Baaqmd/Wocasek |
19005 | 3/2/2001 |
Status Report # 8 - POS
4 page(s)
| | CEC/Keese/moore/dockets | CEC/Davis |
19000 | 3/5/2001 |
Document Handling
3 page(s)
| | Librarian/Dockets | CEC/Richins |
18999 | 3/5/2001 |
Request for Agency Comments on the Final Staff Assessment
2 page(s)
| | Agency Distribution List/Dockets | CEC/Richins |
18998 | 3/5/2001 |
Notice of Availability Final Staff Assessment
1 page(s)
| | CEC/Dockets | CEC/Richens |
18975 | 3/5/2001 |
Waste Discharge Requirements for Mirant Delta, LLC
63 page(s)
| | Dockets | Californa Regional Water Quality Control Bd. |
18962 | 3/5/2001 |
Final Staff Assessment - Staff Report
541 page(s)
| | Dockets | CEC Cec |
18914 | 3/1/2001 |
Revised Sections 5.2 and 5.16 to the AFC - Revised Appendices P, Q, R, and S
1 page(s)
| | CEC/Dockets | Em-one Power Station Llc/Smith |
18902 | 3/1/2001 |
Status Report #8 - POS
2 page(s)
| | CEC/Moore/keese/dockets | CEC/Davis |
18901 | 2/28/2001 |
Notice of Committee Workshop & Pre-Hearing Conference
6 page(s)
| | CEC/Dockets | CEC/Keese/moore |
18882 | 2/13/2001 |
Brief overview for the Industrial Status the OWC Device - Technology & Appliance
11 page(s)
| | Dockets | Hawkins |
18859 | 2/27/2001 |
Revisions to Licensing Regulations
6 page(s)
| | Dockets | Hawkins |
18858 | 2/27/2001 |
Comments
3 page(s)
| | Dockets | Hawkins |
18734 | 2/13/2001 |
Oscillating Water Column web-page address sent to the Environmental News Network
3 page(s)
| | CEC/Dockets | Hawkins |
18676 | 2/12/2001 |
Demanding an FBI Investigation
4 page(s)
| | CEC/Dockets | Hawkins |
18670 | 2/9/2001 |
Electronic Proof of Service List
2 page(s)
| | Dockets | CEC/Shean |
18609 | 2/9/2001 |
Comments on the PDOC
71 page(s)
| | U.s. Epa/Rios | Bay Area Aqmd/Garvey |
18603 | 2/9/2001 |
Responses to CEC Data Requests, Set 3, Nos. 171 & 176 (Attachment: Proof of Service)
3 page(s)
| | CEC/Davis | Livingston & Mattesich/Varanini |
18591 | 2/7/2001 |
Notice of Name Change of Project Owner/Applicant - POS
3 page(s)
| | CEC/Dockets | Livingston & Mattesich/Varanini |
18590 | 2/9/2001 |
CARE's request for assistance in crafting the legislation necessary to bring California out of the current so-called energy crises
9 page(s)
| | CEC/Dockets | Hawkins |
18558 | 2/5/2001 |
Status Report #7 - POS
5 page(s)
| | CEC/Keese/moore/dockets | CEC/Davis |
18540 | 11/30/2000 |
Comments on the PSA
21 page(s)
| | CEC/Docket | Care/Smallwood |
18539 | 12/1/2000 |
Comments on the PSA & PDOC (Attachment: Proof of Service)
57 page(s)
| | CEC/Docket | Care/Boyd |
18468 | 2/9/2001 |
Order Granting Petition to Intervene (Filed by City of Pittsburg/Linda L. Daube) (Attachment: Proof of Service)
3 page(s)
| | CEC/Docket | CEC/Keese |
18461 | 1/10/2001 |
Various Attachments RE: The Dangers of Smaller Particles
11 page(s)
| | CEC/Docket | Hawkins |
18302 | 2/2/2001 |
Responses to Data Requests (Set 3: #168-182)
34 page(s)
| | CEC/Docket | Urs |
18301 | 2/2/2001 |
Responses to CEC 12/21/2000 Data Requests - Figures Submitted Under Separate Cover for Responses to Data Requests Set 3 #168 - 182
4 page(s)
| | CEC/Docket | Urs |
18282 | 2/5/2001 |
Responses to CEC Data Requests, Set 2, No. 176 (Attachment: Proof of Service)
9 page(s)
| | CEC/Davis | Livingston & Mattesich/Varanini |
18251 | 2/2/2001 |
Responses to CEC Data Requests (Set 3) (Attachment: Proof of Service)
4 page(s)
| | CEC/Davis | Livingston & Mattesich/Varanini |
18150 | 2/1/2001 |
Petition to Intervene by City of Pittsburg
5 page(s)
| | CEC/Docket | City Of Pittsburg/Daube |
18011 | 1/23/2001 |
Environmentalists or Economic, or What Caused the Energy Crises Fact or Fiction
4 page(s)
| | CEC/Dockets | Hawkins |
17977 | 1/22/2001 |
Data Request 133
2 page(s)
| | CEC/Docket | CEC/Davis |
17963 | 1/19/2001 |
Sign in Sheet RE: Visual Resources Workshop (January 18, 2001)
2 page(s)
| | CEC/Docket | CEC/Staff |
17962 | 1/12/2001 |
Public Adviser's Status Report 2000
41 page(s)
| | CEC/Docket | CEC/Pao |
17961 | 1/17/2001 |
Comments from the City of Antioch on the CEC PSA (Attachment: Proof of Service)
14 page(s)
| | CEC/Davis | Arcadis/Geraghty & Miler |
17960 | 1/11/2001 |
Letter to Mr. Emilio Varanini (Livingston & Mattesich Law Corp.) RE: On-Site Workshop January 18th 2001 (Attachment: Proof of Service)
4 page(s)
| | Livingston & Mattesich/Varanini | CEC/Davis |
17938 | 1/17/2001 |
Committee Ruling on CARE's Motion re: Public Participation - POS
5 page(s)
| | CEC/Dockets | CEC/Keese/moore |
17929 | 1/11/2001 |
Letter granting extension for the Responses to Data Requests, Set 3 - POS
2 page(s)
| | Livingston & Mattesich/Varanini | CEC/Davis |
17914 | 1/17/2001 |
Peer Review of the Eligibility Evaluation (Attachment: Proof of Service)
6 page(s)
| | CEC/Edwards | California Dept. Of Transportation/King |
17913 | 1/17/2001 |
Committee Ruling on CARE's Motion RE: Public Participation (Attachment: Proof of Service)
5 page(s)
| | CEC/Docket | CEC/Keese/moore |
17881 | 1/18/2001 |
ORDER Granting Petition to Intervene - Elizabeth H. Silver, Meyers, Nave Riback, Silver & Wilson - POS
3 page(s)
| | CEC/Dockets | CEC/Keese |
17831 | 1/11/2001 |
Request for another Extension of the Deadline for Compliance with Your 12/13/00 Order in Regards to CARE's Motion for a Hearing or Workshop on Public Participation Pursuant CEQA - POS
4 page(s)
| | CEC/Dockets | Care/Boyd |
17830 | 1/10/2001 |
Comments and recommendation regarding the proposed "Aquatic Filter Barrier Contra Costa Power Existing Units 6 & 7
1 page(s)
| | CEC/Adams | Depart. Of Boating And Waterways/Johnson |
17820 | 1/10/2001 |
Report of Conversation with Kathie Hammer, Sportmen Yacht Club Regarding Questions about the Sausalito Ferry Clubhouse for Cultural Resources Analysis
1 page(s)
| | CEC/Dockets | CEC/Reinoehl |
17743 | 1/5/2001 |
Status Report #6 - January, 2001 (Attachment: Proof of Service)
6 page(s)
| | CEC/Chairman And Presiding Member | CEC/Davis |
17731 | 1/5/2001 |
CARE's Data Request on the Motion for a hearing or Workshop on Public Participation Pursuant CEQA (Attachment: Proof of Service)
3 page(s)
| | CEC/Docket | Care/Boyd |
17730 | 1/5/2001 |
CARE's Data Request on the Motion for a Hearing or Workshop on Public Participation Pursuant CEQA (Attachment: Proof of Service)
10 page(s)
| | CEC/Docket | Care/Boyd |
17715 | 1/8/2001 |
More on Staff's Role Visa Vi the Public, the CEC's "Overide" of the City of San Jose, Public Participation, and Intervenor Funding As Part of the Evidentiary Hearings
3 page(s)
| | CEC/Docket | Care/Boyd |
17703 | 1/8/2001 |
Workshop Notice - 1/18/01 - Antioch - POS
10 page(s)
| | CEC/Dockets | CEC/Keese |
17700 | 1/5/2001 |
Responses to CEC Data Requests (Set 3) - POS
4 page(s)
| | CEC/Davis | Livingston & Mattesich/Varanini |
17685 | 1/2/2001 |
More on CARE's Petition for a hearing on CEC "override" of the City of San Jose, Public Participation, and Intervenor funding as par of the Evidentiray Hearings
4 page(s)
| | CEC/Dockets | Care/Boyd |
17670 | 12/29/2000 |
Applicant's Comments on the Contra Costa Power Plant Unit 8 Project Preliminary Staff Assessment
11 page(s)
| | CEC/Dockets | Southern Energy Delta Llc |
17660 | 1/2/2001 |
Report of Conversation - Champman - E-mail Q&A's regarding design, condition and use of the Sausalito Ferry
4 page(s)
| | CEC/Dockets | CEC/Davis |
17652 | 1/2/2001 |
Petition for a Hearing on CEC "override" of the City of San Jose, public participation, and Intervenor funding as part of the Evidentiary Hearings
3 page(s)
| | Care/Boyd | Hawkins |
17627 | 12/28/2000 |
Comments on CEC staff regarding the Commission's stated goal of providing California residents with full and complete information about power projects affecting them.
1 page(s)
| | CEC/Keese | Contra Costa Times/May |
17607 | 12/26/2000 |
12/13/00 Order in Regards to CARE's Motion for a Hearing or Workshop on Public Participation Pursuant CEQA
6 page(s)
| | CEC/Dockets | Care/Boyd |
17596 | 12/26/2000 |
Order Granting CARE's Request for an Extension
2 page(s)
| | CEC/Dockets | CEC/Shean |
17593 | 12/27/2000 |
Comments on the PSA - Alternatives and Noise - POS
4 page(s)
| | CEC/Dockets | Sportsmen Yacht Club/Chapman |
17582 | 12/27/2000 |
Response to 12/22/00 Public Records Act request
9 page(s)
| | Care/Boyd | CEC/Munstock |
17552 | 12/22/2000 |
CARE's Data Request on the Motion for a Hearing or Workshop on Public Participation Pursuant CEQA
11 page(s)
| | CEC/Dockets | Care/Boyd |
17551 | 12/26/2000 |
More on the 12/13/00 Order in Regards to CARE's Motion for a Hearing or Workshop on Public Participation Pursuant CEQA
3 page(s)
| | CEC/Dockets | Care/Boyd |
17548 | 12/26/2000 |
ORDER Granting CARE's Request for Extension
1 page(s)
| | CEC/Dockets | CEC/Shean |
17519 | 12/26/2000 |
More on the 12/13/00 Order in Regards to CARE's Motion for a Hearing or Workshop on Public Participation Pursuant CEQA
3 page(s)
| | CEC/Dockets | Care/Boyd |
17506 | 12/26/2000 |
More on the 12-13-00 Order in Regards to CARE's Motion for a Hearing or Workshop on Public Participation Pursuant CEQA
3 page(s)
| | CEC/Dockets | Care/Boyd |
17503 | 12/6/2000 |
Status Report #5
3 page(s)
| | CEC/Keese/moore | CEC/Davis |
17502 | 12/22/2000 |
Request for an Extension of the 12/27/00 Deadline for Compliance with You r12/13/00 Order in Regards to CARE's Motion for a Hearing or Workshop on Public Participatiopn Pursuant CEQA
6 page(s)
| | CEC/Docket | Care/Boyd |
17491 | 12/22/2000 |
Petition for Intervention as an Agency (Attachment: Proof of Service)
4 page(s)
| | CEC/Docket | Meyers, Nave, Riback, Silver & Wilson/Silver |
17486 | 12/26/2000 |
12/13/00 Order to CARE's Motion for a Hearing or Workshop on Public Participation Pursuant CEQA
3 page(s)
| | CEC/Dockets | Care/Boyd |
17483 | 12/14/2000 |
Comments on CCPP #8 PDOC
10 page(s)
| | Mike Boyd | Joe Hawkins |
17474 | 12/26/2000 |
Comments on the PSA - Alternatives and Noise
3 page(s)
| | CEC/Dockets | Sportsmen Yacht Club/Chapman |
17462 | 12/15/2000 |
Comments on the PSA Project Description, Land Use, Cultural Resources and Alternatives
1 page(s)
| | CEC/Docket | Sportsmen Yacht Club/Chapman |
17458 | 12/18/2000 |
Committee Order
5 page(s)
| | CEC/Dockets | Care/Boyd |
17438 | 12/18/2000 |
Comments of the PSA - Project Description Land Use, Cultural Resources Alternatives
4 page(s)
| | CEC/Dockets | Sportsmen Yacht Club/Chapman |
17416 | 12/20/2000 |
Applicant's Comments on the Staff PSA (Attachment: Proof of Service)
11 page(s)
| | CEC/Docket | Livingston & Mattesich/Anderson |
17372 | 12/13/2000 |
Comments RE: Power Plant(s), Measure "C" and General Plan(s) (Attachment: Proof of Service)
14 page(s)
| | CEC/Davis/staff | Norma & Ralph Hernandez |
17366 | 12/11/2000 |
Ionization as a Factor In Our Environment, and in the Health and Behavior of Man Suspected Adverse Ion Effects Upon Employees and Their Work Areas Unhealthy Conditions and the Work Environment
9 page(s)
| | CEC/Docket | Ralph Hernandez |
17331 | 12/11/2000 |
Report of Conversation With Tom Murphy (Aspen Environmental Group) RE: Noise Monitoring
1 page(s)
| | CEC/Docket | CEC/Baker |
17321 | 12/12/2000 |
Project Mailing List - Staff PSA Workshop - Antioch
5 page(s)
| | CEC/Dockets | Contra Costa Power Plant |
17278 | 12/12/2000 |
CEC Energy Crisis
6 page(s)
| | CEC/Dockets | Hawkins |
17262 | 12/7/2000 |
Sign-in Sheet RE: Staff PSA Workshop
2 page(s)
| | CEC/Docket | CEC/Staff |
17259 | 12/7/2000 |
Comments RE: Expansion Plans
2 page(s)
| | CEC/Davis | Charles W. Worrell |
17256 | 12/4/2000 |
Preliminary Determination of Compliance - POS
8 page(s)
| | CEC/Dockets | Us Environmental Protection Agency/Rios |
17254 | 12/4/2000 |
Errata to Comment on the PSA & PDOC
2 page(s)
| | CEC/Dockets | Care/Boyd |
17251 | 12/1/2000 |
Chronic Illness Burden
3 page(s)
| | CEC/Dockets | Hawkins |
17246 | 12/4/2000 |
Comments on PSA
1 page(s)
| | CEC/Dockets | CEC/Davis |
17235 | 12/1/2000 |
Comments on Preliminary Staff Assessment
4 page(s)
| | CEC/Dockets | Baaqmd |
17234 | 12/1/2000 |
Concerning Pollution and Hydrocarbons and Illness
3 page(s)
| | CEC/Dockets | Hawkins |
17233 | 12/6/2000 |
Project Mailing List - Staff PSA Workshop - Antioch
2 page(s)
| | CEC/Dockets | Contra Costa Power Plant Unit 8 |
17230 | 12/6/2000 |
Status Report # 5 - POS
4 page(s)
| | CEC/Keese/moore | CEC/Davis |
17227 | 12/5/2000 |
Comments on Ozone Getting Worse
2 page(s)
| | CEC/Dockets | Hawkins |
17226 | 12/6/2000 |
Comments on the PSA & PDOC
49 page(s)
| | CEC/Dockets | Care/Boyd/mcdonald |
17225 | 12/6/2000 |
Motion for a Hearing or Workshop on Public Participation Pursuant CEQA
17 page(s)
| | CEC/Dockets | Care/Boyd |
17224 | 12/6/2000 |
Comments on the Preliminary Staff Assessment
21 page(s)
| | CEC/Dockets | Care/Boyd |
17215 | 12/8/2000 |
Report of Conversation with Tom Murphy, Aspen Environmental Group regarding Noise Monitoring
1 page(s)
| | CEC/Dockets | CEC/Baker |
17179 | 12/1/2000 |
Review of Preliminary Staff Assessment
2 page(s)
| | CEC/Davis | Contra Costa Co./Fire Protection Dist./thude |
17140 | 12/1/2000 |
Report of Conversation RE: Determination of Eligibility for the Contra Costa Plant
1 page(s)
| | CEC/Docket | CEC/Reinoehl |
17139 | 12/1/2000 |
Concerns stated in letter dated August 29, 2000 - The Department would like the Applicant's Study to identify transmission loading problems during Off-Peak hours that would curtail the peak load of 275 MW at Banks Pumping Plant.
2 page(s)
| | CEC/Davis | Dwr/Ramirez |
17046 | 11/7/2000 |
Preliminary Staff Assessment (Attachment: Proof of Service)
450 page(s)
| | CEC/Docket | CEC/Staff |
16994 | 11/14/2000 |
Order Granting Petition to Intervene (Californians for Renewable Energy, Inc./Mike Boyd) Attachment: Proof of Service)
4 page(s)
| | CEC/Docket | CEC/Keese |
16946 | 11/13/2000 |
BAAQMD Determination of Compliance Review
65 page(s)
| | CEC/Davis | Bay Area Aqmd/Garvey |
16945 | 11/21/2000 |
Teleconference Outcome
2 page(s)
| | Dames & Moore/Shileikis/fehr & Peers/isaac | Korve/Demirjian/menaker |
16865 | 11/16/2000 |
Workshop Notice: Staff PSA Workshop (Air Quality, Public Health and EJ - Dec. 4, 2000; Biology, Soil and Water Resources, and Noise - Dec. 6, 2000; if Necessary Dec. 11,2000) (Attachment: Proof of Service)
5 page(s)
| | CEC/Docket | CEC/Keese |
16754 | 11/14/2000 |
Document Handling
1 page(s)
| | Librarian | CEC/Therkelsen |
16753 | 11/14/2000 |
Public Participation
1 page(s)
| | Member Of The Public | CEC Cec |
16752 | 11/14/2000 |
Request for Agency Comments on the Preliminary Staff Assessment
1 page(s)
| | Agency Distribution List | CEC/Therkelsen |
16734 | 11/14/2000 |
Notice of Availability - Preliminary Staff Assessment
3 page(s)
| | CEC/Dockets | CEC/Therkelsen |
16672 | 11/9/2000 |
Petition for Intervention With Financial Hardship
2 page(s)
| | CEC/Dockets | Care/Boyd |
16620 | 11/6/2000 |
Aquatic Filter Barrier Information and Water Flow and Volume Figure
12 page(s)
| | CEC/Lewis | Livingston & Mattesich/Varanini |
16489 | 10/30/2000 |
Status Report No. 4 (Attachment: Proof of Service)
5 page(s)
| | CEC/Keese/moore | CEC/Davis |
16447 | 10/27/2000 |
Order Granting Petition to Intervene (Sportsmen Inc., Yacht Club/Tony Chapman) (Attachment: Proof of Service)
3 page(s)
| | CEC/Docket | CEC/Keese |
16267 | 10/23/2000 |
Petition for Intervention as a Group - POS
9 page(s)
| | CEC/Dockets | Sportsmen Inc. Yacht Club/Maclear |
16255 | 10/20/2000 |
Responses to CEC Data Requests Dated 9/15/2000: Appendix C, Determination of Eligibility for the Contra Costa Power Plant; Corrected Replacement Pages Which Relate to the Responses to CEC Data Requests 119-167, Filed by Applicant on October 13, 2000 (Attachment: Proof of Service)
64 page(s)
| | CEC/Lewis | Livingston & Mattesich/Varanini |
16183 | 10/17/2000 |
Response to Committee Order Directing Staff to Make Verification Timetable for the Contra Costa Power Project (Attachment: Proof of Service)
8 page(s)
| | CEC/Keese/moore | CEC/Therkelsen |
16146 | 10/18/2000 |
Response to Data Request #164 - Disk
1 page(s)
| | CEC/Lewis | Livingston & Mattesich |
16120 | 9/29/2000 |
Comment RE: Public Participation.
4 page(s)
| | CEC/Docket | Joe Hawkins |
16109 | 10/3/2000 |
Status Report #3 (October 1, 2000) (Attachment: Proof of Service)
5 page(s)
| | CEC/Keese/moore | CEC/Lewis |
16098 | 10/4/2000 |
Summary RE: Biological Resources Workshop (Sept. 14, 2000) (Attachment: Proof of Service)
8 page(s)
| | Proof Of Service | CEC/Lewis |
16097 | 10/5/2000 |
Concern RE: The Proposed 530 MW Contra Costa Power Plant Unit 8 Project will Increase the Available Fault Currents at the Department's Bank Pumping Plant, Which Could Result in Exceeding the Short Circuit Capabilities of the Electrical Equipment at Banks Pumping Plant.
1 page(s)
| | CEC/Lewis | Dept. Of Water Resources/Ramirez |
16067 | 10/13/2000 |
Responses to CEC Data Requests Dated 9/15/2000 (Attached: Proof of Service)
183 page(s)
| | CEC/Docket | Livingston & Mattesich/Varanini |
16058 | 10/12/2000 |
Sign-in Sheet RE: Staff Workshop (Oct. 11, 2000)
5 page(s)
| | CEC/Dockets | CEC/Staff |
16054 | 10/12/2000 |
E-mail Noise Section Status for Contra Costa PSA
1 page(s)
| | CEC/Dockets | Aspen Environmental Group/Murphy |
15990 | 10/6/2000 |
Review/Comments RE: PG&E- Prepared Contra Costa Power Plant Capacity Increase Project
4 page(s)
| | Southern Energy, Inc./Coggins | California Iso/Miller |
15862 | 9/29/2000 |
Workshop Notice: Staff Workshop (October 11, 2000) (Attachment: Meeting Location Map; Proof of Service)
5 page(s)
| | CEC/Docket | CEC/Keese |
15861 | 9/18/2000 |
Application for Confidential Designation Pertaining to Operational Costs Associated With Cooling Technologies.
4 page(s)
| | CEC/Smith | Livingston & Mattesich/Mckinsey |
15860 | 9/18/2000 |
Order Directing Staff to Make Verification Timetable (Attachment: Electronic Proof of Service List)
3 page(s)
| | CEC/Docket | CEC/Keese/moore |
15859 | 9/15/2000 |
Second Set of Data Requests (Attachment: Proof of Service)
20 page(s)
| | Southern Energy California/Harrer | CEC/Lewis |
15858 | 9/15/2000 |
Supplemental Responses to Staff Data Requests 104 and 105. (Attachment: Proof of Service)
17 page(s)
| | CEC/Lewis | Livingston & Mattesich/Mckinsey |
15815 | 9/20/2000 |
Order directing Applicant to Complete Lors Matrix - POS
5 page(s)
| | CEC/Dockets | CEC/Keese/moore |
15754 | 9/14/2000 |
Teleconference Outcome
2 page(s)
| | Dames & Moore/Shilekis/fehr & Peers/isaac | Korve Engineering/Demirjian/menaker |
15736 | 9/8/2000 |
Order Directing Staff to Complete Siting Review Matrix
48 page(s)
| | CEC/Docket | CEC/Keese/moore |
15734 | 9/14/2000 |
Supplemental Information Emissions Offsets (Attachment: Proof of Service)
5 page(s)
| | CEC/Larson | Southern Energy Company/Harrer |
15671 | 9/5/2000 |
Protecting the workshop location and time concerning Biological Resources
15 page(s)
| | CEC/Dockets | Hawkins |
15663 | 9/5/2000 |
Workshop Notice - Biological Resources (Attachment: Proof of Service)
5 page(s)
| | CEC/Docket | CEC/Keese |
15662 | 9/5/2000 |
Status Report #2 - Sept. 1, 2000 (Attachment: Proof of Service)
5 page(s)
| | CEC/Keese/moore | CEC/Lewis |
15661 | 9/5/2000 |
Order Directing Staff to List Past Conditions of Certification for Contra Costa Unit 8 (Attachment: Proof of Service)
82 page(s)
| | CEC/Keese/moore | CEC/Lewis |
15539 | 8/21/2000 |
Public Comments
1 page(s)
| | CEC/Dockets | Joe Hawkins |
15518 | 8/18/2000 |
KOP #2, 4, 7, and 8 responses to Data Request Nos. 61 - 75
22 page(s)
| | CEC/Lewis | Livingston & Mattesich/Mckinsey |
15512 | 8/25/2000 |
Revised POS and the electronic POS List reflecting Mr. Hawkins' request to withdraw - POS
5 page(s)
| | All Parties | CEC/Shean |
15496 | 8/18/2000 |
Application for Revewal of the NPDES Permit No. CA0004863
81 page(s)
| | Ca Regional Water Quality Control Brd/Carlton | Southern Company/Gallo |
15494 | 8/18/2000 |
Draft - Revision 5 - Multispecies Habitat Conservation Plan
367 page(s)
| | CEC/Dockets | Southern Energy/Gallo |
15493 | 8/18/2000 |
Thermal Effects Final Report
293 page(s)
| | Ca Reg. Water Quality Control Brd/Crooks/ritchin | Pg&e/Walton |
15492 | 8/18/2000 |
Application for Renewal of the NPDES Permit # CA0004863
80 page(s)
| | Ca Reg. Water Quality Control Brd/Carlton | Southern Energy California/Gallo |
15490 | 8/18/2000 |
Application for Renewal of the NPDES Permit # CA0004863
80 page(s)
| | Ca Reg. Water Quality Control Brd/Carlton | Southern Energy California/Gallo |
15424 | 8/11/2000 |
Request to Withdraw (Attachment: Proof of Service)
10 page(s)
| | CEC/Docket | Joe Hawkins |
15423 | 8/14/2000 |
Staff Response to Intervenor Joe Hawkins' Data Request (Attachment: Proof of Service)
5 page(s)
| | Joe Hawkins | CEC/Davis |
15416 | 8/16/2000 |
ORDER Instituting Electronic Filing Pilot Project (Effective on of after Sept. 1, 2000) (Attachment: Protocols for Electronic Proof of Service pilot Project; Electronic Proof of ServiceList)
8 page(s)
| | CEC/Docket | CEC/Keese/moore |
15415 | 8/11/2000 |
Detailed Facilities Study - Southern Energy California, Contra Costa Power Plant Capacity Increase Project (Dated July 12, 2000)
362 page(s)
| | CEC/Docket | Pg&e Co. |
15377 | 8/10/2000 |
Request to Loan AFC
1 page(s)
| | CEC/Davis | Weston & Benshoff/Rostker |
15376 | 8/10/2000 |
Public Comment Form
1 page(s)
| | CEC/Docket | Dr. Paulette Lagana |
15375 | 8/10/2000 |
Public Comment Form
1 page(s)
| | CEC/Docket | Bill Worrell |
15374 | 8/10/2000 |
Public Comment Form
1 page(s)
| | CEC/Docket | Ralph A. Hernandez |
15346 | 8/4/2000 |
Fax From Bay Area AQMD, Dated July 28, 2000, Providing a Listing of "Future Sources" Within 10 Miles of the Subject Plant. (Attachment: Proof of Service)
3 page(s)
| | CEC/Docket | Livingston & Mattesich/Mckinsey |
15345 | 8/2/2000 |
Applicant's Objections to Data Requests of Intervenor Joe Hawkins (Attathcment: Proof of Service)
6 page(s)
| | CEC/Docket | Livingston & Mattesich Law Corp./Varanini/mckinse |
15344 | 7/31/2000 |
ORDER Directing Staff to List Past Conditions of Certification (Attachment: Proof of Service)
5 page(s)
| | CEC/Docket | CEC/Keese/moore |
15343 | 7/27/2000 |
Sign-in Sheet RE: Data Request Workshop (July 25, 2000)
8 page(s)
| | CEC/Docket | CEC/Staff |
15279 | 7/24/2000 |
Order Granting Petition to Intervene (Attachment: Proof of Service)
5 page(s)
| | CEC/Docket | CEC/Keese |
15268 | 8/1/2000 |
Status Report #1 - August 1, 2000 (Attachment: Proof of Service)
5 page(s)
| | CEC/Keese/moore | CEC/Lewis |
15267 | 7/21/2000 |
Address Change (Southern Energy Delta LLC/Robert Hayes) (Attachment: Proof of Service)
3 page(s)
| | CEC/Docket | Livingston & Mattesich/Varanini |
15260 | 7/12/2000 |
Application for Certification (Electronic Version)
1 page(s)
| | CEC/Docket | Livingston & Mattesich/Varanini |
15258 | 7/13/2000 |
Request for Extension of First Data Request Response Due Date (Attachment: Proof of Service)
2 page(s)
| | CEC/Keese | Livingston & Mattesich/Varanini |
15207 | 7/20/2000 |
Revised Service List
5 page(s)
| | All Parties | CEC/Shean |
15197 | 7/14/2000 |
Letter granting Joe Hawkins permission to intervene - POS
4 page(s)
| | CEC/Dockets | CEC/Mendonca |
15196 | 7/14/2000 |
Data Requests
6 page(s)
| | CEC/Dockets | Joe Hawkins |
15195 | 7/14/2000 |
Data Request - POS
5 page(s)
| | CEC/Dockets | Joe Hawkins |
15194 | 7/14/2000 |
Data Request - POS
8 page(s)
| | CEC/Dockets | Joe Hawkins |
15145 | 7/18/2000 |
Comments regarding the May 24, 2000 Notice of Public Informational Hearing and Site Visit
2 page(s)
| | CEC/Keese | Department Of The Army/Finan |
15110 | 7/14/2000 |
Staff Data Request Workshop - 7/25/00 - Antioch - Map
2 page(s)
| | CEC/Dockets | CEC/Keese |
15079 | 7/18/2000 |
Detailed Facilities Study
1058 page(s)
| | CEC/Docket | Pacific Gas And Electric Company |
15024 | 7/11/2000 |
Petition for Intervention as a Group - POS
3 page(s)
| | CEC/Docket | Cap-it/Lagana |
15019 | 6/29/2000 |
Contra Costa Power Plant Unit 8 First Set of Data Requests
37 page(s)
| | Southern Energy Ca/Harrer | CEC/Lewis |
14942 | 6/15/2000 |
Sign-in Sheet RE: June 12, 2000 Information Hearing and Site Visit
6 page(s)
| | CEC/Docket | CEC/Staff |
14921 | 6/20/2000 |
Scheduling Order 1st and 2nd Quarters - POS
6 page(s)
| | CEC/Dockets | CEC/Keese/moore |
14866 | 6/7/2000 |
Request to change the location of the June 12th meeting.
1 page(s)
| | CEC/Docket | Joe Hawkins |
14865 | 6/6/2000 |
Petition for Intervention as an Agency (William R. Galstan, City Attorney) (Attachment: Proof of Service)
4 page(s)
| | CEC/Docket | City Of Antioch/Galstan |
14864 | 6/9/2000 |
Orders Granting Petition to Intervene - (Granted to the following Petitioners: Joe P. Hawkins; Christopher T. Ellison, Esq (Ellison & Schneider); City of Antioch (William R. Galstan); (Attachment: Proof of Service)
8 page(s)
| | CEC/Docket | CEC/Keese |
14793 | 6/9/2000 |
Issue Identification Report - POS
13 page(s)
| | CEC/Laurie/moore | CEC/Lewis |
14734 | 5/30/2000 |
E-mail regarding CEC's Informal Hearing - June 12, 2000
2 page(s)
| | CEC/Dockets | Joe Hawkins |
14700 | 6/1/2000 |
Petition to Intervene by CURE Reliable Energy - POS
7 page(s)
| | CEC/Dockets | Cure/Joseph |
14644 | 5/25/2000 |
Notice of Public Informational Hearing & Site Visit (June 12, 2000) (Attachment: Proof of Service)
6 page(s)
| | CEC/Docket | CEC/Keese/moore |
14636 | 5/26/2000 |
Energy Commission Order - Order # 00-0523-03
5 page(s)
| | CEC/Dockets | CEC/Keese |
14594 | 5/17/2000 |
Hearing Officer Assignment - Garret Shean assigned to assist the assigned Committee in conducting proceedings on the Application for Certification for the Contra Costa Power Plant Project
1 page(s)
| | CEC/Commissioners | CEC/Keese |
14588 | 5/22/2000 |
Letter stating that a petition to intervene was received
1 page(s)
| | Joe Hawkins | CEC/Ross |
14576 | 5/20/2000 |
Request to Become Intervenor From: Joe P. Hawkins Concerned Citizen Effected In Air Basin
5 page(s)
| | Dockets | Joe P. Hawkins |
14481 | 5/10/2000 |
Application for Authority to Construct, Submitted to the Bay Area Quality Management District on March 3, 2000; Response to Information Request for Application Number 1000 Authority, Submitted April 18, 2000; A CD Containing Air Qiality and Public Health Modeling Files (Rev. 1, April 2000)
1 page(s)
| | CEC/Mckinney | Dames & Moore/Shileikis |
14471 | 5/10/2000 |
Second Data Adequacy Recommendation
51 page(s)
| | CEC/Commissioners | CEC/Larson |
14469 | 5/11/2000 |
Report of Conversation with Walker, Flores, Edwards, Johnson, DeCarlo, regarding Visual Resources: Photo Simulations
1 page(s)
| | CEC/Dockets | CEC/Mckinney |
14443 | 4/20/2000 |
Authority to Construct and permit to operate for a 530 MW Combined Cycle Cogeneration Facility has been assigned the above application number and is currently incomplete.
2 page(s)
| | Southern Energy Delta/Kino | Bay Area Air Quality Mgmt. Dist. |
14432 | 5/1/2000 |
Agenda Item for the May 17, 2000 Business Meeting - Committee Assignment for the Contra Costa Power Plant Unit 8 (Attachment: Agenda Input Form(General))
3 page(s)
| | CEC/Docket | CEC/Therkelsen |
14385 | 5/8/2000 |
Letter regarding consideration in the setting of allowable limits to additional noise, and effects on air and water quality.
1 page(s)
| | CEC/Keese | Sportsmen Yacht Club/Maclean |
14375 | 5/5/2000 |
Comments on Proposed Contra Costa Unit 8 Project
1 page(s)
| | Sportsman Yacht Club/Maclean | CEC/Keese |
14356 | 5/1/2000 |
Agenda Item for the May 17, 2000 Business Meeting - Commission Consideration for the Executive Director's Second Data Adequacy Recommendation for the Contra Costa Power Plant Unit 8 Project Application for Certification .
2 page(s)
| | CEC/Larson | CEC/Therkelsen |
14343 | 4/20/2000 |
Staff Review of the Application for Certification
1 page(s)
| | CEC/Smith | Bay Area Aqmd/Boisblanc |
14300 | 4/20/2000 |
Response to Information Request for Application Number 1000 Authority to Construct
49 page(s)
| | Baaqmd/De Boisblanc | Southern Com |
14299 | 5/1/2000 |
Commission consideration of the Executive Director's second data adequacy recommendation - Attachment: Agenda Item for the May 17, 2000 Busines Meeting
2 page(s)
| | CEC/Docket | CEC/Mckinney |
14292 | 4/25/2000 |
Supplement to the AFC for the Contra Costa Plant Unit 8 Project
1 page(s)
| | Agency Distribution List | CEC/Therkelsen |
14290 | 4/26/2000 |
Report of Conversation with Mark Herrer - Southern Energy LLC and Bill Stevenson - Dames and Moore Engineering Specialist regarding Data Adequacy for Transmission System Engineering
1 page(s)
| | CEC/Dockets | CEC/Mccuen |
14278 | 4/25/2000 |
Supplement regarding: Construct and operate a 530 MW natural gas-fired, combined-cycle power generating facility
1 page(s)
| | Agency Distribution List | CEC/Therkelsen |
14277 | 4/25/2000 |
Supplement regarding: Construct and operate a 530 megawatt natural gas-fired, combined-cycle power generating facility
1 page(s)
| | Librarian | CEC/Therkelsen |
14276 | 4/25/2000 |
Supplement regarding: construct and operate a 530 megawatt natural gas-fired, combined-cycle power generating facility
1 page(s)
| | Interested Parties | CEC/Therkelsen |
14252 | 4/18/2000 |
SUPPLEMENTAL INFORMATION in Response to CEC Data Adequacy Requests: CESA MOU and Management Authorization by and between PG&E Co. and the CDFG -and- Draft Multispecies Habitat Conservation Plan for the Pittsburg and Contra Costa Power Plants August 10, 1998 (April 2000)
359 page(s)
| | CEC/Docket | Southern Energy Delta Llc/Hayes |
14251 | 4/18/2000 |
SUPPLEMENTAL INFORMATION in Response to CEC Data Adequacy Requests - Waste Discharge Requirements Order 95-234, NPDES No. 0004863
57 page(s)
| | CEC/Docket | Southern Energy Delta Llc/Hayes |
14211 | 4/18/2000 |
SUPPLEMENTAN INFORMATION - In Response to CEC Data Adequacy Request. (April 2000)
1258 page(s)
| | CEC/Smith | Southern Energy Delta Llc/Hayes |
14203 | 4/18/2000 |
Supplemental Information in Response to CEC Data Request
1 page(s)
| | CEC/Smith | Livingston & Mattesich/Varanini |
14142 | 3/29/2000 |
Report of Conversation with Dames & Moore, Dale Shileikis and Mark Strehlow regarding Clarification of Air Quality Data Adequacy Issues
2 page(s)
| | CEC/Docket | CEC/Mckinney |
14130 | 4/4/2000 |
Letter from the US Environmental Protection Agency Region IX regarding an update on the air pollution control technology - POS
7 page(s)
| | CEC/Docket | CEC/Johnson |
14026 | 3/24/2000 |
Unit 8 Project - Compact Disc of Air Quality and Public Health Modeling Files missing from the AFC
1 page(s)
| | CEC/Mckinney | Livingston & Mattesich/Mckinsey |
13924 | 3/16/2000 |
Comments RE: Contra Costa Project.
2 page(s)
| | CEC/Ringer | Dept. Of Toxic Substances Control/Cook |
13923 | 3/16/2000 |
Comments RE: the Review of the Contra Costa Project.
1 page(s)
| | CEC/Adams | Dept. Of Transportation/Finney |
13860 | 3/9/2000 |
Review will be conducted of Contra Costa Power Plant, unit 8 Project Application For Certification,
2 page(s)
| | CEC/Ringer | Dept. Of Toxic Substances Control/Moskat |
13838 | 3/8/2000 |
Contra Costa AFC Transmittal.
1 page(s)
| | Bay Area Aqmd/Wocasek | CEC/Mckinney |
13776 | 3/2/2000 |
DTSC Review of California Energy Commission Siting Project
1 page(s)
| | No. Calif. Coastal Cleanup Operations Bra | CEC/Mckinney |
13775 | 3/2/2000 |
Request to Loan AFC
1 page(s)
| | Adams Broadwell Joseph & Cardozo/Joseph | CEC/Mckinney |
13757 | 2/29/2000 |
Data Adequacy Recommendation for the Contra Costa Power Plant Unit 8 Project.
66 page(s)
| | CEC/Keese/moore/laurie/pernell | CEC/Smith |
13744 | 2/29/2000 |
Phase II Environmental Site Assessment (Volumes I, II and III) (Dated June 1998)
1775 page(s)
| | CEC/Docket | Livingston & Mattesich/Varanini |
13708 | 2/23/2000 |
Project Description
2 page(s)
| | Member Of The Assembly/Hon. Tom Torlakson | CEC/Keese |
13707 | 2/11/2000 |
Notice of Receipt of the Application for Certification for the Contra Costa Power Plant Unit 8 Power Project
3 page(s)
| | CEC/Docket | CEC/Therkelsen |
13702 | 2/23/2000 |
Project Description
2 page(s)
| | Member Of The Senate/Hon. Richard Rainey | CEC/Keese |
13618 | 2/15/2000 |
Loan Letter - Mailed 2/15/00
1 page(s)
| | Calpine Corp./Strachen | CEC/Jim Mckinney |
13611 | 2/14/2000 |
Letter regarding Project Description and CEC Environmental Review Process
2 page(s)
| | Contra Costa Co. Board Of Supervisors/Canciamilla | CEC/Therkelsen |
13593 | 2/11/2000 |
Petition to Intervene by Calpine Corporation and Bechtel Enterprises, Inc. (Attachment: Proof of Service)
3 page(s)
| | CEC/Docket | Ellison & Schneider//ellison/harris |
13581 | 2/10/2000 |
Document Handling
1 page(s)
| | Librarian | CEC/Therkelsen |
13580 | 2/10/2000 |
DTSC Review of CEC Siting Projects
1 page(s)
| | Office Of Environmental Analysis Reg./Moskat | CEC/Ringer |
13577 | 2/10/2000 |
Air Quality Potential Offsets, and Paleontological Report for Confidentiality
5 page(s)
| | Livingston & Mattesich/Varanini | CEC/Smith |
13573 | 2/9/2000 |
Request for Agency Participation
3 page(s)
| | Agency Distribution List | CEC/Therkelsen |
13449 | 1/31/2000 |
Submittial letter for Application for Confidential Designation
6 page(s)
| | CEC/Docket | Livingston & Mattesich/Varanini |
13435 | 1/31/2000 |
Submittal letter for the AFC
3 page(s)
| | CEC/Smith | Southern Company/Hayes |
1519-0 | 6/4/2001 |
Committee Conference
36 page(s)
| | | CEC |
1517-0 | 6/4/2001 |
Committee Conference
36 page(s)
| | | CEC |
1504-0 | 5/7/2001 |
Evidentiary Hearing
141 page(s)
| | | CEC |
1494-0 | 4/5/2001 |
Committee Workshop
121 page(s)
| | | CEC |
1493-0 | 4/5/2001 |
Prehearing Conference and Workshop
54 page(s)
| | | CEC |
1489-0 | 4/2/2001 |
Committee Workshop
149 page(s)
| | | CEC |
1361-0 | 6/19/2000 |
Informational Hearing and Site Visit
81 page(s)
| | | CEC |